Castle Constr., Co. v. Buretta Constr., Inc.

2025 Ohio 4860
CourtOhio Court of Appeals
DecidedOctober 23, 2025
Docket25-COA-006
StatusPublished

This text of 2025 Ohio 4860 (Castle Constr., Co. v. Buretta Constr., Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Castle Constr., Co. v. Buretta Constr., Inc., 2025 Ohio 4860 (Ohio Ct. App. 2025).

Opinion

[Cite as Castle Constr., Co. v. Buretta Constr., Inc., 2025-Ohio-4860.]

COURT OF APPEALS ASHLAND COUNTY, OHIO FIFTH APPELLATE DISTRICT

CASTLE CONSTRUCTION Case No. 25-COA-006 COMPANY, Opinion And Judgment Entry Plaintiff - Appellant Appeal from the Ashland County Court of -vs- Common Pleas, Case No. 23-CIV-130

BURETTA CONSTRUCTION, INC., Judgment: Affirmed

Defendant – Appellee Date of Judgment Entry: October 23, 2025

BEFORE: William B. Hoffman; Craig R. Baldwin; Robert G. Montgomery, Judges

APPEARANCES: BRENT L. ENGLISH, for Plaintiff-Appellant; W. BENJAMIN REESE, for Defendant-Appellee.

Montgomery, J.

{¶1} Plaintiff-Appellant, Castle Construction Company, appeals the decision of

the Ashland County Court of Common Pleas granting summary judgment in favor of

Defendant, Buretta Construction, Inc. For the reasons below, we AFFIRM.

STATEMENT OF THE CASE

{¶2} On July 14, 2023, Castle Construction, Co. (“Appellant”) filed a Complaint

in the Ashland County Court of Common Pleas against the Defendant, Buretta

Construction, Inc. (“Buretta”) and asserted claims for breach of contract, unjust

enrichment, and alleged wrongful assertion of a mechanic's lien. Appellant subsequently

moved for Summary Judgment and a Magistrate granted the Motion relating to Buretta’s

counterclaims against Appellant but denied the Motion as to Appellant’s claims against Buretta. The Magistrate issued a Decision concluding that Appellant waived its claims

against Buretta by failing to file them with the American Arbitration Association within 180

days of its demand letter, as expressly required by Section 16, “Alternative Dispute

Resolution” of the Independent Contractor Agreement between the parties .

{¶3} Pursuant to Civ. R. 53, the Magistrate's Decision notified the parties that

either party adversely affected by the Decision must file objections with specificity to

preserve issues for appeal. Neither party filed any objections, and, on October 8, 2024,

the Court of Common Pleas adopted the Magistrate's Decision. The Court also allowed

Buretta to file its own Motion for Summary Judgment. Buretta did so on January 29, 2025,

and the Magistrate issued a Decision granting Buretta’s Motion, essentially for the

reasons set forth in the Magistrate’s Decision denying Appellant’s Motion. The

Magistrate’s Decision again expressly notified the parties that to preserve issues for

appeal, a party must file objections. Again, neither party filed any objections to the

Magistrate’s Decision. Thus, on February 14, 2025, the Court of Common Pleas adopted

the Magistrate’s Decision granting summary judgment to Buretta.

RELEVANT BACKGROUND FACTS

{¶4} On April 12, 2019, Appellant signed a written contract with Edward Rose

Development Company (“Rose”), a real estate development and management company,

requiring Appellant, in part, to perform rough carpentry work (framing) on a multi-building

apartment project called the 24@Bloomfield Apartment Project. Thereafter, on April 22,

2019, Appellant entered into a written Independent Contractor Agreement (the

“Agreement”) with Buretta, whereby Buretta agreed to act as the subcontractor and

perform the framing work on behalf of Appellant. The Agreement between Appellant and Buretta contained an “Alternate Dispute Resolution” section governing precisely how the

parties would handle any dispute that may arise concerning the project. Section 16 of the

Agreement provides as follows:

Alternate Dispute Resolution: Any dispute arising under this agreement

or a Project Agreement shall be subject to Mediation and Arbitration. Any

party may initiate Arbitration with the American Arbitration Association

within 180 days of presenting the other party with a written demand or claim.

The failure to bring a claim within 180 days of providing the written demand,

shall constitute a waiver of the claim. The mediation and arbitration shall

occur in the State of Ohio.

{¶5} At some point, Appellant became dissatisfied with Buretta and claimed that

Buretta failed to complete its work on the project as set forth in the Agreement. On

March 13, 2020, Appellant sent Buretta a written Demand for Arbitration. The demand

letter states in relevant part that: "Pursuant to the terms of the Independent Contractor

Agreement between Castle and Buretta Construction, Inc., we hereby demand arbitration

of a dispute about claims that Castle has against you and which Buretta has against

Castle related to a project agreement for 24@Bloomfield owned by Edward Rose &

Sons." Buretta did not respond to the demand. Following the demand, Appellant did not

take any further action until it filed the Complaint in this case on July 14, 2023, more than

three years after its initial "demand” letter.

