Dugan & Meyers Construction Company v. The Ascent at Roebling's Bridge, LLC

CourtKentucky Supreme Court
DecidedDecember 12, 2017
Docket2015 SC 000635
StatusUnknown

This text of Dugan & Meyers Construction Company v. The Ascent at Roebling's Bridge, LLC (Dugan & Meyers Construction Company v. The Ascent at Roebling's Bridge, LLC) is published on Counsel Stack Legal Research, covering Kentucky Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dugan & Meyers Construction Company v. The Ascent at Roebling's Bridge, LLC, (Ky. 2017).

Opinion

· RE!'IDERED: DECEMBER 14, 2017 TO BE PUBLISHED

j5upr:ettt:e dtnurf n.f ~:enfurku 2015-SC-000204-DG AND 2015-SC-000636-DG

SUPERIOR STEEL, INC., AND APPELLANTS/CROSS-APPELLEES BEN HUR CONSTRUCTION · COMPANY, INC.

ON REVIEW FROM ·COURT OF APPEALS V. . CASE NOS. 2012-CA-000440-MR, 2012-CA-000441-MR, 2012-CA-000494-MR AND 2012-CA-000495-MR KENTON CIRCUIT COURT NOS. 07-CI-03886 AND 08-Cl-01309

THE ASCENT AT ROEBLING'S BRIDGE, APPELLE~S/CROSS-APPELLANTS LLC.; CORPOREX DEVELOPMENT AND CONSTRUCTION MANAGEMENT LLC; . DUGAN & MEYE~S CONSTRUCTION COMPANY AND ·WESTCHESTER FIRE INSURANCE COMPANY

AND 2015-SC.,000635-DG

DUGAN & MEYERS CONSTRUCTION CROSS-APPELLANT COMPANY

ON REVIEW FROM COURT OF APPEALS V. CASE NOS. 2012-CA-000440-MR, 2012-CA-000441-MR, 2012-CA-000494-MR AND 2012-CA-000495-MR CIRCUIT COURT NOS. 07-CI-03886 AND 08-CI-O 1309

THE ASCENT AT ROEBLING'S BRIDGE, CROSS-APPELLEES LLC.; CORPOREX DEVELOPMENT AND CONSTRUCTION MANAGEMENT LLC; SUPERIOR STEEL, INC.; BEN HUR CONSTRUCTION COMPANY, INC. AND WESTCHESTER FIRE INSURANCE COMPANY OPINION OF THE COURT BY JUSTICE HUGHES

AFFIRMING IN PART, REVERSING IN PART, AND REMANDING

The Ascent at Roebling's Bridge (the "Project") is a 21-floor, luxury

condominium building in downtown Covington, owned by Appellee /Cross-

Appellant The Ascent at Roebling's Bridge, LLC ("Ascent") and developed by

Appellee /Cross-Appellant Corporex Development and Construction ·

Management LLC ("Corporex''). Corporex, the design builder, contracted with

Appellee/Cross-Appellant Dugan & Meyers Construction Company ("D&M"),

the construction manager and general contractor. D&M worked directly with·

subcontractors, including Appellant/ Cross-Appellee Superior Steel, Inc.

("Superior"), the steel fabricator, and Appellant/Cross-Appellee Ben Hur

Construction Company, Inc. ("Ben Hur"), the steel erector and Installer. When

new drawings led to extra work outside the scope of the original bid

documents, Superior. and Ben . Hur proceeded with the work, but they were

never paid for either that. work or the retainage amount owed under Superior's

contract with D&M. The two steel companies banded together as "the Steel

Team~ and brought suit against D&M, Ascent and Corporex.

After a fifteen-day jury trial, the Kenton Circuit Court.entered judgment

. in favor of Superior and Ben Hur against D&M and Ascent for the cost of the

extra work and the unpaid retainage as well as attorneys' fees incurred by . I Superior. D&M prevailed on its indemnification cross-claim against Corporex

and Ascent and on the negligence cross-claim asserted against it by Corporex

and Ascent. On appeal, the Court of Appeals reversed the judgment in its

entirety, unwinding the majority of the trial court's rulings and returning the 2 record and applicable la:w, we affirm the judgment of the Court of Appeals in

part, reverse in part, and remand for further proceedings consistent with this

Opinion.

FACTUAL AND PROCEDURAL BACKGROUND

In November 2005, Ascent hired Corporex to be the "design builder" for

the Project. 1 Later, in March 2006, Corporex hired D&M, as the construction

manager/ general contractor. for the Project. Corporex agreed to pay D&M a

$2.2 million lump sum, a $975,000 contractor's fee (plus any participation in

savings and a potential bonus), and a sum for the cost of the work as identified

in the "Initial Estimate."

In July 2006, D&M solicited bids for the fabrication.and erection of

structural steel for the Project. The bid package that D&M supplied to

potential subcontractors included architectural and structural drawings for the

Project. Notably, those drawings did not include a forces table (a chart which

identifies the forces acting upon each piece of steel to be used on the Project) or

designs for the steel connections.

