MD Drilling & Blasting, Inc. v. MLS Construction, LLC

889 A.2d 850, 93 Conn. App. 451, 2006 Conn. App. LEXIS 48
CourtConnecticut Appellate Court
DecidedJanuary 31, 2006
DocketAC 26330
StatusPublished
Cited by15 cases

This text of 889 A.2d 850 (MD Drilling & Blasting, Inc. v. MLS Construction, LLC) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MD Drilling & Blasting, Inc. v. MLS Construction, LLC, 889 A.2d 850, 93 Conn. App. 451, 2006 Conn. App. LEXIS 48 (Colo. Ct. App. 2006).

Opinion

Opinion

DiPENTIMA, J.

The defendant, MLS Construction, LLC, appeals from the judgment of the trial court concluding that the defendant breached the contract between the defendant and the plaintiff, MD Drilling & Blasting, Inc., and awarding damages, interest and attorney’s fees. On appeal, the defendant claims that the court improperly (1) found that a contract existed between the parties and (2) awarded contract interest and attorney’s fees. We affirm the judgment of the trial court.

The court’s memorandum of decision sets forth the following facts relevant to the defendant’s appeal. The owner of a vacant piece of property in East Haven retained the defendant to do excavation work, and, in February or March, 2003, the defendant asked the plaintiff to perform the necessary rock drilling and blasting for the project. In 2002, the plaintiff had entered into a written contract with the defendant to do similar work on a job in North Branford, for which the plaintiff had not been paid fully. The plaintiff agreed to perform the work in East Haven provided that the defendant make a substantial payment on the outstanding balance owed for the work done in North Branford. On March 31, 2003, the defendant agreed to the condition and tendered a check to the plaintiff for $15,000.

[453]*453For the East Haven agreement, the parties adopted the same terms and conditions contained in the North Branford written agreement, with a minor price reduction made orally during the course of the North Bran-ford job.1 Under the terms of the oral agreement, the plaintiff began work in East Haven on the morning of April 1,2003. On April 15,2003, the plaintiff was notified by its bank that the defendant had stopped payment on the $15,000 check on April 11. After its unsuccessful attempts to locate the defendant for an explanation of the stop payment, the plaintiff ceased work on April 18, 2003. Despite the defendant’s request that the plaintiff continue work on the East Haven project, the plaintiff advised the defendant that it would not resume drilling and blasting without some payment. Receiving none, the plaintiff did not return to the East Haven project.

Thereafter, the plaintiff filed an amended, six count complaint, claiming, inter alia, breach of contract and unjust enrichment.2 After a trial to the court, the court filed its memorandum of decision, concluding that the plaintiff had proven its claims of breach of contract and unjust enrichment, and was entitled to damages in the amount of $26,882.83 plus interest at 2 percent per month from May 25, 2003, to the date of judgment, as well as costs, expenses and attorney’s fees. The court withheld final judgment to allow the plaintiff “to file a computation of interest, including a per diem rate, and [454]*454an affidavit with respect to costs and expenses, and attorney’s fees.” After reviewing the submissions, the court conducted a subsequent hearing, filed a supplemental memorandum of decision and rendered judgment on January 24, 2005, awarding a total of $88,181.09 to the plaintiff. This appeal followed.

We begin by setting forth the applicable standard of review. “The existence of a contract is a question of fact to be determined by the trier on the basis of all of the evidence. ... On appeal, our review is limited to a determination of whether the trier’s findings are clearly erroneous. . . . This involves a two part function: where the legal conclusions of the court are challenged, we must determine whether they are legally and logically correct and whether they find support in the facts set out in the memorandum of decision; where the factual basis of the court’s decision is challenged we must determine whether the facts set out in the memorandum of decision are supported by the evidence or whether, in light of the evidence and the pleadings in the whole record, those facts are clearly erroneous.” (Citations omitted; internal quotation marks omitted.) Fortier v. Newington Group, Inc., 30 Conn. App. 505, 509, 620 A.2d 1321, cert. denied, 225 Conn. 922, 625 A.2d 823 (1993).

