Opinion
GRUENDEL, J.
The defendant, Adrian C. Poffenb-erger, appeals from the judgment of the trial court in favor of the plaintiff, ProBuild East, LLC. The defendant claims that the court improperly determined that (1) the plaintiffs mechanic’s lien was valid in accordance with General Statutes § 49-34, (2) alienable fund existed where the general contractor was paid the contract price in full and (3) a lienable fund existed where the contract between the defendant and the general contractor did not comply with the Home Improvement Act (act), General Statutes § 20-418 et seq. We affirm the judgment of the trial court.
The relevant facts, as found by the court, are as follows. In 2008, the defendant entered into a contract with DJ Flanagan Builders, LLC (Flanagan Builders), to renovate his property in Milford. The initial price was $94,000, but as the work progressed there were various modifications that resulted in increases to the price. On September 23, 2009, Flanagan Builders entered into a contract with the plaintiff, formerly known as Strober Building Supply, LLC,
to provide supplies and materials for the project. The plaintiff delivered various materials to Flanagan Builders in January and February, 2009. On May 4, 2009, the plaintiff filed a certificate of mechanic’s hen dated April 28, 2009. The certificate was sworn and subscribed to by Alexander Pilagin, the credit manager for the plaintiff. The lien claimed that the plaintiff furnished materials and rendered services in the construction of a building on property owned by the defendant in Milford. The lien claimed that materials and services were furnished from January 8 to February 24, 2009, and the value of the materials and services totaled $15,276.47. A notice
of lis pendens thereafter was recorded on the Milford land records.
Thereafter, the plaintiff filed its complaint seeking foreclosure of the hen. The defendant filed an answer, asserting two special defenses. The defendant claimed that the plaintiffs hen was invalid, first, because the defendant paid Flanagan Builders the full amount of the original contract price and, second, because Pilagin had no personal knowledge of the materials purportedly provided by the plaintiff.
The matter was tried to the court. In its memorandum of decision, the court first determined that the hen was not invalidated by an incorrect commencement date on the certificate because the error was not made in bad faith and did not harm the defendant. Turning to the defendant’s arguments about the lack of a henable fund, the court concluded that a henable fund did exist because the defendant still owed Flanagan Builders $10,800. The court then determined that the fact that the underlying contract between the defendant and Flanagan Builders did not comply with the act did not invalidate the hen. It further concluded that the hen should be enforced in the reduced amount of $10,800. Thereafter, the plaintiff filed a motion for a judgment of strict foreclosure. The court rendered a judgment of foreclosure by sale, setting a sale date of January 29, 2011. This appeal followed.
Before turning to the defendant’s claims, we note the apphcable standard of review. “On appeal, it is the function of this court to determine whether the decision of the trial court is clearly erroneous. . . . This involves a two part function: where the legal conclusions of the court are challenged, we must determine whether they are legally and logically correct and whether they find support in the facts set out in the memorandum of decision; where the factual basis of
the court’s decision is challenged we must determine whether the facts set out in the memorandum of decision are supported by the evidence or whether, in light of the evidence and the pleadings in the whole record, those facts are clearly erroneous. That is the standard and scope of this court’s judicial review of decisions of the trial court. Beyond that, we will not go. ... A finding of fact is clearly erroneous when there is no evidence in the record to support it ... or when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and fiim conviction that a mistake has been committed.” (Citation omitted; internal quotation marks omitted.)
Rollar Construction & Demolition, Inc.
v.
Granite Rock Associates, LLC,
94 Conn. App. 125, 130, 891 A.2d 133 (2006).
I
The defendant argues that the court erred in finding that the plaintiffs mechanic’s lien is valid under § 49-34
despite the incorrect commencement date listed on the certificate.
Specifically, the defendant challenges
the court’s factual finding that the defendant was not harmed by the inclusion of an incorrect commencement date, and the lien was therefore not invalid for failing to comply with § 49-34. We disagree.
