Castle Constr., Co. v. Buretta Constr., Inc.

2025 Ohio 4860
Ohio Court of Appeals·Decided October 23, 2025·No. 25-COA-006·Published

Opinion

COURT OF APPEALS

ASHLAND COUNTY, OHIO

FIFTH APPELLATE DISTRICT

CASTLE CONSTRUCTION Case No. 25-COA-006 COMPANY, Opinion And Judgment Entry Plaintiff - Appellant Appeal from the Ashland County Court of -vs- Common Pleas, Case No. 23-CIV-130

BURETTA CONSTRUCTION, INC., Judgment: Affirmed Defendant – Appellee Date of Judgment Entry: October 23, 2025

BEFORE: William B. Hoffman; Craig R. Baldwin; Robert G. Montgomery, Judges

APPEARANCES: BRENT L. ENGLISH, for Plaintiff-Appellant; W. BENJAMIN REESE, for Defendant-Appellee.

Montgomery, J.

{¶1} Plaintiff-Appellant, Castle Construction Company, appeals the decision of the Ashland County Court of Common Pleas granting summary judgment in favor of Defendant, Buretta Construction, Inc. For the reasons below, we AFFIRM.

STATEMENT OF THE CASE

{¶2} On July 14, 2023, Castle Construction, Co. (“Appellant”) filed a Complaint in the Ashland County Court of Common Pleas against the Defendant, Buretta Construction, Inc. (“Buretta”) and asserted claims for breach of contract, unjust enrichment, and alleged wrongful assertion of a mechanic's lien. Appellant subsequently moved for Summary Judgment and a Magistrate granted the Motion relating to Buretta’s counterclaims against Appellant but denied the Motion as to Appellant’s claims against

Buretta. The Magistrate issued a Decision concluding that Appellant waived its claims against Buretta by failing to file them with the American Arbitration Association within 180 days of its demand letter, as expressly required by Section 16, “Alternative Dispute Resolution” of the Independent Contractor Agreement between the parties .

{¶3} Pursuant to Civ. R. 53, the Magistrate's Decision notified the parties that either party adversely affected by the Decision must file objections with specificity to preserve issues for appeal. Neither party filed any objections, and, on October 8, 2024, the Court of Common Pleas adopted the Magistrate's Decision. The Court also allowed Buretta to file its own Motion for Summary Judgment. Buretta did so on January 29, 2025, and the Magistrate issued a Decision granting Buretta’s Motion, essentially for the reasons set forth in the Magistrate’s Decision denying Appellant’s Motion. The Magistrate’s Decision again expressly notified the parties that to preserve issues for appeal, a party must file objections. Again, neither party filed any objections to the Magistrate’s Decision. Thus, on February 14, 2025, the Court of Common Pleas adopted the Magistrate’s Decision granting summary judgment to Buretta.

RELEVANT BACKGROUND FACTS

{¶4} On April 12, 2019, Appellant signed a written contract with Edward Rose Development Company (“Rose”), a real estate development and management company, requiring Appellant, in part, to perform rough carpentry work (framing) on a multi-building apartment project called the 24@Bloomfield Apartment Project. Thereafter, on April 22, 2019, Appellant entered into a written Independent Contractor Agreement (the “Agreement”) with Buretta, whereby Buretta agreed to act as the subcontractor and perform the framing work on behalf of Appellant. The Agreement between Appellant and

Buretta contained an “Alternate Dispute Resolution” section governing precisely how the parties would handle any dispute that may arise concerning the project. Section 16 of the Agreement provides as follows:

Alternate Dispute Resolution: Any dispute arising under this agreement or a Project Agreement shall be subject to Mediation and Arbitration. Any party may initiate Arbitration with the American Arbitration Association within 180 days of presenting the other party with a written demand or claim.

The failure to bring a claim within 180 days of providing the written demand, shall constitute a waiver of the claim. The mediation and arbitration shall occur in the State of Ohio.

{¶5} At some point, Appellant became dissatisfied with Buretta and claimed that Buretta failed to complete its work on the project as set forth in the Agreement. On March 13, 2020, Appellant sent Buretta a written Demand for Arbitration. The demand letter states in relevant part that: "Pursuant to the terms of the Independent Contractor Agreement between Castle and Buretta Construction, Inc., we hereby demand arbitration of a dispute about claims that Castle has against you and which Buretta has against Castle related to a project agreement for 24@Bloomfield owned by Edward Rose & Sons." Buretta did not respond to the demand. Following the demand, Appellant did not take any further action until it filed the Complaint in this case on July 14, 2023, more than three years after its initial "demand” letter.

{¶6} In its Answer and Counterclaim, Buretta averred that: "Plaintiff's claim must be dismissed as the clear terms of the Independent Contractor Agreement states in Paragraph 16 that all disputes under the Agreement or a Project Agreement shall be subject to Mediation or Arbitration and the failure to bring such a claim after 180 days constitutes waiver of such claim." Defendant's Answer and Counterclaim, ¶ 36. As stated above, the trial court ultimately granted summary judgment in favor of Buretta. Appellant timely filed the instant appeal.

ASSIGNMENTS OF ERROR

{¶7} “I. THE TRIAL COURT ERRED IN GRANTING SUMMARY JUDGMENT IN FAVOR OF BURETTA CONSTRUCTION, INC., BECAUSE THE INDEPENDENT CONTRACTOR AGREEMENT BETWEEN CASTLE CONSTRUCTION COMPANY AND BURETTA CONSTRUCTION, INC., DID NOT CONTRACTUALLY REDUCE THE STATUTE OF LIMITATIONS REGARDING INTERPRETATION OF THE INDEPENDENT CONTRACTOR AGREEMENT.”

