Dore & Associates Contracting v. City of Columbus, Ohio

CourtCourt of Appeals for the Sixth Circuit
DecidedMarch 9, 2018
Docket17-3392
StatusUnpublished

This text of Dore & Associates Contracting v. City of Columbus, Ohio (Dore & Associates Contracting v. City of Columbus, Ohio) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dore & Associates Contracting v. City of Columbus, Ohio, (6th Cir. 2018).

Opinion

NOT RECOMMENDED FOR FULL-TEXT PUBLICATION File Name: 18a0121n.06

Case No. 17-3392 FILED Mar 09, 2018 DEBORAH S. HUNT, Clerk UNITED STATES COURT OF APPEALS FOR THE SIXTH CIRCUIT

DORE & ASSOCIATES CONTRACTING, ) INC., ) ) Plaintiff-Appellant, ) ON APPEAL FROM THE UNITED ) STATES DISTRICT COURT FOR v. ) THE SOUTHERN DISTRICT OF ) OHIO CITY OF COLUMBUS, OHIO, ) ) Defendant-Appellee. ) OPINION )

BEFORE: DAUGHTREY, McKEAGUE, and DONALD, Circuit Judges.

BERNICE BOUIE DONALD, Circuit Judge. Plaintiff Dore & Associates

Contracting, Inc. (“Dore”) appeals the district court’s grant of judgment on the pleadings in favor

of Defendant City of Columbus, Ohio (the “City”). We find that the district court was correct in

finding that the plain language of the contract required Dore to perform the work as set forth

therein, regardless of whether Dore agreed with the soundness or necessity of that work. If Dore

wished to alter the scope of the work it contracted to perform, there were prescribed methods for

doing so. Dore failed to employ those mechanisms and was therefore bound to perform the

contract as specified. We AFFIRM the judgment of the district court. Case No. 17-3392 Dore & Associates Contracting, Inc. v. City of Columbus, Ohio

I

On May 3, 2013, the City of Columbus issued a Construction Project Proposal soliciting

bids for the demolition of a building. The Proposal sought bids for the removal and disposal of

asbestos-containing materials (“ACM”) in accordance with the technical specifications for

abatement of hazardous materials (“Hazmat Specs”). The specifications were set forth in the bid

documents and incorporated into the contract, along with the Proposal and solicitation for bids.

The Hazmat Specs referred bidders to “Attachment 1,” a Hazardous Material Assessment Report

(“Lawhon Report”) authored by Lawhon & Associates, a licensed hazardous materials inspection

firm retained by the City. The Lawhon Report estimated 218,000 square feet of asbestos-

containing plaster on the site. The Hazmat Specs stated that the report should not be used for

“bidding or notification purposes.” (RE 1-2, PageID #251.) The Hazmat Specs “included” the

Lawhon Report, but qualified that the report was “ to be used as a reference only.” (RE 12-

1, Hazmat Specs § 1.3(A)(1), PageID #701.) The City expressly disclaimed any responsibility

for the accuracy of the estimates. Section 1.3(B)–(C) of the Specifications provided the

following instructions:

B. Site Investigation. The Hazardous Materials Abatement Contractor shall conduct a site investigation prior to submission of bid to verify asbestos containing materials locations and quantities within the building. The contractor will be responsible for removing and disposing of all asbestos containing materials (except roofing materials) throughout the entire building. The contractor must submit in writing, within 72 hours of bids, any exceptions or discrepancies to this section. If no exceptions are made, the winning contractor will be held responsible for removal and disposal of all asbestos containing materials within the building, identified or not.

C. Removal and Disposal. The Hazardous Material Abatement Contractor, as directed, shall remove and dispose of all regulated asbestos containing materials (RACM), Category II and Category I asbestos containing materials ([e]xcept roofing materials) throughout [the site]. The quantities provided below are only estimations based on the [Lawhon Report]. The City, Architect and [Lawhon] assume no responsibility for the accuracy of these estimates. The contractor shall

-2- Case No. 17-3392 Dore & Associates Contracting, Inc. v. City of Columbus, Ohio

review the [Lawhon] Report in conjunction with site investigations, other specification sections and project drawings and confirm all existing site conditions prior to submission of his/her bid.

(Id.)

The Hazmat Specs also contained “General Notes,” which explained:

1. Listed quantities and locations are only estimates. The contractor is responsible to verify all quantities, special conditions, locations and bidding according to their findings. It is strongly encouraged that the bidding contractor conduct a site investigation to verify materials and quantities prior to bid. Any exceptions to the materials and quantities listed in [the Hazmat Specs] or the [Lawhon Report] must be submitted in writing prior to 72 hours before bids are due. If no exceptions are made, then the contractor will be responsible to remove and dispose of all asbestos containing materials, identified or not within the building.

