Gibbons-Grable Co. v. Gilbane Building Co.

517 N.E.2d 559, 34 Ohio App. 3d 170, 1986 Ohio App. LEXIS 10299
CourtOhio Court of Appeals
DecidedDecember 1, 1986
Docket51150
StatusPublished
Cited by98 cases

This text of 517 N.E.2d 559 (Gibbons-Grable Co. v. Gilbane Building Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gibbons-Grable Co. v. Gilbane Building Co., 517 N.E.2d 559, 34 Ohio App. 3d 170, 1986 Ohio App. LEXIS 10299 (Ohio Ct. App. 1986).

Opinion

Patton, J.

This is an appeal from the decision of the Cuyahoga County Court of Common Pleas granting the defendants’ (Gilbane Building Company et al.) motion to dismiss for lack of subject matter jurisdiction and referring the plaintiffs claims to the American Arbitration Association. The facts giving rise to this appeal are as follows.

This lawsuit arises out of the construction of the Sohio Corporate Headquarters in Cleveland, Ohio. Gilbane Building Company/Polytech Corporation, a defendant-appellee, was the general contractor for the project. In March 1983, the plaintiff-appellant, Gibbons-Grable Company (hereinafter “Gibbons-Grable”), was retained by Gilbane Building Company/Polytech Corporation (a joint venture) to perform concrete work on the project.

On December 20, 1984, Gibbons-Grable filed a complaint against Gil-bane Building Company, Polytech Corporation and Gilbane Building Company/Polytech Corporation (hereinafter collectively referred to as “Gilbane”) alleging breach of contract, fraud, misrepresentation, quantum meruit, and promissory estoppel. Gibbons-Grable sought to recover in counts one through three of the complaint 1 damages in the amount of at least $3,386,588 owed to it by Gilbane for additional costs and expenses allegedly incurred. Paragraph seven of the complaint alleged that:

•“As a direct and proximate result of the actions and/or omissions of defendants as described herein, plaintiff has incurred additional expenses and suffered damages, which damages, as they are presently determinable, are in excess of Two Million Two Hundred Thirty-Five Thousand Dollars ($2,235,000.00).” (Emphasis added.)

Paragraph eight of the complaint further alleged that Gibbons-Grable was due an additional $1,151,588 pursuant to the terms of the contract between Gilbane and Gibbons-Grable and the amendments thereto.

Gibbons-Grable also sought punitive damages on its fraud and misrepresentation claims. Notwithstanding the various legal theories propounded by Gibbons-Grable for recovery, the substance of Gibbons-Grable’s claim was a claim for additional costs and expenses.

On January 30,1985, Gilbane filed a motion to dismiss or to stay this ac *172 tion pending arbitration of Gibbons-Grable’s claim for additional costs. Gilbane had submitted that the contract between it and Gibbons-Grable expressly provided that all claims for additional costs must be arbitrated. Therefore, according to Gilbane, the court lacked jurisdiction to adjudicate Gibbons-Grable’s claims. Gibbons-Grable opposed the motion, arguing among other things that it had never agreed to arbitration of such claims. In its brief, Gibbons-Grable stated that it performed extra work and accelerated its work at Gilbane’s directions, resulting in costs to Gibbons-Grable in excess of $3,000,000.

On October 9, 1985, the court granted Gilbane’s motion to dismiss, citing the court’s lack of subject matter jurisdiction. The court then referred Gibbons-Grable’s remaining claims to the American Arbitration Association.

Gibbons-Grable has timely appealed the court’s finding that its claims are subject to arbitration, reasserting its contention inter alia that it never agreed to arbitration.

I

Gibbons-Grable’s sole assignment of error is as follows:

“The trial court erred in dismissing the action and referring the case to arbitration because there is no arbitration clause in Gibbons-Grable’s contract and the arbitration clause between the owner, Sohio, and the general contractor, Gilbane, does not apply to Gibbons-Grable.”

Gibbons-Grable contends as the basis for its argument that the case should not have been dismissed and referred to arbitration because (1) it never agreed to arbitration and never waived its right to resolve disputes in court; (2) the arbitration provision agreed upon by Gilbane (the prime contractor) and Sohio (the owner) is not binding upon Gibbons-Grable; and (3) Section 4.2.1 of the Gilbane/Sohio contract is inconsistent with Section 7.1.1. Gibbons-Grable also asserts that it is entitled to conduct discovery.

This case involves the interpretation of various contracts between Sohio and Gilbane and between Gilbane and Gibbons-Grable.

Gibbons-Grable has propounded various contentions to support its position that its claims are not subject to arbitration. “The question of whether a controversy is arbitrable under * * * [a] contract is a question for the Court to decide upon an examination of the contract.” Siam Feather & Forest Products Co. v. Midwest Feather Co. (S.D. Ohio 1980), 503 F. Supp. 239, 241, affirmed (C.A. 6, 1981), 663 F. 2d 1073.