{¶8} “II. THE TRIAL COURT ERRONEOUSLY DETERMINED THAT THE STATUTE OF LIMITATIONS HAD BEEN CONTRACTUALLY REDUCED FROM SIX YEARS TO 368 DAYS.”

{¶9} “III. THE TRIAL COURT ERRED IN FINDING THAT CASTLE CONSTRUCTION COMPANY WAIVED ITS RIGHTS UNDER THE STATUTE OF LIMITATIONS FOR WRITTEN CONTRACTS WHEN, IN FACT, IT DID NO SUCH THING.”

{¶10} “IV. THE TRIAL COURT ERRED IN FINDING THAT A SUBSTANTIALLY REDUCED STATUTE OF LIMITATIONS WAS ENFORCEABLE UNDER THE FACTS OF THIS CASE.”

{¶11} “V. THE BALANCE OF THE INDEPENDENT CONTRACT AGREEMENT SPECIFICALLY PROVIDED FOR LITIGATION AS BEING THE PREFERRED METHODOLOGY OF DISPUTE RESOLUTION.”

ANALYSIS

Failure to Object to Magistrate’s Decision

{¶12} Pursuant to Civ. R. 53(E)(3)(b), “[a] party shall not assign as error on appeal the court's adoption of any finding of fact or conclusion of law unless the party has objected to that finding or conclusion under this rule.” See Brown v. Zurich US, 2002- Ohio-6099, ¶ 26; Clendenen v. Fannin Realty, Inc., 2002-Ohio-4548, ¶ 17; McBroom v. Bob-Boyd Lincoln Mercury, Inc. (Oct. 22, 1998), Franklin App. No. 98AP-229. Thus,

“ ‘Civ.R. 53(E) imposes an affirmative duty on the parties to make timely, specific objections in writing to the trial court, identifying any error of fact or law in the magistrate's decision.” ’ State ex rel. Alston v. Indus. Comm., 2002-Ohio-4720, ¶ 4 (citations omitted); In re G.S., 2011-Ohio-2487, ¶ 6 (10th Dist.); see also Ohio Receivables, LLC v. Durunner, 2013-Ohio-5514, ¶ 25 (5th Dist.).

{¶13} The staff notes to Civ.R. 53 provide that “[d]ivision (E)(3)(b) * * * reinforces the finality of trial court proceedings by providing that failure to object constitutes a waiver on appeal of a matter which could have been raised by objection.” As such, under Civ.R. 53, a party’s failure to file specific written objections to a magistrate's decision within the 14-day deadline generally forfeits that party’s right to challenge the decision on appeal. In construing Civ.R. 53, the Ohio Supreme Court has “held that the failure to file objections to the magistrate's decision under Civ.R. 53(E)(3)(b) constitutes the waiver of the right to appellate review ‘of all but plain error.’ “Uretsky v. Uretsky, 2003-Ohio-1455, ¶ 7. However, in appeals of civil cases, the plain error doctrine is not favored and may be applied only in extremely rare cases. Id., ¶ 8, citing Goldfuss v. Davidson, 79 Ohio St.3d 116 (1997), syllabus.

Free access — add to your briefcase to read the full text and ask questions with AI

Castle Constr., Co. v. Buretta Constr., Inc., 2025 Ohio 4860 (Ohio Ct. App. 2025).

2025 Ohio 4860 (Castle Constr., Co. v. Buretta Constr., Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ohio Receivables, L.L.C. v. Durunner
2013 Ohio 5514 (Ohio Court of Appeals, 2013)
Brads v. First Baptist Church
624 N.E.2d 737 (Ohio Court of Appeals, 1993)
Neubrander v. Dean Witter Reynolds, Inc.
610 N.E.2d 1089 (Ohio Court of Appeals, 1992)
Gibbons-Grable Co. v. Gilbane Building Co.
517 N.E.2d 559 (Ohio Court of Appeals, 1986)
Porterfield v. Bruner Land Co., Inc.
2017 Ohio 9045 (Ohio Court of Appeals, 2017)
Mid Ohio Coal Co. v. Brown
2018 Ohio 1934 (Ohio Court of Appeals, 2018)
Skivolocki v. East Ohio Gas Co.
313 N.E.2d 374 (Ohio Supreme Court, 1974)
Alexander v. Buckeye Pipe Line Co.
374 N.E.2d 146 (Ohio Supreme Court, 1978)
Schade v. Carnegie Body Co.
436 N.E.2d 1001 (Ohio Supreme Court, 1982)
Kraly v. Vannewkirk
635 N.E.2d 323 (Ohio Supreme Court, 1994)
Goldfuss v. Davidson
679 N.E.2d 1099 (Ohio Supreme Court, 1997)
ABM Farms, Inc. v. Woods
692 N.E.2d 574 (Ohio Supreme Court, 1998)
Gerig v. Kahn
95 Ohio St. 3d 478 (Ohio Supreme Court, 2002)
Hoague v. Cottrill Servs., L.L.C.
2024 Ohio 531 (Ohio Court of Appeals, 2024)
Coinbase v. Suski
602 U.S. 143 (Supreme Court, 2024)
Cincinnati Indemn. Co. v. Martin
1999 Ohio 322 (Ohio Supreme Court, 1999)