The Thos. J. Dyer Company v. Bishop International Engineering Company and General Insurance Company of America

303 F.2d 655, 21 Ohio Op. 2d 235, 1962 U.S. App. LEXIS 4969
CourtCourt of Appeals for the Sixth Circuit
DecidedMay 30, 1962
Docket14550_1
StatusPublished
Cited by75 cases

This text of 303 F.2d 655 (The Thos. J. Dyer Company v. Bishop International Engineering Company and General Insurance Company of America) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Thos. J. Dyer Company v. Bishop International Engineering Company and General Insurance Company of America, 303 F.2d 655, 21 Ohio Op. 2d 235, 1962 U.S. App. LEXIS 4969 (6th Cir. 1962).

Opinion

SHACKELFORD MILLER, JR., Chief Judge.

Appellee, The Thos. J. Dyer Company, a subcontractor on the project hereinafter referred to, brought this action against the appellant, Bishop International Engineering Company, hereinafter referred to as Engineering Company, the general contractor, to recover the sum of $134,684.53 for materials and labor furnished by it in the construction of the project. The appellant, General Insurance Company of America, was also made a defendant as surety on the “Owner’s Protective Bond,” executed by the Engineering Company as principal.

The following facts were stipulated by the parties. Appellee is an Ohio corporation engaged in the plumbing contracting business. The Engineering Company is a partnership engaged in the general contracting business. On or about August 19, 1958, the Engineering Company entered into a written contract with The Kentucky Jockey Club, Inc., hereinafter referred to as the Jockey Club, by the terms of which it agreed to provide labor and materials required in connection with the construction of a portion of a Horse Racing Plant, known as Latonia Race Track, upon premises belonging to the Jockey Club, situated in Boone County, Kentucky. That portion of the construction project covered by the contract was described as “Phase One.”

On or about April 27, 1959, the appellee entered into a written subcontract with the Engineering Company, by the provisions of which it agreed to provide materials for and to install certain plumbing and utilities required in connection with the completion of the construction work to be performed by the Engineering Company, pursuant to its contract with the Jockey Club, for which it was to receive the sum of $115,000.00. Paragraph 3 of this subcontract reads as follows:

“3. The total price to be paid to Subcontractor shall be ........ Dollars ($115,000.00) lawful money of the United States, no part of which shall be due until five (5) days after Owner shall have paid Contractor therefor, provided however, that not more than......... per cent (90%) thereof shall be due until thirty-five (35) days after the entire work to be performed and completed under said contract shall have been completed to the satisfaction of Owners, and provided further that Contractor may retain sufficient moneys to fully pay and discharge any and all liens, stop-notices, attachments, garnishments and executions. Nothing herein is to be construed as preventing Con *657 tractor from paying to the Subcontractor all or any part of said price at any time hereafter as an advance or otherwise.”

The Engineering Company has provided all of the labor and material and has done all things necessary for the completion of the work required of it under the contract of August 19, 1958, and has received payment of the sum of $2,236,908.95, specified by the contract as the consideration to be paid to it for the work to be performed by it thereunder.

From time to time following the execution of the contract of August 19, 1958, the Engineering Company was called upon by the Jockey Club to provide labor, services and materials for the completion of various items of construction relating to the above mentioned Horse Racing Plant which had not been included within Phase One of the construction program of the Jockey Club. The Engineering Company has received compensation for certain portions of such additional labor, services and materials provided by it at the request of the Jockey Club but has not yet received payment for all of it.

From time to time after April 27, 1959, the date of the subcontract with appellee, appellee was called upon by the Engineering Company to provide labor, services and materials in addition to those specified in the above described subcontract, to which it agreed, as evidenced by change orders, letter proposals and acceptances. Some of such additional labor, services and materials fell within the scope of the above described construction contract between the Engineering Company and the Jockey Club, while some of it was beyond the scope of that contract.