The arbitration clause which is at issue in the instant case is contained in Section 4.2.1 of the Supplementary General Conditions of the contract between Gilbane and Sohio. Section 4.2.1 states*

“4.2.1 If the Contractor [Gilbane] claims that additional cost is involved because of, but not limited to, (1) any written interpretation pursuant to Subparagraph 1.1.2 of the General Conditions, (2) any order by the Owner [Sohio] to stop the Work pursuant to Paragraph 3.2 of the General Conditions where the Contractor was not at fault, (3) any written order for a minor change in the Work issued pursuant to Paragraph 4.3, or (4) failure of payment by the Owner pursuant to Paragraph 2.2.4, the Contractor shall make such claim within twenty (20) days after such event has occurred, or such claim shall be disallowed. If Owner and Contractor are unable to dispose of such claim in a mutually agreeable fashion, such claim shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association.” (Emphasis added.)

*173 In construing a contract providing for dispute resolution by arbitration, we are mindful of the policy of the law to favor and encourage arbitration. Brennan v. Brennan (1955), 164 Ohio St. 29, 57 O.O. 71, 128 N.E. 2d 89; Automatic Die & Products Co. (1954), 162 Ohio St. 321, 55 O.O. 195, 123 N.E. 2d 401. “* * * Arbitrability ‘should not be denied unless it may be said with positive assurance that the arbitration clause is not susceptible of an interpretation that covers the asserted dispute. Doubts should be resolved in favor of coverage.’ ” Siam Feather, supra, at 241 (citations omitted).

We will now apply these principles to Gibbons-Grable’s contentions. Gibbons-Grable has argued that it never agreed to arbitrate its claims with Gilbane. The basis of Gibbons-Grable’s complaint is that it has incurred additional costs and is entitled to be compensated for these expenses. These claims for additional costs would be covered by Section 4.2.1 (the arbitration clause) of the contract between Gilbane and Sohio if this section were incorporated by reference into the contract between Gilbane (the prime contractor) and Gibbons-Grable (the subcontractor).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Castle Constr., Co. v. Buretta Constr., Inc.
2025 Ohio 4860 (Ohio Court of Appeals, 2025)
Westlake Servs., L.L.C. v. Chandler
2023 Ohio 3714 (Ohio Court of Appeals, 2023)
Ohio Council 8 v. Marion
2016 Ohio 1144 (Ohio Court of Appeals, 2016)
Jurgensen Co. v. Fairborn
2015 Ohio 5478 (Ohio Court of Appeals, 2015)
Blanchard Valley Health Sys. v. Canterbury Holdings, Inc.
2012 Ohio 5134 (Ohio Court of Appeals, 2012)
Tedeschi v. Atrium Ctrs., L.L.C.
2012 Ohio 2929 (Ohio Court of Appeals, 2012)
State Ex Rel. Rogers v. Philip Morris, Inc., 06ap-1012 (7-24-2008)
2008 Ohio 3690 (Ohio Court of Appeals, 2008)
Lindeman v. Southwestern City School Dist., 08ap-50 (6-30-2008)
2008 Ohio 3303 (Ohio Court of Appeals, 2008)
Miller v. Erie Ins. Co., 5-07-36 (2-11-2008)
2008 Ohio 515 (Ohio Court of Appeals, 2008)
Penton Media, Inc. v. Affiliated FM Insurance
245 F. App'x 495 (Sixth Circuit, 2007)
Urban Associates, Inc. v. Standex Electronics, Inc.
216 F. App'x 495 (Sixth Circuit, 2007)
Barhorst, Inc. v. Hanson Pipe & Products Ohio, Inc.
865 N.E.2d 75 (Ohio Court of Appeals, 2006)
Barto v. Ben D. Imhoff, Inc., Unpublished Decision (12-11-2006)
2006 Ohio 6479 (Ohio Court of Appeals, 2006)
Scott v. Centex Homes, Unpublished Decision (7-31-2006)
2006 Ohio 3928 (Ohio Court of Appeals, 2006)
Olah v. Ganley Chevrolet, Inc., Unpublished Decision (2-16-2006)
2006 Ohio 694 (Ohio Court of Appeals, 2006)
Shumaker v. Saks, Inc.
837 N.E.2d 393 (Ohio Court of Appeals, 2005)
Liese v. Kent State Univ., Unpublished Decision (9-30-2004)
2004 Ohio 5322 (Ohio Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
517 N.E.2d 559, 34 Ohio App. 3d 170, 1986 Ohio App. LEXIS 10299, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gibbons-grable-co-v-gilbane-building-co-ohioctapp-1986.