Section 49-34 sets forth the required contents of a certificate of mechanic’s lien. Among the requisites is that the certificate state “the date of the commencement of the performance of services or furnishing of materials . . . .” The commencement date, and not the filing date, establishes the lienor’s priority as against other claimants. General Statutes § 49-33 (b); see also
New England Savings Bank
v.
Meadow Lakes Realty Co.,
243 Conn. 601, 616, 706 A.2d 465 (1998).
“We have long endorsed a policy favoring liberal construction of claimed inadequacies in certificates of mechanics’ liens in order to achieve the remedial purposes of the mechanics’ hen statutes. ... In accordance with this policy, our courts have been liberal in validating hens despite claimed errors on the face of the hen certificate where the mistake was made in good faith and no resulting prejudice was claimed.”
J. C. Penney Properties, Inc.
v.
Peter M. Santella Co.,
210 Conn. 511, 514-15, 555 A.2d 990 (1989). “As we have reasoned many times, we do not think a court of equity can be called upon to declare [a] hen utterly void upon the motion of persons who have lost nothing by [the] mistake. . . . Therefore, [wjhere the misstatement of
the claim is intentional, that is, where the statement of the claim is intentionally false, or where it is fraudulent, the hen will be void; but where it is the result of a mistake, the misstatement of the claim will not invalidate the lien.” (Citation omitted; internal quotation marks omitted.)
First Constitution Bank
v.
Harbor Village Ltd. Partnership,
230 Conn. 807, 816, 646 A.2d 812 (1994).
Free access — add to your briefcase to read the full text and ask questions with AI
Opinion
GRUENDEL, J.
The defendant, Adrian C. Poffenb-erger, appeals from the judgment of the trial court in favor of the plaintiff, ProBuild East, LLC. The defendant claims that the court improperly determined that (1) the plaintiffs mechanic’s lien was valid in accordance with General Statutes § 49-34, (2) alienable fund existed where the general contractor was paid the contract price in full and (3) a lienable fund existed where the contract between the defendant and the general contractor did not comply with the Home Improvement Act (act), General Statutes § 20-418 et seq. We affirm the judgment of the trial court.
The relevant facts, as found by the court, are as follows. In 2008, the defendant entered into a contract with DJ Flanagan Builders, LLC (Flanagan Builders), to renovate his property in Milford. The initial price was $94,000, but as the work progressed there were various modifications that resulted in increases to the price. On September 23, 2009, Flanagan Builders entered into a contract with the plaintiff, formerly known as Strober Building Supply, LLC,
to provide supplies and materials for the project. The plaintiff delivered various materials to Flanagan Builders in January and February, 2009. On May 4, 2009, the plaintiff filed a certificate of mechanic’s hen dated April 28, 2009. The certificate was sworn and subscribed to by Alexander Pilagin, the credit manager for the plaintiff. The lien claimed that the plaintiff furnished materials and rendered services in the construction of a building on property owned by the defendant in Milford. The lien claimed that materials and services were furnished from January 8 to February 24, 2009, and the value of the materials and services totaled $15,276.47. A notice
of lis pendens thereafter was recorded on the Milford land records.
Thereafter, the plaintiff filed its complaint seeking foreclosure of the hen. The defendant filed an answer, asserting two special defenses. The defendant claimed that the plaintiffs hen was invalid, first, because the defendant paid Flanagan Builders the full amount of the original contract price and, second, because Pilagin had no personal knowledge of the materials purportedly provided by the plaintiff.
The matter was tried to the court. In its memorandum of decision, the court first determined that the hen was not invalidated by an incorrect commencement date on the certificate because the error was not made in bad faith and did not harm the defendant. Turning to the defendant’s arguments about the lack of a henable fund, the court concluded that a henable fund did exist because the defendant still owed Flanagan Builders $10,800. The court then determined that the fact that the underlying contract between the defendant and Flanagan Builders did not comply with the act did not invalidate the hen. It further concluded that the hen should be enforced in the reduced amount of $10,800. Thereafter, the plaintiff filed a motion for a judgment of strict foreclosure. The court rendered a judgment of foreclosure by sale, setting a sale date of January 29, 2011. This appeal followed.