The aggregate additional consideration which the Engineering Company agreed to pay appellee for the additional labor, services and materials to be provided pursuant to the change orders, letter proposals and acceptances, amounted to $112,652.17, making the total consideration payable to appellee for all services and materials which it agreed to perform and provide in connection with the construction of the Latonia Race Track equal the sum of $227,652.17.

Appellee has provided all the labor and materials and has done all things necessary for the completion of the work required of it under the subcontract, change orders, proposals and acceptances. Appellee completed its work as required on or before August 1, 1959, and the completed project was accepted by the owners on or about August 28, 1959.

The Engineering Company has not been paid by the Jockey Club for any work performed or material supplied by the appellee, other than that required pursuant to the terms of the original contract, dated August 19, 1958, between the Engineering Company and the Jockey Club.

The Engineering Company has paid to appellee for work performed and materials provided under the subcontract, changes orders, proposals and acceptances the sum of $119,133.06. After the payment of $119,133.06 there remained a balance due from the Engineering Company to the appellee of $108,-519.11.

Under date of August 19, 1958, the appellant General Insurance Company of America executed a bond to the Jockey Club in the face amount of $2,086,908.-75, upon which the Engineering Company was the principal.

On December 4, 1959, the Jockey Club filed in the United States District Court for the Western District of Kentucky, Louisville Division, a proceeding for its reorganization under Chapter X of the Federal Bankruptcy Act. That proceeding is still pending.

The Engineering Company in its defense to the action contends that by the provisions of paragraph 3 of its subcontract with the appellee no payment was due thereunder to the appellee until five days after the Jockey Club, owner of the construction project to which the *658 contract related, had made payment to the Engineering Company; that the Jockey Club has paid to it on account of the work performed and the materials furnished by the appellee certain payments, all of which have been paid by the Engineering Company to the appellee ; and that because it has not received any further payment from the Jockey Club, now being reorganized in bankruptcy, it has no obligation to make further payment to the appellee.

Following the filing of the stipulation of facts, the District Judge made findings of fact and conclusions of law, sustained appellee’s motion for summary judgment, and entered judgment for the appellee in the principal amount of $108,519.11, together with $9,224.12 as interest due to the date of the judgment.

Appellant questions the right of the District Judge to make findings of fact in passing on a motion for summary judgment. Rules 52(a) and 56(e), Rules of Civil Procedure, 28 U.S.C.A. The facts were stipulated, and insofar as the findings of the District Judge may vary from them or from the admissions contained in the pleadings, they will be disregarded.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J&H Grading & Paving v. Clayton Construction
Court of Appeals of South Carolina, 2023
Young Elec. Contractors, Inc. v. Dustin Constr., Inc.
185 A.3d 170 (Court of Appeals of Maryland, 2018)
Superior Steel, Inc. v. Ascent at Roebling's Bridge, LLC
540 S.W.3d 770 (Missouri Court of Appeals, 2017)
Tymeless Flooring, Inc. v. Rotolo Consultants, Inc.
172 So. 3d 145 (Louisiana Court of Appeal, 2015)
Hunt v. Kadlick
972 F. Supp. 2d 772 (D. Maryland, 2013)
BMD CONTRACTORS v. Fidelity and Deposit Co. of Md.
679 F.3d 643 (Seventh Circuit, 2012)
Evans, Mechwart, Hambleton & Tilton, Inc. v. Triad Architects, Ltd.
965 N.E.2d 1007 (Ohio Court of Appeals, 2011)
Sloan & Co. v. Liberty Mutual Insurance
653 F.3d 175 (Third Circuit, 2011)
Wellington Power Corp. v. CNA Surety Corp.
614 S.E.2d 680 (West Virginia Supreme Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
303 F.2d 655, 21 Ohio Op. 2d 235, 1962 U.S. App. LEXIS 4969, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-thos-j-dyer-company-v-bishop-international-engineering-company-and-ca6-1962.