2. Any materials which have not been listed in the [Lawhon Report] and not tested for asbestos content must be tested by the Hazardous Materials Abatement Contractor. Results of this testing must be submitted to the Project Architect for review and approval. [Lawhon] reserves the right to conduct side-by-side testing to confirm results of the [contractor’s] testing.

(Id., Hazmat Specs § 1.3(H), PageID # 705.)

As a potential bidder, Dore conducted the mandated pre-bid site inspection and

concluded that the Lawhon Report over-estimated the amount of ACM in the building. Five

days before bids were due, the City filed a document entitled Addendum No. 1 (“Addendum”),

which was to “take full and complete precedence over anything stated or shown to the contrary

in them,” and stated that “all of the plaster is confirmed to contain asbestos and is to be

removed.” (RE 1-1, PageID #7.) Dore received the Addendum and did not file an exception or

otherwise object, although it contemporaneously considered the Addendum incorrect and,

according to its pleadings, had no intention of removing all plaster or altering its bid to include

the cost of such abatement. Based on its estimations, Dore submitted a bid of $1,677,000;

-3- Case No. 17-3392 Dore & Associates Contracting, Inc. v. City of Columbus, Ohio

$1,051,100 of Dore’s bid was allotted to hazardous materials abatement. Dore submitted no

exceptions—to the Lawhon Report or otherwise.

On August 2, 2013, the City awarded Dore the contract. Before commencing its work,

Dore hired another consultant to conduct detailed testing of the site plaster. The consultant

determined that there were 43,500 square feet of ACM in the building—similar to Dore’s

estimate. Dore submitted the estimate to the City, which rejected it. In hopes of reversing the

City’s rejection, Dore submitted the consultant’s report to the Ohio Environmental Protection

Agency, which determined that Dore’s estimate was an “accurate and safe finding of ACM.”

(RE 1, PageID #3.) Nevertheless, the City rejected Dore’s second request for approval of its

estimate. Undeterred, Dore notified the City that it would begin abatement in accordance with

its own estimates. The City then threatened to declare Dore in default. Dore relented and began

its abatement of the materials identified in the Lawhon Report, including all plaster, under

protest. In doing so, Dore spent $1,195,794.58 more in material and labor costs than if Dore had

been permitted to abate only the asbestos identified in its own estimates.

On July 31, 2015, Dore filed a breach of contract claim against the City to recover

damages for its additional material and labor costs. On March 14, 2017, the district court

granted the City judgment on the pleadings and dismissed the case. The district court ruled that

the Hazmat Specs, including the Lawhon Report estimates, were incorporated into the contract

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Kottmyer v. Maas
436 F.3d 684 (Sixth Circuit, 2006)
Rachel Krumpelbeck v. Breg Inc.
491 F. App'x 713 (Sixth Circuit, 2012)
National City Bank v. Syatt Realty Group, Inc.
497 F. App'x 465 (Sixth Circuit, 2012)
Fritz v. Charter Township of Com-Stock
592 F.3d 718 (Sixth Circuit, 2010)
United States v. Aluminum Co. of America
148 F.2d 416 (Second Circuit, 1945)
Wood v. Moss
134 S. Ct. 2056 (Supreme Court, 2014)
King v. Burwell
135 S. Ct. 2480 (Supreme Court, 2015)
Motorists Mutual Insurance v. Dandy-Jim, Inc.
912 N.E.2d 659 (Ohio Court of Appeals, 2009)
Mercer v. 3M Precision Optics, Inc.
908 N.E.2d 1016 (Ohio Court of Appeals, 2009)
Blair v. McDonagh
894 N.E.2d 377 (Ohio Court of Appeals, 2008)
Hutton v. Monograms Plus, Inc.
604 N.E.2d 200 (Ohio Court of Appeals, 1992)
Gibbons-Grable Co. v. Gilbane Building Co.
517 N.E.2d 559 (Ohio Court of Appeals, 1986)
Siemaszko v. Firstenergy Nuclear Operating Co.
932 N.E.2d 414 (Ohio Court of Appeals, 2010)
Hersh v. Kelman
104 N.E.2d 35 (Ohio Court of Appeals, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
Dore & Associates Contracting v. City of Columbus, Ohio, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dore-associates-contracting-v-city-of-columbus-ohio-ca6-2018.