PROBUILD EAST, LLC v. Poffenberger

45 A.3d 654, 136 Conn. App. 184, 2012 WL 1990566, 2012 Conn. App. LEXIS 273
CourtConnecticut Appellate Court
DecidedJune 12, 2012
DocketAC 32996
StatusPublished
Cited by6 cases

This text of 45 A.3d 654 (PROBUILD EAST, LLC v. Poffenberger) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PROBUILD EAST, LLC v. Poffenberger, 45 A.3d 654, 136 Conn. App. 184, 2012 WL 1990566, 2012 Conn. App. LEXIS 273 (Colo. Ct. App. 2012).

Opinion

*186 Opinion

GRUENDEL, J.

The defendant, Adrian C. Poffenb-erger, appeals from the judgment of the trial court in favor of the plaintiff, ProBuild East, LLC. The defendant claims that the court improperly determined that (1) the plaintiffs mechanic’s lien was valid in accordance with General Statutes § 49-34, (2) alienable fund existed where the general contractor was paid the contract price in full and (3) a lienable fund existed where the contract between the defendant and the general contractor did not comply with the Home Improvement Act (act), General Statutes § 20-418 et seq. We affirm the judgment of the trial court.

The relevant facts, as found by the court, are as follows. In 2008, the defendant entered into a contract with DJ Flanagan Builders, LLC (Flanagan Builders), to renovate his property in Milford. The initial price was $94,000, but as the work progressed there were various modifications that resulted in increases to the price. On September 23, 2009, Flanagan Builders entered into a contract with the plaintiff, formerly known as Strober Building Supply, LLC, 1 to provide supplies and materials for the project. The plaintiff delivered various materials to Flanagan Builders in January and February, 2009. On May 4, 2009, the plaintiff filed a certificate of mechanic’s hen dated April 28, 2009. The certificate was sworn and subscribed to by Alexander Pilagin, the credit manager for the plaintiff. The lien claimed that the plaintiff furnished materials and rendered services in the construction of a building on property owned by the defendant in Milford. The lien claimed that materials and services were furnished from January 8 to February 24, 2009, and the value of the materials and services totaled $15,276.47. A notice *187 of lis pendens thereafter was recorded on the Milford land records.

Thereafter, the plaintiff filed its complaint seeking foreclosure of the hen. The defendant filed an answer, asserting two special defenses. The defendant claimed that the plaintiffs hen was invalid, first, because the defendant paid Flanagan Builders the full amount of the original contract price and, second, because Pilagin had no personal knowledge of the materials purportedly provided by the plaintiff.

The matter was tried to the court. In its memorandum of decision, the court first determined that the hen was not invalidated by an incorrect commencement date on the certificate because the error was not made in bad faith and did not harm the defendant. Turning to the defendant’s arguments about the lack of a henable fund, the court concluded that a henable fund did exist because the defendant still owed Flanagan Builders $10,800. The court then determined that the fact that the underlying contract between the defendant and Flanagan Builders did not comply with the act did not invalidate the hen. It further concluded that the hen should be enforced in the reduced amount of $10,800. Thereafter, the plaintiff filed a motion for a judgment of strict foreclosure. The court rendered a judgment of foreclosure by sale, setting a sale date of January 29, 2011. This appeal followed.

Before turning to the defendant’s claims, we note the apphcable standard of review. “On appeal, it is the function of this court to determine whether the decision of the trial court is clearly erroneous. . . . This involves a two part function: where the legal conclusions of the court are challenged, we must determine whether they are legally and logically correct and whether they find support in the facts set out in the memorandum of decision; where the factual basis of *188 the court’s decision is challenged we must determine whether the facts set out in the memorandum of decision are supported by the evidence or whether, in light of the evidence and the pleadings in the whole record, those facts are clearly erroneous. That is the standard and scope of this court’s judicial review of decisions of the trial court. Beyond that, we will not go. ... A finding of fact is clearly erroneous when there is no evidence in the record to support it ... or when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and fiim conviction that a mistake has been committed.” (Citation omitted; internal quotation marks omitted.) Rollar Construction & Demolition, Inc. v. Granite Rock Associates, LLC, 94 Conn. App. 125, 130, 891 A.2d 133 (2006).

I

The defendant argues that the court erred in finding that the plaintiffs mechanic’s lien is valid under § 49-34 2 despite the incorrect commencement date listed on the certificate. 3 Specifically, the defendant challenges *189 the court’s factual finding that the defendant was not harmed by the inclusion of an incorrect commencement date, and the lien was therefore not invalid for failing to comply with § 49-34. We disagree.

Section 49-34 sets forth the required contents of a certificate of mechanic’s lien. Among the requisites is that the certificate state “the date of the commencement of the performance of services or furnishing of materials . . . .” The commencement date, and not the filing date, establishes the lienor’s priority as against other claimants. General Statutes § 49-33 (b); see also New England Savings Bank v. Meadow Lakes Realty Co., 243 Conn. 601, 616, 706 A.2d 465 (1998).

“We have long endorsed a policy favoring liberal construction of claimed inadequacies in certificates of mechanics’ liens in order to achieve the remedial purposes of the mechanics’ hen statutes. ... In accordance with this policy, our courts have been liberal in validating hens despite claimed errors on the face of the hen certificate where the mistake was made in good faith and no resulting prejudice was claimed.” J. C. Penney Properties, Inc. v. Peter M. Santella Co., 210 Conn. 511, 514-15, 555 A.2d 990 (1989). “As we have reasoned many times, we do not think a court of equity can be called upon to declare [a] hen utterly void upon the motion of persons who have lost nothing by [the] mistake. . . . Therefore, [wjhere the misstatement of *190 the claim is intentional, that is, where the statement of the claim is intentionally false, or where it is fraudulent, the hen will be void; but where it is the result of a mistake, the misstatement of the claim will not invalidate the lien.” (Citation omitted; internal quotation marks omitted.) First Constitution Bank v. Harbor Village Ltd. Partnership, 230 Conn. 807, 816, 646 A.2d 812 (1994).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pittu v. Bugaj Contractors Co., LLC
234 Conn. App. 28 (Connecticut Appellate Court, 2025)
Strazza Building & Construction, Inc. v. Harris
207 Conn. App. 649 (Connecticut Appellate Court, 2021)
Morison v. Hannaford Bros. Co.
Maine Superior, 2014
Absolute Plumbing & Heating, LLC v. Edelman
77 A.3d 889 (Connecticut Appellate Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
45 A.3d 654, 136 Conn. App. 184, 2012 WL 1990566, 2012 Conn. App. LEXIS 273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/probuild-east-llc-v-poffenberger-connappct-2012.