Rollar Construction & Demolition, Inc. v. Granite Rock Associates, LLC

891 A.2d 133, 94 Conn. App. 125, 2006 Conn. App. LEXIS 101
CourtConnecticut Appellate Court
DecidedMarch 7, 2006
DocketAC 25705
StatusPublished
Cited by21 cases

This text of 891 A.2d 133 (Rollar Construction & Demolition, Inc. v. Granite Rock Associates, LLC) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rollar Construction & Demolition, Inc. v. Granite Rock Associates, LLC, 891 A.2d 133, 94 Conn. App. 125, 2006 Conn. App. LEXIS 101 (Colo. Ct. App. 2006).

Opinion

Opinion

DiPENTIMA, J.

This appeal arises from a battle of priority rights, in which the dispositive issue is whether the plaintiff, Rollar Construction & Demolition, Inc., properly recorded its mechanic’s lien as required to foreclose the hen against certain real property owned by the defendant Granite Rock Associates, LLC (Granite [127]*127Rock).1 The plaintiff appeals from the judgment of the trial court, rendered after a trial to the court, in which the court found the plaintiffs mechanic’s lien invalid. On appeal, the plaintiff claims that the court (1) improperly applied General Statutes §§ 49-33 and 49-34, and (2) used improper standards of proof.2 We disagree and, accordingly, affirm the judgment of the trial court.

The court found the following relevant facts. Granite Rock, a Connecticut limited liability company, was created for the purpose of operating a company that bottled spring water at 124 High Street in Haddam. On August 17, 1999, the company obtained title to that property in its “as is” condition. Soon after, Granite Rock sought a loan and, through an attorney, one of the owners agreed to pay to the order of defendants Walter Gretchyn and his mother, Mary Gretchyn, the amount of $300,000 by commercial term promissory note, dated February 7, 2000. The note was secured by a mortgage deed on the property.3

The mechanic’s lien at issue in this case is based on work performed pursuant to a contract dated January [128]*1285, 1998, between the plaintiff, a construction company, and Granite Rock. During the entire period of the contract, the plaintiff received no payment from Granite Rock for any of the work completed. On February 14, 2002, the plaintiff recorded the certificate of mechanic’s hen for the entire balance of $265,316.27 on the Haddam land records. The certificate stated that the plaintiff ceased furnishing services and materials on January 9, 2002.

The plaintiff subsequently filed the present action seeking to foreclose its mechanic’s lien and claiming, pursuant to § 49-33,4 that its lien was prior in right to both the Gretchyns’ mortgage and a mortgage to Victory State Bank.5 The court heard four days of testimony and rendered judgment in favor of the defendants, finding, inter alia, that the plaintiff had not complied with the requirements for the proper recording of a mechanic’s lien, as set forth in § 49-34.6 This appeal followed.

[129]*129We begin by noting that “in Connecticut, the mechanic’s lien is a creature of statute and gives a right of action which did not exist at common law. . . . The purpose of the mechanic’s lien is to give one who furnishes materials or services the security of the building and land for the payment of his claim by making such claim a lien thereon .... Moreover, [t]he guidelines for inteipreting mechanic’s lien legislation are . . . well established. Although the mechanic’s lien statute creates a statutory right in derogation of the common law ... its provisions should be liberally construed in order to implement its remedial purpose of furnishing security for one who provides services or materials. . . . Our interpretation, however, may not depart from reasonable compliance with the specific terms of the statute under the guise of a liberal construction.” (Citations omitted; internal quotation marks omitted.) F. B. Mattson Co. v. Tarte, 247 Conn. 234, 237-38, 719 A.2d 1158 (1998).

I

The plaintiff first argues that the court’s findings of fact regarding the ninety day requirement for filing a valid mechanic’s lien were clearly erroneous. We disagree.7

[130]*130Before addressing the merits of the plaintiffs first argument, we note the applicable standard of review. “On appeal, it is the function of this court to determine whether the decision of the trial court is clearly erroneous. . . . This involves a two part function: where the legal conclusions of the court are challenged, we must determine whether they are legally and logically correct and whether they find support in the facts set out in the memorandum of decision; where the factual basis of the court’s decision is challenged we must determine whether the facts set out in the memorandum of decision are supported by the evidence or whether, in light of the evidence and the pleadings in the whole record, those facts are clearly erroneous. That is the standard and scope of this court’s judicial review of decisions of the trial court. Beyond that, we will not go.” (Citation omitted.) Pandolphe’s Auto Parts, Inc. v. Manchester, 181 Conn. 217, 221-22, 435 A.2d 24 (1980). “A finding of fact is clearly erroneous when there is no evidence in the record to support it ... or when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.” (Internal quotation marks omitted.) United Components, Inc. v. Wdowiak, 239 Conn. 259, 263, 684 A.2d 693 (1996).

