Fleischmann Construction Co. v. United States Ex Rel. Forsberg

270 U.S. 349, 46 S. Ct. 284, 70 L. Ed. 624, 1926 U.S. LEXIS 415
CourtSupreme Court of the United States
DecidedMarch 1, 1926
Docket50
StatusPublished
Cited by226 cases

This text of 270 U.S. 349 (Fleischmann Construction Co. v. United States Ex Rel. Forsberg) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fleischmann Construction Co. v. United States Ex Rel. Forsberg, 270 U.S. 349, 46 S. Ct. 284, 70 L. Ed. 624, 1926 U.S. LEXIS 415 (1926).

Opinion

Mr. Justice Sanford

delivered the opinion of the Court.

This is a suit under the Materialmen’s Act of 1894, 28 Stat. 278, c. 280, as amended by the Act of 1905, c. 778. 1 It was brought in the name of the United States by Forsberg, a materialman, as use plaintiff, in the federal district court for Eastern Virginia, to recover on a bond given by the Fleischmann Construction Company, as contractor, and the National Surety Company, as surety, for the construction, under a contract with the United States, of a torpedo assembly plant in Alexandria. Various materialmen and subcontractors filed intervening petitions in the suit. The plaintiff and the intervenors recovered judgment, 298 Fed. 320, which was affirmed by the Circuit Court of Appeals, 298 Fed. 330. This writ of error was allowed in'March, 1924. A motion was interposed to dismiss the writ of error upon the ground that the record presents no question properly reviewable by this Court, or to affirm the judgment; the consideration of which was postponed to the hearing on the merits.

The Materialmen’s Act, as amended, 1 provides, that the usual penal bond required of anyone entering into a contract with the United States for the construction of any *352 public work, ■ shall* contain an additional' obligation for •the payment by the contractor of all persons supplying labor.and materials in the prosecution of the work. Any such person not thus paid may intervene in any action instituted by the Unitéd States on the bond arid obtain judgment pro rata with other intervenors, subject to the priority of the claim of the United States. If no suit is brought by the United States “within six months from the completion .and final settlement” of the'contract, any such ^person shall have, a right of action upon-the bond, and may, “within one year after the performance and final settlement ” of the contract, but not later, commence suit against.the contractor.and his sureties, in the name of the United States, for his use and benefit, in the federal court of the district in which the contract was performed, .and prosecute the same to final judgment and execution. Where suitis so instituted by a creditor or by creditors, only one action shall be brought; and any creditor may 'file his claim in such action.''and be made party thereto within one year from the completion of the work under said contract, and not later.” If. the recovery, on the bond is inadequate to pay the amounts due to all of the creditors, judgment. shall be given to each pro rata '.

The first question to be determined is whether any of the matters presented by the assignment of errors — which relate chiefly to the times at which- the suit was brought and the intervening petitions - filed — are now open to review upqn the record.

Shortly outlined, the proceedings in the case were these: The suit was brought by Forsberg on April 6,1921. The declaration alleged that the Construction Company entered into a contract with the United States for the construction of the plant and gave bond to secure its performance, in October, 1918; and that this contract “was completed and final,settlement had on” September 25, 1920, “ more than six months and within one year before ” *353 the filing of the suit. The intervening petitions, which' were filed between June 15 and September 24, 1-921, contained substantially the same general averments as the declaration, and alleged further that they were filed “ before the expiration of one year after the completion” of the contract. In December, 1921, the plaintiff, by leave of court, amended the declaration so as to allege that the original contract, had been amended by a supplemental contract in May, 1919, and the defendants had thereafter executed .an additional bond; and that the contract as amended “ was completed and final- settlement had ” on September 25, 1920. The intervening petitions were likewise amended so as to incorporate substantially these same averments, and allege further that the petitions were filed “before the expiration of one year after the 'completion of said original contract as amended.”

The defendants filed demurrers to the original and amended declaration and petitions. All of these were overruled. And the amended declaration and petitions were then put at issue under pleas filed by the defendants.

By agreement of all the parties the case was .referred to a special master to hear the evidence and find the facts. In his report, he found that, the work was completed February. 5, 1920, and that the date of final settlement wai October 1, 1920.

Thereafter, in April, 1923, before action had been taken on this report, the parties filed a written stipulation, under § 649 of the Revised Statutes, waiving'a jury and agreeing that all the issues might be tried and determined by' the court.

In August, the District Judge handed down an extended written opinion in which he considered the entire case as to the facts and law, and concluded, inter alia, that the master had found correctly that the date of the final settlement was October 1, 1920;.that it was unnecessary to determine the date on which the work had been com *354 pleted, since the intervenors had filed their petitions within one year after the final settlement; that the actions were not barred because the amendments setting up the supplemental contract were made more than a year after the final settlement, the original and supplemental contracts being one and the same, and the amendments relating back to the bringing of the original suit and the filing of the original petition; and that the claims of the plaintiff and the intervenors were severally established. No special findings of fact had been requested; and none were made.

On the same day a judgment was entered,, which for reasons stated ” in the opinion, awarded the plaintiff and the intervenors recoveries upon their several claims, the aggregate of which was less than the amount of either bond.

The defendants, without having excepted to any of the rulings or conclusions of the court or requested any special findings of fact, sued out, in September, a writ of error from the Circuit Coúrt of Appeals. After this writ had issued, however, the District Judge, in October, granted them a bill of exceptions,” which recited that the court had filed its opinion and entered its final judgment on the same day, without notice to the parties; set forth various exceptions then, for the first time, noted by the defendants “to the rulings, findings of fact and conclusions of law by the, court” in the opinion and judgment; and stated that, by reason of the circumstances, these exceptions were “ to be taken as severally made at the'time thereof and before the entry of judgment thereon.” And later the District Judge granted them another “ bill of exceptions,” embodying the evidence and the proceedings before the master, and setting forth in the saíne manner other- exceptions to be taken, for like reason, as made before, the entry of the judgment.

The Circuit Court of Appeals disposed of the case in a per curiam

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dodd v. United States
545 U.S. 353 (Supreme Court, 2005)
Virginia Lomas v. State
Court of Appeals of Texas, 2000
Hunter Mfg. Corp. v. Commissioner
21 T.C. 424 (U.S. Tax Court, 1953)
Central-Penn Nat. Bank of Philadelphia v. Portner
201 F.2d 607 (Third Circuit, 1953)
Lambur v. Yates
148 F.2d 137 (Eighth Circuit, 1945)
United States Ex Rel. Mutual Metal Mfg. Co. v. Biggs
46 F. Supp. 8 (E.D. Illinois, 1942)
Alexander Thomson, Inc. v. B. Perini & Sons, Inc.
10 Conn. Super. Ct. 38 (Connecticut Superior Court, 1941)
Mosley v. Magnolia Petroleum Co.
114 P.2d 740 (New Mexico Supreme Court, 1941)
Maryland Casualty Co. v. Fidelity & Casualty Co.
147 S.W.2d 1097 (Court of Appeals of Texas, 1941)
United States v. Havner
101 F.2d 161 (Eighth Circuit, 1939)
Mutual Benefit Health & Accident Ass'n v. Bowman
99 F.2d 856 (Eighth Circuit, 1938)
Barry v. Hall
98 F.2d 222 (D.C. Circuit, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
270 U.S. 349, 46 S. Ct. 284, 70 L. Ed. 624, 1926 U.S. LEXIS 415, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fleischmann-construction-co-v-united-states-ex-rel-forsberg-scotus-1926.