The defendant first argues that the court improperly found that a contract existed between the parties. Specifically, the defendant alleges that there was no offer and acceptance between the parties because the plaintiff revoked its offer, and there was no meeting of the minds. We disagree. “It is a fundamental principle of contract law that the existence and terms of a contract are to be determined from the intent of the parties. . . . The parties’ intentions manifested by their acts and words are essential to the court’s determination of whether a contract was entered into and what its terms were. . . . Whether the parties intended to be bound [455]*455without signing a formal written document is an inference of fact for the trial court that we will not review unless we find that its conclusion is unreasonable.” (Citations omitted.) Steeltech Building Products, Inc. v. Edward Suit Associates, Inc., 18 Conn. App. 469, 471-72, 559 A.2d 228 (1989).

The following additional facts educed from the record are relevant to the disposition of the defendant’s appeal. On the afternoon of April 1, 2003, the same day that it had begun drilling and blasting for the East Haven project, the plaintiff faxed the defendant its standard form of agreement. The agreement was intended to be identical to the North Branford agreement but reflected the orally agreed upon reduction to $2.75 per cubic yard.3 The plaintiff had not signed the written agreement, and the defendant testified that it never received it. The defendant argues that the unsigned written agreement that the plaintiff faxed on April 1, 2003, effectively revoked the original offer and, thus, invalidated the oral contract.

The defendant’s revocation argument was not raised or preserved, and the defendant filed no motion for articulation. We note, however, that because the court properly found that the defendant had accepted the offer, as a matter of law there could be no revocation. It is a fundamental principle of contract law that “ [r] evocation of an offer in order to be effectual must be received by the offeree and before he has exercised his power of creating a contract by acceptance of the offer.” (Emphasis added; internal quotation marks omitted.) Lyon v. Adgraphics, Inc., 14 Conn. App. 252, 255, 540 [456]*456A.2d 398, cert. denied, 208 Conn. 808, 545 A.2d 1103 (1988); see also L. & E. Wertheimer, Inc. v. Wehle-Hartford Co., 126 Conn. 30, 35, 9 A.2d 279 (1939); 1 A. Corbin, Contracts (Rev. Ed. 1993) § 2.18, p. 215 (“[a]fter an acceptance has become effective, there is no power in either party to revoke or withdraw”); 1 Restatement (Second), Contracts § 42, comment (c), p. 114 (1981) (“[o]nce the offeree has exercised his power to create a contract by accepting the offer, a purported revocation is ineffective as such”). Thus, even if the plaintiff had attempted to revoke its offer, which required a partial payment for the balance owed on the North Branford job, the fact that the defendant had accepted the offer by tendering the check terminated any possible revocation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Larobina v. Altice Media Solutions, LLC
229 Conn. App. 791 (Connecticut Appellate Court, 2024)
Platt v. Tilcon Connecticut, Inc.
196 Conn. App. 564 (Connecticut Appellate Court, 2020)
Computer Reporting Services, LLC v. Lovejoy & Associates, LLC
145 A.3d 266 (Connecticut Appellate Court, 2016)
Sean O'Kane A.I.A. Architect, P.C. v. Puljic
87 A.3d 1124 (Connecticut Appellate Court, 2014)
Cruz v. Visual Perceptions, LLC
46 A.3d 209 (Connecticut Appellate Court, 2012)
Harley v. Indian Spring Land Co.
3 A.3d 992 (Connecticut Appellate Court, 2010)
Auto Glass Express, Inc. v. Hanover Insurance
975 A.2d 1266 (Supreme Court of Connecticut, 2009)
Scrivani v. Vallombroso
916 A.2d 827 (Connecticut Appellate Court, 2007)
Aquarion Water Co. v. Beck Law Products & Forms, LLC
907 A.2d 1274 (Connecticut Appellate Court, 2006)
Duplissie v. Devino
902 A.2d 30 (Connecticut Appellate Court, 2006)
Ullman, Perlmutter & Sklaver v. Byers
900 A.2d 602 (Connecticut Appellate Court, 2006)
United Social & Mental Health Services, Inc. v. Rodowicz
899 A.2d 85 (Connecticut Appellate Court, 2006)
Valdes v. Yankee Casting Co.
891 A.2d 994 (Connecticut Appellate Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
889 A.2d 850, 93 Conn. App. 451, 2006 Conn. App. LEXIS 48, Counsel Stack Legal Research, https://law.counselstack.com/opinion/md-drilling-blasting-inc-v-mls-construction-llc-connappct-2006.