{¶6} In its Answer and Counterclaim, Buretta averred that: "Plaintiff's claim must

be dismissed as the clear terms of the Independent Contractor Agreement states in

Paragraph 16 that all disputes under the Agreement or a Project Agreement shall be subject to Mediation or Arbitration and the failure to bring such a claim after 180 days

constitutes waiver of such claim." Defendant's Answer and Counterclaim, ¶ 36. As stated

above, the trial court ultimately granted summary judgment in favor of Buretta. Appellant

timely filed the instant appeal.

ASSIGNMENTS OF ERROR

{¶7} “I. THE TRIAL COURT ERRED IN GRANTING SUMMARY JUDGMENT IN FAVOR OF BURETTA CONSTRUCTION, INC., BECAUSE THE INDEPENDENT CONTRACTOR AGREEMENT BETWEEN CASTLE CONSTRUCTION COMPANY AND BURETTA CONSTRUCTION, INC., DID NOT CONTRACTUALLY REDUCE THE STATUTE OF LIMITATIONS REGARDING INTERPRETATION OF THE INDEPENDENT CONTRACTOR AGREEMENT.”

{¶8} “II. THE TRIAL COURT ERRONEOUSLY DETERMINED THAT THE STATUTE OF LIMITATIONS HAD BEEN CONTRACTUALLY REDUCED FROM SIX YEARS TO 368 DAYS.”

{¶9} “III. THE TRIAL COURT ERRED IN FINDING THAT CASTLE CONSTRUCTION COMPANY WAIVED ITS RIGHTS UNDER THE STATUTE OF LIMITATIONS FOR WRITTEN CONTRACTS WHEN, IN FACT, IT DID NO SUCH THING.”

{¶10} “IV. THE TRIAL COURT ERRED IN FINDING THAT A SUBSTANTIALLY REDUCED STATUTE OF LIMITATIONS WAS ENFORCEABLE UNDER THE FACTS OF THIS CASE.”

{¶11} “V. THE BALANCE OF THE INDEPENDENT CONTRACT AGREEMENT SPECIFICALLY PROVIDED FOR LITIGATION AS BEING THE PREFERRED METHODOLOGY OF DISPUTE RESOLUTION.” ANALYSIS

Failure to Object to Magistrate’s Decision

{¶12} Pursuant to Civ. R. 53(E)(3)(b), “[a] party shall not assign as error on appeal

the court's adoption of any finding of fact or conclusion of law unless the party has

objected to that finding or conclusion under this rule.” See Brown v. Zurich US, 2002-

Ohio-6099, ¶ 26; Clendenen v. Fannin Realty, Inc., 2002-Ohio-4548, ¶ 17; McBroom v.

Bob-Boyd Lincoln Mercury, Inc. (Oct. 22, 1998), Franklin App. No. 98AP-229. Thus, “ ‘Civ.R. 53(E) imposes an affirmative duty on the parties to make timely, specific

objections in writing to the trial court, identifying any error of fact or law in the magistrate's

decision.” ’ State ex rel. Alston v. Indus. Comm., 2002-Ohio-4720, ¶ 4 (citations omitted);

In re G.S., 2011-Ohio-2487, ¶ 6 (10th Dist.); see also Ohio Receivables, LLC v. Durunner,

2013-Ohio-5514, ¶ 25 (5th Dist.).

{¶13} The staff notes to Civ.R. 53 provide that “[d]ivision (E)(3)(b) * * * reinforces

the finality of trial court proceedings by providing that failure to object constitutes a waiver

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ohio Receivables, L.L.C. v. Durunner
2013 Ohio 5514 (Ohio Court of Appeals, 2013)
Brads v. First Baptist Church
624 N.E.2d 737 (Ohio Court of Appeals, 1993)
Neubrander v. Dean Witter Reynolds, Inc.
610 N.E.2d 1089 (Ohio Court of Appeals, 1992)
Gibbons-Grable Co. v. Gilbane Building Co.
517 N.E.2d 559 (Ohio Court of Appeals, 1986)
Porterfield v. Bruner Land Co., Inc.
2017 Ohio 9045 (Ohio Court of Appeals, 2017)
Mid Ohio Coal Co. v. Brown
2018 Ohio 1934 (Ohio Court of Appeals, 2018)
Skivolocki v. East Ohio Gas Co.
313 N.E.2d 374 (Ohio Supreme Court, 1974)
Alexander v. Buckeye Pipe Line Co.
374 N.E.2d 146 (Ohio Supreme Court, 1978)
Schade v. Carnegie Body Co.
436 N.E.2d 1001 (Ohio Supreme Court, 1982)
Kraly v. Vannewkirk
635 N.E.2d 323 (Ohio Supreme Court, 1994)
Goldfuss v. Davidson
679 N.E.2d 1099 (Ohio Supreme Court, 1997)
ABM Farms, Inc. v. Woods
692 N.E.2d 574 (Ohio Supreme Court, 1998)
Gerig v. Kahn
95 Ohio St. 3d 478 (Ohio Supreme Court, 2002)
Hoague v. Cottrill Servs., L.L.C.
2024 Ohio 531 (Ohio Court of Appeals, 2024)
Coinbase v. Suski
602 U.S. 143 (Supreme Court, 2024)
Cincinnati Indemn. Co. v. Martin
1999 Ohio 322 (Ohio Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
2025 Ohio 4860, Counsel Stack Legal Research, https://law.counselstack.com/opinion/castle-constr-co-v-buretta-constr-inc-ohioctapp-2025.