Ricardo Garza v. Marine Transport Lines, Inc., and Third-Party v. Norfolk Shipbuilding & Drydock Corporation, Third-Party

861 F.2d 23, 1989 A.M.C. 228, 1988 U.S. App. LEXIS 14843
CourtCourt of Appeals for the Second Circuit
DecidedNovember 3, 1988
Docket1361, Docket 88-7246
StatusPublished
Cited by202 cases

This text of 861 F.2d 23 (Ricardo Garza v. Marine Transport Lines, Inc., and Third-Party v. Norfolk Shipbuilding & Drydock Corporation, Third-Party) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ricardo Garza v. Marine Transport Lines, Inc., and Third-Party v. Norfolk Shipbuilding & Drydock Corporation, Third-Party, 861 F.2d 23, 1989 A.M.C. 228, 1988 U.S. App. LEXIS 14843 (2d Cir. 1988).

Opinion

BILLINGS, District Judge:

Defendant and third-party plaintiff-appellant Marine Transport Lines, Inc., (“MTL”) seeks review of an order of the United States District Court for the Southern District of New York (Cooper, J.) granting summary judgment to third-party defendant-appellee Norfolk Shipbuilding & Dry-dock Corporation (“Norshipeo”) on MTL’s third-party claim for indemnification and legal fees. The district court granted summary judgment and dismissed the third-party action on the ground that it was time-barred by the terms of the agreement between MTL and Norshipeo. Garza v. Marine Transport Lines, Inc., 680 F.Supp. 624 (S.D.N.Y.1988).

MTL argues on this appeal that the district court erred in concluding that the contract clauses were unambiguous, and that because of that error, the court improperly excluded parol evidence relevant to the meaning of the clauses. MTL also requests that this Court, upon examination of the parol offered, rule upon the meaning of the contract clauses in dispute. We agree that the clauses are ambiguous and therefore reverse and remand for reconsideration. We do not pass on the proper interpretation of the disputed contract clauses because we believe the district court should have the first opportunity to assess these clauses in light of the parol evidence introduced.

BACKGROUND

Plaintiff Ricardo Garza commenced this suit in September, 1984, to recover damages for personal injuries sustained while a *25 crew member on the MARINE CHEMIST, a vessel owned and operated by MTL. The MARINE CHEMIST was repaired by Nor-shipeo pursuant to contract during the period between October 11 and November 10, 1983. On November 17, the second time the ship was docked after the repairs, the starboard head mooring line parted and struck plaintiff, causing serious injuries to his right leg. Plaintiff settled with MTL for $200,000 in June, 1985, and is no longer an active party.

Sometime after the accident, it was determined that the synthetic mooring line that hit Garza had been damaged at the location of the break by contact with hot molten metal. MTL claims that this damage was caused during the repair period at the Norshipco Yard, presumably as a result of repairs involving burning and welding in the vicinity of the mooring line. MTL notified Norshipco of Garza’s claim in May, 1985, and commenced this third-party action against Norshipco in June, 1985, pursuant to leave of the district court. MTL contends that the mooring line parted because it had been damaged by Norshipco employees while the MARINE CHEMIST was at Norshipeo’s shipyard. Norshipco denies liability on the basis of certain so-called “red letter clauses” contained in the written agreement between the parties.

The contract for repair of the MARINE CHEMIST consists of MTL’s invitation to bid with repair specifications dated July 25, 1983, Norshipeo’s bid dated August 26, 1983, and MTL’s letter of September 1, 1983, awarding the job to Norshipco. The repair specifications do not indicate that any work was to be performed on the mooring line involved in the accident, nor was that line purchased from Norshipco.

Norshipeo’s bid contained several exculpatory “red-letter” clauses which are common in maritime repair contracts. The red-letter clause upon which Norshipco grounded the instant summary judgment motion reads as follows:

We shall be discharged from all liability for defective workmanship or material or for loss or damage, unless the same is discovered prior to and claim in writing made to us within sixty (60) days and litigation is commenced within one year after our work has ceased for whatever reason or has been completed, or the vessel has been redelivered, whichever first occurs. 1

The district court agreed with Norshipco that the clause unambiguously imposed a sixty-day limitation period on MTL’s indemnification claim, and dismissed the third-party action because written notice had not been provided within the time required by the clause. The district court refused to consider evidence from “without the four corners of the ship repair contract” as to the meaning or application of the clause. 680 F.Supp. at 628. MTL argues on this appeal, as it did in the court below, that the sixty-day limitation clause did not apply to claims for personal injury. Rather, MTL urges, a different red-letter clause was applicable:

We do not agree to the accident, indemnity, and insurance provisions, if any, contained in your invitation or specifications, relating to liability for death or personal injury, and in such cases we accept only such liability as is imposed upon us by law.