Before turning to the defendant’s claims, we note the apphcable standard of review. “On appeal, it is the function of this court to determine whether the decision of the trial court is clearly erroneous. . . . This involves a two part function: where the legal conclusions of the court are challenged, we must determine whether they are legally and logically correct and whether they find support in the facts set out in the memorandum of decision; where the factual basis of
the court’s decision is challenged we must determine whether the facts set out in the memorandum of decision are supported by the evidence or whether, in light of the evidence and the pleadings in the whole record, those facts are clearly erroneous. That is the standard and scope of this court’s judicial review of decisions of the trial court. Beyond that, we will not go. ... A finding of fact is clearly erroneous when there is no evidence in the record to support it ... or when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and fiim conviction that a mistake has been committed.” (Citation omitted; internal quotation marks omitted.)
Rollar Construction & Demolition, Inc.
v.
Granite Rock Associates, LLC,
94 Conn. App. 125, 130, 891 A.2d 133 (2006).
I
The defendant argues that the court erred in finding that the plaintiffs mechanic’s lien is valid under § 49-34
despite the incorrect commencement date listed on the certificate.
Specifically, the defendant challenges
the court’s factual finding that the defendant was not harmed by the inclusion of an incorrect commencement date, and the lien was therefore not invalid for failing to comply with § 49-34. We disagree.
Section 49-34 sets forth the required contents of a certificate of mechanic’s lien. Among the requisites is that the certificate state “the date of the commencement of the performance of services or furnishing of materials . . . .” The commencement date, and not the filing date, establishes the lienor’s priority as against other claimants. General Statutes § 49-33 (b); see also
New England Savings Bank
v.
Meadow Lakes Realty Co.,
243 Conn. 601, 616, 706 A.2d 465 (1998).
“We have long endorsed a policy favoring liberal construction of claimed inadequacies in certificates of mechanics’ liens in order to achieve the remedial purposes of the mechanics’ hen statutes. ... In accordance with this policy, our courts have been liberal in validating hens despite claimed errors on the face of the hen certificate where the mistake was made in good faith and no resulting prejudice was claimed.”
J. C. Penney Properties, Inc.
v.
Peter M. Santella Co.,
210 Conn. 511, 514-15, 555 A.2d 990 (1989). “As we have reasoned many times, we do not think a court of equity can be called upon to declare [a] hen utterly void upon the motion of persons who have lost nothing by [the] mistake. . . . Therefore, [wjhere the misstatement of
the claim is intentional, that is, where the statement of the claim is intentionally false, or where it is fraudulent, the hen will be void; but where it is the result of a mistake, the misstatement of the claim will not invalidate the lien.” (Citation omitted; internal quotation marks omitted.)
First Constitution Bank
v.
Harbor Village Ltd. Partnership,
230 Conn. 807, 816, 646 A.2d 812 (1994).
The court noted that Dennis J. Flanagan, the operator of Flanagan Builders, testified that he began to use materials provided by the plaintiff in October, 2008. The hen certificate stated a commencement date of January 8, 2009. The court found that there was no evidence indicating how the defendant was prejudiced by this error, nor was there evidence demonstrating a fraudulent intent. The record supports the court’s conclusion. Flanagan testified at trial that he began work at the defendant’s property in late September or early October, 2008, and that he began using materials from the plaintiff in the end of September or October, 2008. The invoices for these materials are dated from January 8 to February 24, 2009. The fact that the dates on the certificate correspond to the dates on the invoices support the court’s finding that the commencement date was not intentionally false or fraudulent. Upon our review of the record, there is no evidence to demonstrate a fraudulent intent in stating the commencement date as January 8, 2009. The court also found that the defendant failed to introduce any evidence or present any argument regarding how he was injured or prejudiced by the incorrect commencement date. “If neither deficiency exists, we express satisfaction that the statute has been substantially complied with and reject the argument that the hen should be invalidated.”
First Constitution Bank
v.
Harbor Village Ltd. Partnership,
supra, 230 Conn. 818. The court thus properly found that the hen was valid.
n
The defendant claims that the court’s factual finding that there was unpaid contract debt owed to Flanagan Builders by the defendant was improper given that the defendant paid Flanagan Builders the original contract price of $94,000. We disagree.