On August 4, 2006, D&M received three bids, including one from

Superior, to be the subcontractor for the structural steel work. Subsequently,

D&M contacted Superior and inquired whether the company would be willing

to modify its bid proposal. As a cost saving measure, D&M wanted Superior to

I At the time of the Project and to this day, Ascent and Corporex exist as related entities. They are referred to hereafter as Ascent/ Corporex except in reference to the Corporex/D&M contract, to which Ascent was not a party, and in other instances where a distinction is appropriate.

3 fabricate the steel for the project and have Ben Hur complete the erection and

installation work. Prior to Superior submitting its modified bid, the Project's

architect issued a revised se~ of drawings. Despite that fact; D&M instructed

Superior to not acknowledge the revised drawings in making its bid; D&M

wanted to be able to evaluate each of the bids it had received on an equal

basis. Superior's modified bid was accepted by D&M in September 20062 and

the parties' contract had a fixed price of $1,814,000. In turn, Superior

contracted with Ben Hur to erect the steel and metal decking for $444,000. As

structured, payment for all of the steel work flowed from Corporex to D&M and

then from D&M to Superior. Superior would then pay Ben Hur what it was

owed for erection and installation of the steel fabricated by Superior.

After Superior and Ben Hur were retained to work on the .Project, further

alterations were made to the structural design drawings issued by

Ascent/ Corporex. Corporex alerted D&M to the changes, and D&M in turn

informed Superior and Ben Hur. Superior and Ben Hur expressed concern

about the design changes as they would require additional work to be

performed, work beyond the original scope of the contract. 3 In response, D&M

separately directed both Superior ~d Ben Hur to perform the extra work, while

keeping track of the time and costs.

2 After D&M issued a letter of intent to award the steel and metal decking contract to Superior, Superior and Ben Hur began working on the J>roject. This work · was done prior to finalizing the contract between D&M and Superior. 3 The claimed value of the extra work performed by Ben Hur and Superior fluctuated prior to and during the course of the litigation in this case.

4 Prior to starting the additional work, Ben flur's Vice President, Mark

Douglas, sought the personal assurance of D&M's President, Jay Meyers, along

with Corporex Vice-President Mike O'Donnell, that Ben Hur would be paid for

the additional work. In a meeting with Meyers, Douglas was directed to

proceed with the extra work, while tracking the time and costs. Meyers

reassured Douglas that Ben Hur would not be cheated~ On the day following

the meeting, Dan Dugan of D&M drafted a letter to· Superior acknowledging

that additional work was necessitated due to ~hanges to the design from the

original bid· documents and authorizing Superior to proceed with the additional

work. That draft letter was forwarded to O'Donnell at Corporex, who .directed

Dugan not to send the letter.

Later, Ben H71r and Superior submitted work orders to D&M detailing the·

additional work done on the Project. In turn, D&M submitted those work

orders to Corporex. While Ascent/ Corporex did pay for some of the extra work

performed, they failed to pay for additional work performed on the forces

table/design load increase, the roof edge c~ndition, and the roof tip. When

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sloan & Co. v. Liberty Mutual Insurance
653 F.3d 175 (Third Circuit, 2011)
BMD CONTRACTORS v. Fidelity and Deposit Co. of Md.
679 F.3d 643 (Seventh Circuit, 2012)
ASHTON COMPANY, INC., CONTR. & ENG'RS v. State
454 P.2d 1004 (Court of Appeals of Arizona, 1969)
Wellington Power Corp. v. CNA Surety Corp.
614 S.E.2d 680 (West Virginia Supreme Court, 2005)
AIK Selective Self-Insurance Fund v. Minton
192 S.W.3d 415 (Kentucky Supreme Court, 2006)
Hoheimer v. Hoheimer
30 S.W.3d 176 (Kentucky Supreme Court, 2000)
Montgomery Independent School District v. Davis
34 S.W.3d 559 (Texas Supreme Court, 2000)
Frear v. P.T.A. Industries, Inc.
103 S.W.3d 99 (Kentucky Supreme Court, 2003)
Zeitz v. Foley
264 S.W.2d 267 (Court of Appeals of Kentucky (pre-1976), 1954)
Nucor Corp. v. General Electric Co.
812 S.W.2d 136 (Kentucky Supreme Court, 1991)
Morganfield National Bank v. Damien Elder & Sons
836 S.W.2d 893 (Kentucky Supreme Court, 1992)
Brock v. Pilot Corp.
234 S.W.3d 381 (Court of Appeals of Kentucky, 2007)
Penco, Inc. v. Detrex Chemical Industries, Inc.
672 S.W.2d 948 (Court of Appeals of Kentucky, 1984)
Commonwealth v. English
993 S.W.2d 941 (Kentucky Supreme Court, 1999)
Cantrell Supply, Inc. v. Liberty Mutual Insurance Co.
94 S.W.3d 381 (Court of Appeals of Kentucky, 2002)
Codell Construction Co. v. Commonwealth
566 S.W.2d 161 (Court of Appeals of Kentucky, 1977)
Goodyear Tire and Rubber Co. v. Thompson
11 S.W.3d 575 (Kentucky Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Dugan & Meyers Construction Company v. The Ascent at Roebling's Bridge, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dugan-meyers-construction-company-v-the-ascent-at-roeblings-bridge-llc-ky-2017.