MTL argues that under this clause, the proper limitations period for actions grounded in personal injury would be that “imposed upon us by law”, not the sixty-day period. At the very least, MTL argues, the meaning and application of the contract clauses are ambiguous and parol should have been allowed to determine the application of the clauses. 2 We agree.

*26 DISCUSSION

1. Summary Judgment

Summary judgment may be granted only if the moving party can show that there is “no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed.R.Civ. P. 56(c). Summary judgment is a drastic procedural weapon because “its prophylactic function, when exercised, cuts off a party’s right to present his case to the jury.” Donnelly v. Guion, 467 F.2d 290, 291 (2d Cir.1972). Thus, when the court considers a summary judgment motion, it must draw all reasonable inferences and resolve all ambiguities in favor of the non-moving party. United States v. Diebold, Inc., 369 U.S. 654, 655, 82 S.Ct. 993, 994, 8 L.Ed.2d 176 (1962). The burden is on the moving party to demonstrate the lack of genuine dispute on any material factual issue. Adickes v. S.H. Kress & Co., 398 U.S. 144, 157, 90 S.Ct. 1598, 1608, 26 L.Ed. 2d 142 (1970); Heyman v. Commerce and Industry Insurance Co., 524 F.2d 1317, 1320 (2d Cir.1975).

In this case, the district court concluded that no triable issue of material fact remained because the parol evidence rule barred extrinsic evidence concerning the meaning of the clauses. 680 F.Supp. at 626. Although the district court was correct in proceeding via the summary judgment route once it determined that the clauses were unambiguous, see Tokio Marine & Fire Insurance Co. v. McDonnell Douglas Corp., 617 F.2d 936, 940 (2d Cir.1980), we disagree with the court’s determination that the clauses were unambiguous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pereira v. Brown
S.D. New York, 2022
Kimmel's Coal and Packaging, Inc.
M.D. Pennsylvania, 2021
Brenner v. Brenner
821 F. Supp. 2d 533 (E.D. New York, 2011)
United States v. Toscano
799 F. Supp. 2d 230 (E.D. New York, 2011)
In Re Toscano
799 F. Supp. 2d 230 (E.D. New York, 2011)
Chen-Oster v. Goldman, Sachs & Co.
785 F. Supp. 2d 394 (S.D. New York, 2011)
Consolidated Edison Co. v. Port Authority
734 F. Supp. 2d 542 (S.D. New York, 2010)
LAUDADIO v. Johanns
677 F. Supp. 2d 590 (E.D. New York, 2010)
Wells Fargo Bank, N.A. v. LaSalle Bank National Ass'n
643 F. Supp. 2d 1014 (S.D. Ohio, 2009)
In Re Delta Air Lines, Inc.
381 B.R. 57 (S.D. New York, 2008)
Edwards v. Brookhaven Science Associates, LLC
390 F. Supp. 2d 225 (E.D. New York, 2005)
Saffire Corp. v. Newkidco., LLC.
286 F. Supp. 2d 302 (S.D. New York, 2003)
Penske Logistics, Inc. v. KLLM, Inc.
285 F. Supp. 2d 468 (D. New Jersey, 2003)
Eastman Kodak Co. v. STWB INC.
232 F. Supp. 2d 74 (S.D. New York, 2002)
Municipal Capital Appreciation Partners I, L.P. v. Page
181 F. Supp. 2d 379 (S.D. New York, 2002)
Wayland Investment Fund, LLC v. Millenium Seacarriers, Inc.
111 F. Supp. 2d 450 (S.D. New York, 2000)
Kovian v. Fulton County National Bank & Trust Co.
100 F. Supp. 2d 129 (N.D. New York, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
861 F.2d 23, 1989 A.M.C. 228, 1988 U.S. App. LEXIS 14843, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ricardo-garza-v-marine-transport-lines-inc-and-third-party-v-norfolk-ca2-1988.