The statutory limitations on lienable funds as applicable to subcontractors are set forth in General Statutes §§ 49-33
and 49-36.
A subcontractor is subrogated to
the rights of the general contractor through whom he claims, such that a subcontractor only can enforce a mechanic’s lien to the extent that there is unpaid contract debt owed to the general contractor by the owner. See General Statutes § 49-33 (f); see also
Seaman
v.
Climate Control Corp.,
181 Conn. 592, 601-602, 436 A.2d 271 (1980). Sections 49-33 and 49-36 “define and delimit the fund to which a properly noticed mechanic’s hen may attach. Both of these sections start with the proposition that no mechanic’s lien may attach to any building or land in an amount greater than the price which the owner has agreed to pay the general contractor for the building being erected or improved. The amount may be diminished ... by bona fide payments, as defined in section 49-36, made by the owner . . . before receiving notice of [the mechanic’s] hen or hens.” (Citation omitted; internal quotation marks omitted.)
Rene Dry Wall Co.
v.
Strawberry Hill Associates,
182 Conn. 568, 571-72, 438 A.2d 774 (1980); see also
W. G. Glenney Co.
v.
Bianco,
27 Conn. App. 199, 205, 604 A.2d 1345 (1992).
The court found that the original contract price was $94,000 and that Flanagan Builders was paid that amount by the defendant. The court also found, however, that due to modifications to the plans made along the way, or “extras,” the price increased and the defendant still owed Flanagan Builders $10,800 for the project. These determinations find ample support in the
record, specifically Flanagan’s trial testimony. There was no conflicting testimony or evidence presented as to the existence or amount of the unpaid debt. In light of the foregoing, the court’s factual finding that the defendant still owed $10,800 under the general contract was not clearly erroneous.
The lienable fund is limited to “the unpaid contract debt owed by the owner to the general contractor.”
Seaman
v.
Climate Control Corp.,
supra, 181 Conn. 602. Because the court properly found that there was unpaid contract debt, a lienable fund exists. Accordingly, the defendant’s argument that the lien is invalid for lack of a lienable fund because he paid the original contract price must fail.
Ill
Finally, the defendant claims that the court improperly applied the statutes and case law regarding the subrogation of subcontractors’ claims. He claims that, because the underlying contract violates General Statutes § 20-429 (a),
it is unenforceable against him by Flanagan Builders and there is therefore no lienable fund from which the plaintiff can collect. We disagree.
The act is a consumer protection statute. Its purpose is “to promote understanding by the consumer, to ensure his ability to make an informed decision and to protect him from substantial work by an unscrupulous contractor.”
Habetz
v.
Condon,
224 Conn. 231, 239, 618 A.2d 501 (1992). The act requires that home improvement contractors register with the commissioner of consumer protection and that a home improvement contract include certain provisions to be valid and enforceable. General Statutes §§ 20-420 and 20-429. It also prohibits a home improvement contractor from enforcing any home improvement contract made with a homeowner that fails to adhere to the statutory requirements.
MJM Landscaping, Inc.
v.
Lorant,
268 Conn. 429, 435, 845 A.2d 382 (2004). Subcontractors do not fall within the statutory definition of home improvement contractor, and they are therefore not required to register nor are they required to enter into valid home improvement contracts.
Meadows
v.
Higgins,
249 Conn. 155, 165-68, 733 A.2d 172 (1999).
The court in the present case determined that it would be inequitable to subject the plaintiff to the terms of a contract to which it was not a party. It determined that the subrogation language of § 49-33 (f) was created solely for the purpose of protecting homeowners and should be interpreted to protect homeowners from double liability or liability beyond the contract price. The court concluded that, because the doctrine of subrogation is flexible, the subrogation language in § 49-33 (f) should not be interpreted to bar claims of subcontractors who were not involved in the formation of an invalid contract between the general contractor and the homeowner.
The court’s interpretation of § 49-33 (f) is an issue of law subject to plenary review.
