Massachusetts Electrical Systems, Inc. v. R. W. Granger & Sons, Inc.
This text of 594 N.E.2d 545 (Massachusetts Electrical Systems, Inc. v. R. W. Granger & Sons, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
The plaintiff, a subcontractor subject to G. L. c. 149, § 44F, brought an action against the defendant general contractor (Granger) and its surety1 alleging breach of contract with respect to the construction of a school for the town of Harwich. Granger filed an answer and a motion to stay the action and compel arbitration. This appeal is from the denial of Granger’s motion. See G. L. c. 251, § 18. We reverse.
The construction contract between Granger and the town included an arbitration provision,2 and by virtue of the statutory form of subcontract required by G. L. c. 149, § 44F(4)(c) (1988 ed.), set forth in the margin,3 the provisions of the contract between Granger and the town were incorporated into the subcontract. See Exchange Mut. Ins. Co. v. Haskell Co., 742 F.2d 274, 275 (6th Cir. 1984), and Maxum Foundations, Inc. v. Salus Corp., 779 F.2d 974, 979, 980 (4th Cir. 1985), where, on almost identical language, the court held the subcontractor bound by the arbitration clause in the prime contract.
Buttressed by the “strong public policy favoring arbitration as an expe[983]*983ditious alternative to litigation for settling commercial disputes,” Danvers v. Wexler Constr. Co., 12 Mass. App. Ct. 160, 161, 163 (1981), courts generally hold that where a subcontract (or a performance bond) incorporates the prime contract, the subcontractor (or the surety) is bound by an arbitration clause contained in the prime contract. See, e.g., Kearsarge Metallurgical Corp. v. Peerless Ins. Co., 383 Mass 162, 166-167, 170 and 167 n. 8 (1981) (construing New Hampshire law but where there was no specific New Hampshire case on point); Exchange Mut. Ins. Co. v. Haskell Co., 742 F.2d at 276; Maxum Foundations, Inc. v. Salus Corp., 779 F.2d at 980; United States Fid. & Guar. Co. v. W. Point Constr. Co., 837 F.2d 1507, 1508 (11th Cir. 1988); Thomas O’Connor & Co. v. Insurance Co. of N. Am., 697 F. Supp. 563 (D. Mass. 1988); Hoffman v. Fidelity & Deposit Co., 734 F. Supp. 192, 194-195 (D. N.J. 1990). See also Uniroyal, Inc. v. A. Epstein & Sons, 428 F.2d 523, 526-527 (7th Cir. 1970); Compania Espanola de Petroleos v. Nereus Shipping, 527 F.2d 966, 973-74 (2d Cir. 1975), cert. denied, 426 U.S. 936 (1976); Acret, Construction Arbitration Handbook § 5.05 (1985 & 1991 Supp.), and cases cited. The plaintiff has presented no meritorious reason to apply a different rule here.
Accordingly, the parties should have been directed to proceed to arbitration, and the action should have been stayed. See G. L. c. 251, §§ 2(c) and 2(d); Danvers v. Wexler Constr. Co., 12 Mass. App. Ct. at 161-162. The order denying a stay of the action is reversed, and the matter is remanded to the Superior Court for the entry of an order directing the parties to proceed to arbitration.
So ordered.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
594 N.E.2d 545, 32 Mass. App. Ct. 982, 1992 Mass. App. LEXIS 548, Counsel Stack Legal Research, https://law.counselstack.com/opinion/massachusetts-electrical-systems-inc-v-r-w-granger-sons-inc-massappct-1992.