Transtar Elec., Inc. v. A.E.M. Elec. Servs. Corp. (Slip Opinion)

2014 Ohio 3095, 16 N.E.3d 645, 140 Ohio St. 3d 193
CourtOhio Supreme Court
DecidedJuly 17, 2014
Docket2013-0148
StatusPublished
Cited by54 cases

This text of 2014 Ohio 3095 (Transtar Elec., Inc. v. A.E.M. Elec. Servs. Corp. (Slip Opinion)) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transtar Elec., Inc. v. A.E.M. Elec. Servs. Corp. (Slip Opinion), 2014 Ohio 3095, 16 N.E.3d 645, 140 Ohio St. 3d 193 (Ohio 2014).

Opinions

Kennedy, J.

{¶ 1} In this appeal from the Sixth District Court of Appeals, we consider whether a provision addressing payment of a subcontractor by a general contractor in a contract between appellant, A.E.M. Electric Services Corporation, the general contractor, and appellee, Transtar Electric, Inc., the subcontractor, that uses the term “condition precedent” is sufficient to establish a pay-if-paid payment provision. We hold that the use of the term “condition precedent” is an explicit statement of the parties’ intent to transfer the risk of the project owner’s nonpayment from A.E.M. to Transtar.

{¶ 2} A.E.M. advances one proposition of law: “The unambiguous language in the subcontract between the parties is a ‘pay-if-paid’ provision, which without payment by the owner, does not require the contractor to pay the subcontractor.” For the reasons that follow, we hold that when a contract provides that payment by a project owner to the general contractor for work performed by a subcontractor is a condition precedent to payment by the general contractor to the subcontractor, the provision is a pay-if-paid provision. We further hold that the use of the term “condition precedent” in a payment provision of a contract between a general contractor and a subcontractor clearly and unequivocally shows the intent of those parties to transfer the risk of the project owner’s nonpayment from the general contractor to the subcontractor.

[195]*195I. Facts and Procedural History

{¶ 3} A.E.M., the general contractor, contracted with Transtar, the subcontractor, to provide electrical services for the installation of a pool at a Holiday Inn.

{¶ 4} Transtar fully performed the work under the contract, submitted invoices to A.E.M., and was paid $142,620.10 in 11 installments. However, A.E.M. did not pay Transtar for the last three invoices, totaling $44,088.90, because the owner of the project had failed to pay A.E.M. for the work performed by Transtar. A.E.M. argues that Section 4 of the contract is controlling and that it establishes a pay-if-paid payment provision. Section 4 of the contract reads:

(b) The Subcontractor shall submit weekly certified payroll reports, and shall pay all workmen employed on the Project labor rates equal to or greater than those required by the Prime Contract. The weekly certified payroll reports shall set forth with particularity the number of hours that each employee of the Subcontractor has worked on the project.
(c) The Contractor shall pay to the Subcontractor the amount due under subparagraph (a) above only upon the satisfaction of all four of the following conditions: * * * (iv) the Contractor has received payment from the Owner for the Work performed by the Subcontractor. RECEIPT OF PAYMENT BY CONTRACTOR FROM THE OWNER FOR WORK PERFORMED BY SUBCONTRACTOR IS A CONDITION PRECEDENT TO PAYMENT BY CONTRACTOR TO SUBCONTRACTOR FOR THAT WORK.

(Capitalization and boldface sic.)

{¶ 5} Transtar filed suit demanding judgment against A.E.M. for breach of contract, unjust enrichment, and money damages totaling $44,088.90, plus costs and prejudgment interest.

{¶ 6} Both Transtar and A.E.M. filed motions for summary judgment. A.E.M. did not dispute the facts as asserted by Transtar. A.E.M. argued that Section 4 of the contract provided that it did not require A.E.M. to pay Transtar until the owner of the project paid A.E.M. for Transtar’s work. The trial court agreed and granted summary judgment in favor of A.E.M., holding that Transtar’s claims for payment failed as a matter of law.

{¶ 7} The Sixth District Court of Appeals reversed. The court held that absent language making manifest the intent to shift the risk of nonpayment to the subcontractor, a provision for payment must be construed as an absolute promise on the part of the general contractor to pay the subcontractor within a reasonable time. The court then held that the payment provision in the contract between [196]*196the parties was not specific enough to show that both parties understood and agreed that the risk of the owner’s nonpayment would be borne by the subcontractor instead of the general contractor. The court further held that to shift the risk of the owner’s nonpayment from the general contractor to the subcontractor, “[i]t must be made plain, in plain language, that a subcontractor must look to the owner for payment.” 2012-Ohio-5986, 983 N.E.2d 399, ¶ 30 (6th Dist.). As a result, the general contractor was liable to the subcontractor for the work performed without regard to whether the general contractor had been paid by the owner.