Ceci Bros., Inc.
v.
Five Twenty-One Corp.,
51 Conn. App. 773, 776, 724 A.2d 541 (1999). Likewise, whether the act applies to
the facts of this case is a matter of statutory construction over which we exercise plenary review.
Meadows
v.
Higgins,
supra, 249 Conn. 162.
“[T]he guidelines for interpreting mechanic’s hen legislation are . . . weh established. Although the mechanic’s lien statute creates a statutory right in derogation of the common law ... its provisions should be liberally construed in order to implement its remedial purpose of furnishing security for one who provides services or materials. . . . Our interpretation, however, may not depart from reasonable compliance with the specific terms of the statute under the guise of a liberal construction.” (Internal quotation marks omitted.)
Rollar Construction & Demolition, Inc.
v.
Granite Rock Associates, LLC,
supra, 94 Conn. App. 129. “A subcontractor’s right to claim a hen against a property owner with whom he is not in privity was created because the subcontractor has furnished material or labor to or for the contractor which has gone into the owner’s building.” (Internal quotation marks omitted.)
H & S Torrington Associates
v.
Lutz Engineering Co.,
185 Conn. 549, 553, 441 A.2d 171 (1981).
Assuming without deciding that the defendant is correct in his assertion that the underlying contract does not meet the requirements of § 20-429 (a),
we do not agree that this is a bar to the plaintiffs right to recover against him under the mechanic’s hen statute. The defendant has provided no authority to support his proposition that when a general contractor’s hen is unenforceable for a lack of compliance with the act, the subcontractor’s hen also is unenforceable. Indeed, our trial courts consistently have rejected the proposition. See, e.g.,
White
v.
Edwards,
Superior Court, judicial district of New Haven, Docket No. CV-00-0437477-S (June 9, 2000);
Fromm
v.
FAS Designer & Builders,
Inc.,
Superior Court, judicial district of Stamford-Norwalk, Docket No. CV-97-0160094-S (March 16, 1998) (21 Conn. L. Rptr. 494);
Fink
v.
Olson,
Superior Court, judicial district of Fairfield, Docket No. CV-96-0335948S (November 19, 1996) (18 Conn. L. Rptr 259);
Torre Builders
v.
Steven,
Superior Court, judicial district of Stamford-Norwalk, Docket No. CV-92-0121684-S (October 21, 1992) (7 Conn. L. Rptr. 491);
Baxter
v.
Quoka,
Superior Court, judicial district of Ansonia-Milford, Docket No. CV-90-031911-S (July 3, 1990) (1 Conn. L. Rptr. 817); see also D. Rosengren, 13 Connecticut Practice Series: Construction Law (2005) § 8.5, p. 175 (“[W]hen a construction contract is unenforceable due to a violation of [the act], any hen held by the contractor is invalid. However, any subcontractor holding a hen will still be able to enforce it, as [the act] does not apply to subcontractors, and the validity of a subcontractor’s hen will not be affected by the validity of a contractor’s hen.”). To hold otherwise would expand the subrogation language of § 49-33 and impute additional conditions on subcontractors’ hens. It would also be a de facto apphcation of the requirements of the act to subcontractors, a group clearly excluded from complying with the act. See
Meadows
v.
Higgins,
supra, 249 Conn. 165-68. There is nothing in either the mechanic’s hen statutes or the act to indicate that the legislature intended such a result.
The subrogation language of § 49-33 (f) certainly requires that subcontractors’ hens be invalidated where there is no unpaid contract debt owed to the general contractor from the owner.
Seaman
v.
Climate Control Corp.,
supra, 181 Conn. 601-602;
W. G. Glenney Co.
v.
Bianco,
supra, 27 Conn. App. 201. But where, as here, there is unpaid contract debt and the defendant asserts speculatively that the general contractor would be
unable to collect that debt because of a separate statutory regime that does not apply to subcontractors, sub-rogation principles are not a bar to the validity of the plaintiffs lien.
The judgment is affirmed and the case is remanded for the purpose of setting a new sale date.
In this opinion the other judges concurred.