Massachusetts Electrical Systems, Inc. v. R. W. Granger & Sons, Inc.

594 N.E.2d 545, 32 Mass. App. Ct. 982, 1992 Mass. App. LEXIS 548
Massachusetts Appeals Court·Decided June 22, 1992·No. No. 91-P-625·Published·Cited by 6 cases

Opinion

The plaintiff, a subcontractor subject to G. L. c. 149, § 44F, brought an action against the defendant general contractor (Granger) and its surety1 alleging breach of contract with respect to the construction of a school for the town of Harwich. Granger filed an answer and a motion to stay the action and compel arbitration. This appeal is from the denial of Granger’s motion. See G. L. c. 251, § 18. We reverse.

The construction contract between Granger and the town included an arbitration provision,2 and by virtue of the statutory form of subcontract required by G. L. c. 149, § 44F(4)(c) (1988 ed.), set forth in the margin,3 the provisions of the contract between Granger and the town were incorporated into the subcontract. See Exchange Mut. Ins. Co. v. Haskell Co., 742 F.2d 274, 275 (6th Cir. 1984), and Maxum Foundations, Inc. v. Salus Corp., 779 F.2d 974, 979, 980 (4th Cir. 1985), where, on almost identical language, the court held the subcontractor bound by the arbitration clause in the prime contract.

Buttressed by the “strong public policy favoring arbitration as an expe[983] ditious alternative to litigation for settling commercial disputes,” Danvers v. Wexler Constr. Co., 12 Mass. App. Ct. 160, 161, 163 (1981), courts generally hold that where a subcontract (or a performance bond) incorporates the prime contract, the subcontractor (or the surety) is bound by an arbitration clause contained in the prime contract. See, e.g., Kearsarge Metallurgical Corp. v. Peerless Ins. Co., 383 Mass 162, 166-167, 170 and 167 n. 8 (1981) (construing New Hampshire law but where there was no specific New Hampshire case on point); Exchange Mut. Ins. Co. v. Haskell Co., 742 F.2d at 276; Maxum Foundations, Inc. v. Salus Corp., 779 F.2d at 980; United States Fid. & Guar. Co. v. W. Point Constr. Co., 837 F.2d 1507, 1508 (11th Cir. 1988); Thomas O’Connor & Co. v. Insurance Co. of N. Am., 697 F. Supp. 563 (D. Mass. 1988); Hoffman v. Fidelity & Deposit Co., 734 F. Supp. 192, 194-195 (D. N.J. 1990). See also Uniroyal, Inc. v. A. Epstein & Sons, 428 F.2d 523, 526-527 (7th Cir. 1970); Compania Espanola de Petroleos v. Nereus Shipping, 527 F.2d 966, 973-74 (2d Cir. 1975), cert. denied, 426 U.S. 936 (1976); Acret, Construction Arbitration Handbook § 5.05 (1985 & 1991 Supp.), and cases cited. The plaintiff has presented no meritorious reason to apply a different rule here.

Charles A. Plunkett for the defendant. Martin Fisch for the plaintiff.

Accordingly, the parties should have been directed to proceed to arbitration, and the action should have been stayed. See G. L. c. 251, §§ 2(c) and 2(d); Danvers v. Wexler Constr. Co., 12 Mass. App. Ct. at 161-162. The order denying a stay of the action is reversed, and the matter is remanded to the Superior Court for the entry of an order directing the parties to proceed to arbitration.

So ordered.

Footnotes

Free access — add to your briefcase to read the full text and ask questions with AI

Massachusetts Electrical Systems, Inc. v. R. W. Granger & Sons, Inc., 594 N.E.2d 545, 32 Mass. App. Ct. 982, 1992 Mass. App. LEXIS 548 (Mass. Ct. App. 1992).

594 N.E.2d 545 (Massachusetts Electrical Systems, Inc. v. R. W. Granger & Sons, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Costa v. Brait Builders Corp.
972 N.E.2d 449 (Massachusetts Supreme Judicial Court, 2012)
C & I Steel, LLC v. Travelers Casualty & Surety Co. of America
876 N.E.2d 442 (Massachusetts Appeals Court, 2007)
Travelers Casualty & Surety Co. of America, Inc. v. Long Bay Management Co.
792 N.E.2d 1013 (Massachusetts Appeals Court, 2003)
Town of Wellesley v. D&C Construction Co.
8 Mass. L. Rptr. 300 (Massachusetts Superior Court, 1998)
Slaught v. Bencomo Roofing Co.
25 Cal. App. 4th 744 (California Court of Appeal, 1994)