The court found that the plaintiffs mechanic’s lien was filed more than ninety days after work had ceased on the property and that therefore the lien was invalid. General Statutes § 49-34 provides in relevant part: “A mechanic’s lien is not valid unless the person performing the services or furnishing the materials . . . within ninety days after he has ceased to do so, lodges with the town clerk of the town in which the building, lot or plot of land is situated a certificate in writing . . . .” Applying the deferential standard of review, we conclude that the court’s finding that the mechanic’s [131]*131lien had not been filed within the statutory ninety day period was not clearly erroneous.

The plaintiff relies on documentary evidence and testimony to assert that the court’s finding is improper. The record discloses that, as the court found, the plaintiff filed the certificate of lien on February 14, 2002. The certificate lists January 9, 2002, as the date of completion of services rendered, materials furnished and repairs done on the property, which is clearly within ninety days of the date of filing. As evidence of the date of completion, the plaintiff submitted numerous invoices and receipts spanning the years 1998 to 2002. The photocopies of receipts, statements and invoices from various building supply companies and related services are dated from 1998 to 2000. The plaintiffs own invoices documenting work done for Granite Rock, on the other hand, extend until January 20, 2002. Robin Lewis French, the plaintiffs president, signed the certificate, but was unable to testify as to its specifics.8 Her [132]*132father, Walter Lewis, however, testified as to the accuracy of the invoices and the date of completion.9 In its memorandum of decision, the court stated that “Walter Lewis offered no documentation which specified the dates on which work was done on the property. Instead, he offered a series of invoices to ‘Granite Rock Associates’ with no address specified.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Herron v. Daniels
208 Conn. App. 75 (Connecticut Appellate Court, 2021)
Reinke v. Sing
201 A.3d 404 (Connecticut Appellate Court, 2018)
Papallo v. Lefebvre
161 A.3d 603 (Connecticut Appellate Court, 2017)
Marshall v. Marshall
Connecticut Appellate Court, 2014
CONSTRUCTION KEN-NECTION, INC. v. Cipriano
45 A.3d 663 (Connecticut Appellate Court, 2012)
PROBUILD EAST, LLC v. Poffenberger
45 A.3d 654 (Connecticut Appellate Court, 2012)
Cianci v. ORIGINALWERKS, LLC
16 A.3d 705 (Connecticut Appellate Court, 2011)
Kaczynski v. Kaczynski
981 A.2d 1068 (Supreme Court of Connecticut, 2009)
Testone v. C. R. Gibson Co.
969 A.2d 179 (Connecticut Appellate Court, 2009)
Stuart v. Stuart
962 A.2d 842 (Connecticut Appellate Court, 2009)
Wieselman v. Hoeniger
930 A.2d 768 (Connecticut Appellate Court, 2007)
Vissa v. Pagano
919 A.2d 488 (Connecticut Appellate Court, 2007)
Chernick v. Johnston
917 A.2d 1042 (Connecticut Appellate Court, 2007)
Whitaker v. Taylor
916 A.2d 834 (Connecticut Appellate Court, 2007)
36 DeForest Avenue, LLC v. Creadore
915 A.2d 916 (Connecticut Appellate Court, 2007)
566 New Park Associates, LLC v. Blardo
906 A.2d 720 (Connecticut Appellate Court, 2006)
MD Drilling & Blasting, Inc. v. MLS Construction, LLC
902 A.2d 686 (Connecticut Appellate Court, 2006)
Heaven v. Timber Hill, LLC
900 A.2d 560 (Connecticut Appellate Court, 2006)
Positive Impact Corp. v. Indotronix International Corp.
900 A.2d 535 (Connecticut Appellate Court, 2006)
State v. KEITH B.
897 A.2d 725 (Connecticut Appellate Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
891 A.2d 133, 94 Conn. App. 125, 2006 Conn. App. LEXIS 101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rollar-construction-demolition-inc-v-granite-rock-associates-llc-connappct-2006.