MJM Landscaping, Inc. v. Lorant

845 A.2d 382, 268 Conn. 429, 2004 Conn. LEXIS 153
CourtSupreme Court of Connecticut
DecidedApril 13, 2004
DocketSC 17023
StatusPublished
Cited by14 cases

This text of 845 A.2d 382 (MJM Landscaping, Inc. v. Lorant) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MJM Landscaping, Inc. v. Lorant, 845 A.2d 382, 268 Conn. 429, 2004 Conn. LEXIS 153 (Colo. 2004).

Opinion

Opinion

PALMER, J.

The dispositive issue raised by this appeal is whether a written agreement (agreement) entered into by the plaintiff, MJM Landscaping, Inc., and the named defendant, Paul R. Lorant,1 is subject to the requirements of the Home Improvement Act (act), General Statutes § 20-418 et seq. The plaintiff initiated this action seeking strict foreclosure of a mechanic’s lien that was filed in connection with the defendant’s failure to pay in full for a septic system that the plaintiff [431]*431had constructed and installed on the defendant’s property. The defendant acknowledged that he had failed to pay the plaintiff in accordance with the agreement, but claimed, by way of special defense, that the agreement is unenforceable because it does not comply with the act, in particular, General Statutes § 20-429 (a).2 The defendant also filed a counterclaim alleging, inter alia, that the plaintiffs failure to comply with the act constituted a violation of the Connecticut Unfair Trade Practices Act (CUTPA), General Statutes § 42-110a et seq.3 The case was tried to the court, which concluded that the agreement is not a home improvement contract within the meaning of the act and, therefore, not governed by the act because the plaintiff was acting as a subcontractor rather than a home improvement contractor when it constructed and installed the septic system. In accordance with this conclusion, the court rendered judgment for the plaintiff both on its complaint and on the defendant’s counterclaim.4 On [432]*432appeal,5 the defendant challenges the conclusion of the trial court that the agreement falls outside the purview of the act. We reject the defendant’s claim and, consequently, affirm the judgment of the trial court.6

The evidence adduced at trial revealed the following relevant facts. In 1992, the defendant, a resident of Japan, purchased residential property located at 43 West Brother Drive in Greenwich for investment purposes. In 1998, a departing tenant informed the defendant that there was a problem with the property’s septic system. Upon the recommendation of a real estate broker with whom the defendant previously had done business, the defendant retained an engineer to design a new septic system.

The defendant subsequently hired Greenwich Design and Build, LLC7 (Greenwich Design) to supervise the construction of the new septic system. To ensure that there was no misunderstanding as to what he expected of Greenwich Design, the defendant prepared and transmitted to Greenwich Design a document entitled “Engineering Consultant: Request For Cost Estimate.” That document states that the defendant was retaining Greenwich Design in connection with the “[c]onstruction and installation of a new septic system for the property,” and lists Greenwich Design’s job specifica[433]*433tions as: (1) “[selection of one septic system construction and installation company . . . based on review of alternate cost estimate submissions from respective companies”; (2) “[o]n-going direction and monitoring of actual construction work to insure that the optimum quality new septic system is installed at the property”; and (3) “[o]n-going reporting of the work progress as appropriate . . . .” Thereafter, the defendant urged Greenwich Design to proceed as quickly as possible, describing the nature of the project as “urgent.” Nevertheless, the defendant and Greenwich Design never executed a written contract.

Greenwich Design solicited bids from a number of companies for the construction and installation of the septic system. As part of this process, Adam Ross of Greenwich Design, and Rene Bastías, a site engineer and principal of the plaintiff, met at the property to review the design plan for the septic system. The plaintiff subsequently prepared a handwritten proposal for Greenwich Design providing for the construction and installation of the septic system at a price of $58,000. Ross asked Bastías to forward a typed version of the proposal to the defendant in Japan so that the defendant could review and execute it, and Bastías did so.8 This proposal contained a list of services that the plaintiff had agreed to provide, a list of exclusions and a price of $58,000. The proposal did not contain a notice of cancellation provision and did not specify either a starting date or a completion date for the project.9 The defendant executed the proposal and sent $29,000 to the plaintiff via wire transfer. This executed proposal is the agreement that the plaintiff seeks to enforce and that the defendant claims is in violation of the act.