II. Standard of Review

{¶ 8} Our review of cases involving a grant of summary judgment is de novo. Bonacorsi v. Wheeling & Lake Erie Ry. Co., 95 Ohio St.3d 314, 2002-Ohio-2220, 767 N.E.2d 707, ¶ 24. Summary judgment may be granted only when (1) there is no genuine issue of material fact, (2) the moving party is entitled to judgment as a matter of law, and (3) upon viewing the evidence in favor of the nonmoving party, reasonable minds can come to but one conclusion, and that conclusion is adverse to the nonmoving party. M.H. v. Cuyahoga Falls, 134 Ohio St.3d 65, 2012-Ohio-5336, 979 N.E.2d 1261, ¶ 12.

III. Analysis

{¶ 9} The cardinal principle in contract interpretation is to give effect to the intent of the parties. Skivolocki v. E. Ohio Gas Co., 38 Ohio St.2d 244, 313 N.E.2d 374 (1974), paragraph one of the syllabus. “[W]e will look to the plain and ordinary meaning of the language used in the contract unless another meaning is clearly apparent from the contents of the agreement. When the language of a written contract is clear, a court may look no further than the writing itself to find the intent of the parties.” Sunoco, Inc. (R & M) v. Toledo Edison Co., 129 Ohio St.3d 397, 2011-Ohio-2720, 953 N.E.2d 285, ¶ 37.

{¶ 10} Generally, there are two types of contractual provisions that establish the manner by which a general contractor pays a subcontractor for the subcontractor’s work. A general contractor can make an unconditional promise to pay the subcontractor, usually within a reasonable time to allow the general contractor to be paid. Thos. J. Dyer Co. v. Bishop Internatl. Eng. Co., 303 F.2d 655, 659 (6th Cir.1962). An unconditional promise to pay is a pay-when-paid payment provision. Such a promise is not dependent on or modified by the owner’s nonpayment.

{¶ 11} Alternatively, the general contractor may make a conditional promise to pay the subcontractor that is enforceable only if a condition precedent has occurred. Id. A conditional promise to pay is a pay-if-paid payment provision. This provision requires the general contractor to pay the subcontractor only if the [197]*197owner pays the general contractor. Therefore, the risk of the owner’s nonpayment is transferred to the subcontractor. Chapman Excavating Co., Inc. v. Fortney & Weygandt, Inc., 8th Dist. Cuyahoga No. 84005, 2004-Ohio-3867, 2004 WL 1631118, ¶ 22.

{¶ 12} A contract may include either a pay-when-paid or a pay-if-paid contract provision, but a contract cannot contain both.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reissland v. Sage Park Alzheimer's Special Care Ctr.
2025 Ohio 5153 (Ohio Court of Appeals, 2025)
Clark v. Clark
2025 Ohio 159 (Ohio Court of Appeals, 2025)
Caldwell v. Whirlpool Corp.
2024 Ohio 1625 (Ohio Supreme Court, 2024)
Miller v. NWD 355 McConnell, L.L.C.
2023 Ohio 3374 (Ohio Court of Appeals, 2023)
Estate of Mehrer v. Walgreens Specialty Pharmacy
2023 Ohio 2070 (Ohio Court of Appeals, 2023)
Tera, L.L.C. v. Rice Drilling D., L.L.C.
2023 Ohio 273 (Ohio Court of Appeals, 2023)
Eagle Realty Invests., Inc. v. Dumon
2022 Ohio 4106 (Ohio Court of Appeals, 2022)
Ltd. Invest. Group Corp. v. Huntington Natl. Bank
2022 Ohio 3657 (Ohio Court of Appeals, 2022)
WSB Rehab. Servs. Inc. v. Cent. Accounting Sys. Inc.
2022 Ohio 2160 (Ohio Court of Appeals, 2022)
Sanzo Ents., L.L.C. v. Erie Ins. Exchange
2021 Ohio 4268 (Ohio Court of Appeals, 2021)
Razi v. Wedgewood Golf & Country Club
2021 Ohio 4145 (Ohio Court of Appeals, 2021)
Gilman v. Physna, L.L.C.
2021 Ohio 3575 (Ohio Court of Appeals, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
2014 Ohio 3095, 16 N.E.3d 645, 140 Ohio St. 3d 193, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transtar-elec-inc-v-aem-elec-servs-corp-slip-opinion-ohio-2014.