Sean O'Kane A.I.A. Architect, P.C. v. Puljic

87 A.3d 1124, 148 Conn. App. 728, 2014 WL 928697, 2014 Conn. App. LEXIS 98
CourtConnecticut Appellate Court
DecidedMarch 18, 2014
DocketAC35245
StatusPublished
Cited by5 cases

This text of 87 A.3d 1124 (Sean O'Kane A.I.A. Architect, P.C. v. Puljic) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sean O'Kane A.I.A. Architect, P.C. v. Puljic, 87 A.3d 1124, 148 Conn. App. 728, 2014 WL 928697, 2014 Conn. App. LEXIS 98 (Colo. Ct. App. 2014).

Opinion

Opinion

BEACH, J.

The plaintiff, Sean O’Kane A.I.A. Architect, P.C., 1 appeals from the judgment of the trial court in favor of the defendants, Goran Puljic and Melinda Pul-jic. The plaintiff claims that the court erred in (1) concluding that his breach of contract claim was barred by the statute of limitations; (2) finding that the parties did not enter into a “standstill” agreement, thus tolling the statute of limitations; and (3) concluding that the count of his complaint alleging unjust enrichment was barred by the doctrine of laches. We affirm in part and reverse in part the judgment of the trial court.

The action was commenced by service of process on June 29, 2010. The plaintiff later filed an amended complaint alleging (1) breach of contract for failure to pay for architectural services, and (2) unjust enrichment. By way of special defenses, the defendants alleged that the breach of contract claim was barred by the applicable statute of limitations, General Statutes § 52-576, and that the unjust enrichment claim was barred by the doctrine of laches. In the plaintiff’s reply *731 to the defendants’ special defense asserting the statute of limitations, the plaintiff alleged, as a “matter in avoidance,” that the parties had agreed not to “bring claims against one another” until after arbitration proceedings involving the builder, a third parly, were concluded, and thus the statute of limitations had been tolled.

The parties entered into a stipulation agreeing to bifurcate the trial, under which the facts and issues relating to the defendants’ special defenses would be decided prior to the adjudication of the other facts and issues in this case. Accordingly, the court, in its November 28,2012 decision, addressed only the special defenses alleging that any recovery was barred by the statute of limitations and laches.

The following facts were found by the trial court. In December, 2000, the plaintiff and Melinda Puljic executed a contract for architectural services (contract). The contract was addressed to: “Mr. & Mrs. G. Puljic.” Both defendants were the owners of a house in Darien. Pursuant to the contract, the plaintiff was to perform restoration and alteration work on “two adjacent houses built almost 200 years ago, improved with additions and alterations joining the two houses into one building.” On October 10, 2001, both defendants and E. M. Rose Builders, Inc. (Rose), entered into a construction contract (construction contract) pursuant to which Rose commenced work. The plaintiff was not a party to the construction contract. The goal of the project was to complete the house by December, 2002.

The plaintiff submitted twenty-three serially numbered invoices to the defendants for architectural services. The defendants paid invoices one through seventeen, but failed to pay invoices eighteen through twenty-three. The total of the unpaid invoices was $92,201.35, which the plaintiff claimed in damages in his complaint. The unpaid invoices were for work allegedly *732 done during the period from July through December, 2002. No invoices were submitted into evidence for architectural services rendered after December 31, 2002, and there was no testimony that any such invoices were prepared. All invoices were addressed and billed to both defendants.

The court found that the breach of contract claim was barred by § 52-576, and that the unjust enrichment claim was barred by the doctrine of laches. This appeal followed.

HH

The plaintiff first claims that the court erred in concluding that the breach of contract claim was barred by the six year statute of limitations set forth in § 52-576. He specifically argues that the court erred in concluding that the continuous representation doctrine did not apply. 2 He contends that pursuant to the architectural contract and the construction contract, his services on the project were to continue until the project was complete—in other words, until the issuance of the certificate of occupancy and zoning compliance on September 25, 2005. He argues, therefore, that under the continuous representation doctrine, the breach of contract claim accrued on September 25, 2005, and the action was commenced within six years of that date. We disagree, and affirm the court’s holding that the breach of contract claim is barred by the statute of limitations. 3

*733 Section 52-576 (a) provides in relevant part: “No action for an account, or on any simple or implied contract, or on any contract in writing, shall be brought but within six years after the right of action accrues . . . “[I]n an action for breach of contract . . . the cause of action is complete at the time the breach of contract occurs, that is, when the injury has been inflicted. . . . While the statute of limitations normally begins to run immediately upon the accrual of the cause of action, some difficulty may arise in determining when the cause or right of action is considered as having accrued. . . . The true test for determining the appropriate date when a statute of limitations begins to run is to establish the time when the plaintiff first successfully could have maintained an action. That is, an action cannot be maintained until a right of action is complete and hence, the statute of limitations cannot run before *734 that time.” (Citation omitted; footnote omitted; internal quotation marks omitted.) I. Rosenfield v. David Marder & Associates, LLC, 110 Conn. App. 679, 685-86, 956 A.2d 581 (2008). The question of whether a party’s claim is barred by the statute of limitations is one of law subject to plenary review. Certain Underwriters at Lloyd’s, London v. Cooperman, 289 Conn. 383, 407-408, 957 A.2d 836 (2008).

Several doctrines tolling the statutes of limitations have emerged for policy reasons. The continuing course of conduct doctrine, the continuous treatment doctrine, and the continuous representation doctrine present similar solutions to similar problems. The plaintiff argues that this case is appropriately subject to the continuous representation doctrine. That doctrine, however, has been applied thus far only to contexts involving attorneys, where ethical considerations inform the preference to delay accrual, from the time of the act or omission complained of until the attorney’s representation has ended. “[O]ur Supreme Court [in DeLeo v. Nusbaum, 263 Conn. 588, 596-97, 821 A.2d 744

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Probate Appeal of Barbera
Connecticut Appellate Court, 2025
Essex Ins. Co. v. William Kramer & Associates, LLC
205 A.3d 534 (Supreme Court of Connecticut, 2019)
Doe v. Hartford Roman Catholic Diocesan Corp.
Supreme Court of Connecticut, 2015
Molleur v. Bucknam
Vermont Superior Court, 2015
In re Actiq Sales & Marketing Practices Litigation
307 F.R.D. 150 (E.D. Pennsylvania, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
87 A.3d 1124, 148 Conn. App. 728, 2014 WL 928697, 2014 Conn. App. LEXIS 98, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sean-okane-aia-architect-pc-v-puljic-connappct-2014.