[434]*434Shortly thereafter, the plaintiff obtained a construction permit from the town of Greenwich and, on August 25, 1998, began work on the project. The defendant repeatedly underscored his desire to have the project completed as expeditiously as possible. Greenwich Design supervised the plaintiffs work throughout the duration of the project, and a representative of Greenwich Design was present at the project site every day. Nevertheless, the defendant communicated directly with the plaintiff when he had questions or concerns regarding the project. At the same time that the plaintiff was constructing and installing the septic system, other tradesmen, including electricians, plumbers and carpenters, also were performing work inside the residence. Greenwich Design supervised that work as well.

Upon completion of the project,10 Greenwich Design instructed the plaintiff to send a final bill directly to the defendant, and the plaintiff did so. In response, the defendant sent a facsimile to Greenwich Design and the plaintiff requesting certain information, including a use permit from the town of Greenwich, and “one comprehensive invoice” for services rendered by Greenwich Design and the plaintiff. In that facsimile, however, the defendant expressly acknowledged that he had paid only one half of the agreed upon price for the septic system. The facsimile further advised Greenwich Design and the plaintiff to “rest assured that [they would] receive [their] respective due payments.”

The defendant failed, however, to remit any additional payments to the plaintiff.11 As a result, the plaintiff filed a mechanic’s lien on the defendant’s property and subsequently commenced this action for strict foreclosure of the lien. The defendant raised a special defense [435]*435alleging that the agreement constituted a home improvement contract subject to the requirements of the act and that, consequently, the agreement was unenforceable because it did not specify a starting date or a completion date, and did not contain a notice of cancellation provision, all of which are required under § 20-429 (a). In addition, the defendant filed a counterclaim alleging, inter alia, that the plaintiffs violation of the act constituted a violation of CUTPA. The trial court rejected the defendant’s special defense and counterclaim, concluding that the agreement is not governed by the act because the plaintiff was acting as a subcontractor rather than a home improvement contractor when it constructed and installed the septic system. In accordance with this conclusion, the trial court rendered judgment for the plaintiff on its complaint and on the defendant’s counterclaim. This appeal followed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Probate Appeal of Barbera
Connecticut Appellate Court, 2025
Krausman v. Liberty Mutual Ins. Co.
236 Conn. App. 109 (Connecticut Appellate Court, 2025)
White v. Latimer Point Condominium Assn., Inc.
Connecticut Appellate Court, 2019
In re Champlain Oil Company Conditional Use Application
2014 VT 19 (Supreme Court of Vermont, 2014)
PROBUILD EAST, LLC v. Poffenberger
45 A.3d 654 (Connecticut Appellate Court, 2012)
McBurney v. Paquin
28 A.3d 272 (Supreme Court of Connecticut, 2011)
ANDY'S OIL SERVICE, INC. v. Hobbs
9 A.3d 433 (Connecticut Appellate Court, 2010)
Meagher v. DIACRI
3 A.3d 120 (Connecticut Appellate Court, 2010)
Bahjat v. Dadi
1 A.3d 212 (Connecticut Appellate Court, 2010)
Taylor v. King
994 A.2d 330 (Connecticut Appellate Court, 2010)
Hees v. Burke Construction Inc.
961 A.2d 373 (Supreme Court of Connecticut, 2009)
Lowe v. City of Shelton
851 A.2d 1183 (Connecticut Appellate Court, 2004)
Nationwide Mutual Insurance v. Allen
850 A.2d 1047 (Connecticut Appellate Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
845 A.2d 382, 268 Conn. 429, 2004 Conn. LEXIS 153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mjm-landscaping-inc-v-lorant-conn-2004.