Nation Electrical Contracting, LLC v. St. Dimitrie Romanian Orthodox Church

74 A.3d 474, 144 Conn. App. 808, 2013 WL 3990878, 2013 Conn. App. LEXIS 403
CourtConnecticut Appellate Court
DecidedAugust 13, 2013
DocketAC 34599
StatusPublished
Cited by11 cases

This text of 74 A.3d 474 (Nation Electrical Contracting, LLC v. St. Dimitrie Romanian Orthodox Church) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nation Electrical Contracting, LLC v. St. Dimitrie Romanian Orthodox Church, 74 A.3d 474, 144 Conn. App. 808, 2013 WL 3990878, 2013 Conn. App. LEXIS 403 (Colo. Ct. App. 2013).

Opinion

Opinion

ROBINSON, J.

The defendant St. Dimitrie Romanian Orthodox Church appeals from the judgment of the trial court finding it jointly and severally hable with the defendant Primrose Construction Company, Inc. (Primrose), to the plaintiff, Nation Electrical Contracting, LLC, for damages of $34,900 and prejudgment interest of $11,621.70.1 The defendant claims that the court improperly (1) rendered judgment against it on a theory of unjust enrichment despite evidence that it had paid all sums due and owing under its construction contract with Primrose, which necessarily included payment for the work done by the plaintiff as a subcontractor of [810]*810Primrose, and (2) awarded prejudgment interest pursuant to General Statutes § 37-3a where there was no basis in law or in fact to award such interest. We affirm the judgment of the trial court.

The following facts, which were found by the court or are undisputed, and procedural history are relevant to our resolution of the claims on appeal. The defendant entered into a written contract with Primrose in 2006, for the construction of a new church in Easton. Primrose agreed to act as the general contractor for the project, and the defendant agreed to pay Primrose $2,954,250 plus extras. Primrose retained a number of subcontractors to help with the project, including accepting abid of $109,795 from the plaintiff to perform electrical work. The plaintiff never entered into any contractual agreement with the defendant.

In October and November, 2007, the plaintiff submitted invoices to Primrose requesting progress payments of $10,000 and $12,000, respectively. Primrose later submitted its own invoice for progress payments to the defendant, which included those sums sought by the plaintiff. The defendant paid Primrose, and Primrose paid the plaintiff the sum due on the October and November invoices.

On January 1, 2008, the plaintiff submitted a third invoice to Primrose for $40,000.2 On February 18, 2008, [811]*811prior to the completion of the church, Primrose left the job and stopped working on the project.3 The plaintiff also stopped its work at that time. Up to that date, the plaintiff had complied with all the terms and conditions of its contract with Primrose, and all the parties agreed that the plaintiff’s work was completed in a workmanlike manner.4

On February 23, 2008, Primrose submitted a final progress billing to the defendant. Primrose indicated on the progress billing that the defendant had thus fax paid Primrose $1,500,795.15 on the contract, and Primrose sought an additional $241,424.11 for the work performed up to February 18, 2008, which included the sum sought by the plaintiff in its January 1,2008 invoice. The defendant did not make any payments on the February 23, 2008 invoice to Primrose nor did it make any direct payments to the plaintiff. Primrose and several of its subcontractors, including the plaintiff, filed mechanic’s hens against the defendant’s property to secure the balance they claimed remained due to them.

In November, 2008, the plaintiff commenced the present action. The original complaint contained four counts. Count one sought to foreclose on the plaintiff’s mechanic’s hen, count two alleged unjust enrichment on the part of the defendant, count three sounded in breach of contract against Primrose, and count four alleged liability on the part of John N. Guedes based on his personal guarantee of Primrose’s performance under the contract with the plaintiff. The plaintiff filed a first amended complaint that included an additional [812]*812count against the defendant sounding in quantum meruit. The plaintiff later filed a second amended, and operative, complaint that dropped the foreclosure count and the count against Guedes.

In March, 2009, Primrose filed an action to foreclose its mechanic’s lien on the defendant’s property. The defendant filed an application in that matter to discharge Primrose’s lien. On December 24, 2009, following briefing and an evidentiary hearing, the court, Levin, J., issued an order granting the application to discharge the lien. See Primrose Construction Co. v. St. Dimitrie Romanian Orthodox Church, Superior Court, judicial district of Fairfield, Docket No. CV-09-5023147-S (December 24, 2009). In the order, Judge Levin included a number of findings “[b]y clear and convincing evidence.” Judge Levin found, inter alia, that the defendant had agreed to pay Primrose $2,954,250 for the construction of the church, that $99,970.10 in change orders had been made, that the defendant thus far had paid Primrose $1,500,795.15, that the work performed by Primrose or its subcontractors was not of a workmanlike manner, that the defendant reasonably had expended in excess of $300,000 to repair the deficient workmanship, that after Primrose abandoned the contract the defendant paid more than $3,000,000 to complete the work that Primrose had agreed to perform, and, finally, that “[t]here is no balance owing or fund which [Primrose] can hen.” On the basis of those findings, Judge Levin concluded that Primrose had failed to meet its burden of establishing probable cause for sustaining the validity of its mechanic’s lien.

The present action was tried thereafter to the court, Hon. Richard P. Gilardi, judge trial referee. At some point prior to trial, the parties agreed that Judge Levin’s December 24, 2009 order, including ah factual findings therein, should be entered into evidence and that the court should consider Judge Levin’s factual findings in [813]*813reaching its decision in the present case.5 The order was admitted at trial as the defendant’s exhibit 3.

The court issued a memorandum of decision on January 24, 2012. With regard to the unjust enrichment count, the court first rejected the defendant’s argument that it was entitled to a set off with respect to the value of any benefit allegedly received from the plaintiff because, due to damage, it was able to use only 35 or 40 percent of the electrical work provided by the plaintiff. The court found that the alleged damage occurred after the plaintiff had completed the work, without any complaint as to the quality of the work from the defendant, and that the damage was self-inflicted by the defendant or by a subsequent contractor.

The court next rejected the defendant’s claim that the plaintiff should be prohibited from claiming unjust enrichment because the defendant had paid Primrose everything it was owed under the construction contract prior to its abandonment of the project, which necessarily included payment for the work performed by its subcontractors, and allowing an unpaid subcontractor subsequently to sue for unjust enrichment would result in the defendant paying twice for the same benefit. See Providence Electric Company v. Sutton Place, Inc., 161 Conn. 242, 246, 287 A.2d 379 (1971). In rejecting that argument, the court reasoned that the defendant “never introduced any evidence, testimony or even a claim that [814]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mystic Oil Co. v. Shaukat, LLC
228 Conn. App. 147 (Connecticut Appellate Court, 2024)
Kohl's Dept. Stores, Inc. v. Rocky Hill
Connecticut Appellate Court, 2020
Crosskey Architects, LLC v. POKO Partners, LLC
Connecticut Appellate Court, 2019
Meribear Prods., Inc. v. Frank
183 A.3d 1164 (Supreme Court of Connecticut, 2018)
Superior Steel, Inc. v. Ascent at Roebling's Bridge, LLC
540 S.W.3d 770 (Missouri Court of Appeals, 2017)
Marshall v. Marshall
Connecticut Appellate Court, 2014
Sean O'Kane A.I.A. Architect, P.C. v. Puljic
87 A.3d 1124 (Connecticut Appellate Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
74 A.3d 474, 144 Conn. App. 808, 2013 WL 3990878, 2013 Conn. App. LEXIS 403, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nation-electrical-contracting-llc-v-st-dimitrie-romanian-orthodox-church-connappct-2013.