Uniroyal, Inc. v. A. Epstein and Sons, Inc., George A. Fuller & Company, Inc., Additional

428 F.2d 523
CourtCourt of Appeals for the Seventh Circuit
DecidedJuly 14, 1970
Docket17794
StatusPublished
Cited by15 cases

This text of 428 F.2d 523 (Uniroyal, Inc. v. A. Epstein and Sons, Inc., George A. Fuller & Company, Inc., Additional) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Uniroyal, Inc. v. A. Epstein and Sons, Inc., George A. Fuller & Company, Inc., Additional, 428 F.2d 523 (7th Cir. 1970).

Opinion

KERNER, Circuit Judge.

The sole issue involved in this appeal is whether a contract between the general contractor, A. Epstein and Sons, Inc., (appellant-Epstein) and the subcontractor, George A. Fuller and Company, Inc., (appellee-Fuller) required the subcontractor to participate in an arbitration proceeding between the owner, Uniroyal, Inc., (Uniroyal) and the contractor to arbitrate the owner’s claim for damáges arising out of an alleged failure of performance by the subcontractor. The trial court held that the contract between the contractor and the subcontractor did not require that the subcontractor be made a party to the arbitration proceeding between the owner and the contractor. We disagree and reverse and remand.

In September of 1952 Uniroyal awarded a contract to Epstein for the construction of an office building and warehouse in Vernon, California. Previous to the finalization date of this contract ■ — -March 12, 1953- — Epstein entered into a subcontract with Fuller. (January 12, 1953) The contract between Epstein and Fuller provided in relevant part:

Section 5. The Contractor and Subcontractor Agree to be bound by the terms of the Agreement, the General Conditions, Drawings and Specifications as far as applicable to this subcontract, and also by the following provisions:
The Subcontractor agrees:
(a) To be bound to the Contractor by the terms of the Agreement, General Conditions, Drawings and Specifications, and to assume toward him all the obligations and responsibilities that he, by those documents, assumes toward the Owner. «•***•**
The Contractor agrees:
(d) To be bound to the Subcontractor by all the obligations that the Owner assumes to the Contractor under the Agreement, General Conditions, Drawings and Specifications, and by all the provisions thereof according remedies and redress to the Contractor from the Owner.
The Contractor and the Subcontractor agree that:
(o) In the matter of arbitration, their rights and obligations and all procedure shall be analogous to those set forth in this Contract.

The following provisions are part of a document entitled “GENERAL CONDITIONS OF THE CONTRACT” which was incorporated by reference into the subcontract:

20. Correction of work after final payment:
Neither the final certificate nor payment nor any provision in the Contract Documents shall relieve the Contractor of responsibility for faulty materials or workmanship and, unless otherwise specified, he shall remedy *525 any defects due thereto and pay for any damage to the other work resulting therefrom, which shall appear within a period of one year from the date of substantial completion. The Owner shall give notice of observed defects with reasonable promptness. All questions arising under this article shall be decided by the Engineer subject to arbitration.
31. Damages:
If either party to this contract should suffer damage in any manner because of any wrongful act or neglect of the other' party or of anyone employed by him, then he shall be reimbursed by the other party for such damage.
Claims under this clause shall be made in writing to the party liable within a reasonable time of final payment, except as expressly stipulated otherwise in the case of faulty work or materials, and shall be adjusted by agreement or arbitration.
40. ARBITRATION:
Unless otherwise provided in the Agreement all disputes, claims or questions subject to arbitration under this contract shall be submitted to arbitration in accordance with the provisions, then obtaining, of the Standard Form of Arbitration Procedure of the American Institute of Architects, and this agreement shall be specifically enforceable under the prevailing arbitration law, and judgment upon the award rendered may be entered in the highest court of the forum, state or federal, having jurisdiction. It is mutually agreed that the decision of the arbitrators shall be a condition precedent to any right or legal action that either party may have against the other.
The Contractor shall, not cause delay of the work during any arbitration proceeding, except by agreement with the Owner.
Notice of the demand for arbitration of a dispute shall be filed in writing with the Engineer and the other party to the contract. If the arbitration is an appeal from the Engineer’s decision, the demand therefor shall be made within ten days of its receipt; in any other case the demand for arbitration shall be made within a reasonable time after the dispute has arisen; in no case, however, shall the demand be made later than the time of final payment, except as otherwise expressly stipulated in the contract.
The arbitrators, if they deem that the case requires it, are authorized to award to the party whose contention is sustained, such sums as they or a majority of them shall deem proper to compensate it for the time and expense incident to the proceeding and, if the arbitration was demanded without reasonable cause, they may award damages for delay. The arbitrators shall fix their own compensation, unless otherwise provided by agreement, and shall assess the costs and charges of the proceeding upon either or both parties.

On November 2, 1953, the contracted work between Uniroyal and Epstein was completed and final payment was made by Uniroyal. Thirteen years later, in November of 1966, Uniroyal notified Epstein that a section of the roof on the constructed building had collapsed. And the following January, Uniroyal claims that all of the trusses supporting the roof were defective.

Uniroyal then filed a petition in the district court to compel Epstein to arbitrate pursuant to their contract of March, 1953, which provided in relevant part:

17.0 ARBITRATION:
Any controversy or claim arising out of or relating to this Agreement, or in the breach thereof, shall be settled by arbitration, in accordance with *526 the Rules, then obtaining of the American Arbitration Association and judgment upon the award rendered may be entered in any court having jurisdiction thereof. All arbitration hearings pursuant to this Section shall be conducted at Chicago, Illinois, unless otherwise agreed upon by the parties.

The district court found that Section 17 of the agreement between Uniroyal and Epstein

“was intended to apply to disputes arising out of such matters as allegedly defective construction of major portions of the building, even if the defects were not discovered until after the work was completed and full payment was made”

and ordered Epstein to proceed to arbitration. 1 Epstein relying on 5(a) 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Insurance Co. v. Siena Construction Corp.
23 Mass. L. Rptr. 232 (Massachusetts Superior Court, 2007)
Slaught v. Bencomo Roofing Co.
25 Cal. App. 4th 744 (California Court of Appeal, 1994)
3A Industries, Inc. v. Turner Construction Co.
869 P.2d 65 (Court of Appeals of Washington, 1993)
Massachusetts Electrical Systems, Inc. v. R. W. Granger & Sons, Inc.
594 N.E.2d 545 (Massachusetts Appeals Court, 1992)
Turner Construction Co. v. Midwest Curtainwalls, Inc.
543 N.E.2d 249 (Appellate Court of Illinois, 1989)
Gibbons-Grable Co. v. Gilbane Building Co.
517 N.E.2d 559 (Ohio Court of Appeals, 1986)
Commonwealth v. Lord International, Inc.
2 N. Mar. I. Commw. 828 (Northern Mariana Islands Commonwealth Trial Court, 1986)
Maxum Foundations, Inc. v. Salus Corp.
779 F.2d 974 (Fourth Circuit, 1985)
Gavlik Construction Co. v. H. F. Campbell Co.
526 F.2d 777 (Third Circuit, 1975)
Gavlik Construction Co. v. H. F. Campbell Co.
389 F. Supp. 551 (W.D. Pennsylvania, 1975)
Bartley, Inc. v. Jefferson Parish School Board
302 So. 2d 280 (Supreme Court of Louisiana, 1974)
Long v. Marion Manufacturing Company
402 F. Supp. 69 (D. South Carolina, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
428 F.2d 523, Counsel Stack Legal Research, https://law.counselstack.com/opinion/uniroyal-inc-v-a-epstein-and-sons-inc-george-a-fuller-company-ca7-1970.