Hartford Accident & Indemnity Co. v. Scarlett Harbor Associates Ltd. Partnership

695 A.2d 153, 346 Md. 122, 1997 Md. LEXIS 78
CourtCourt of Appeals of Maryland
DecidedJune 18, 1997
Docket65, Sept. Term, 1996
StatusPublished
Cited by138 cases

This text of 695 A.2d 153 (Hartford Accident & Indemnity Co. v. Scarlett Harbor Associates Ltd. Partnership) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartford Accident & Indemnity Co. v. Scarlett Harbor Associates Ltd. Partnership, 695 A.2d 153, 346 Md. 122, 1997 Md. LEXIS 78 (Md. 1997).

Opinion

RODOWSKY, Judge.

We granted certiorari to review the holding concerning arbitrability made by the Court of Special Appeals in Hartford Accident & Indem. Co. v. Scarlett Harbor Assocs. Ltd. Partnership, 109 Md.App. 217, 674 A.2d 106 (1996). A condominium developer’s agreement with a construction contractor included a provision for arbitration between those parties. The contract containing the arbitration provision had been incorporated by reference into the contractor’s performance bond. The court held that the developer had not agreed to arbitrate its claim against the bond with the surety. As explained below, we agree with the holding by the Court of Special Appeals.

*124 This dispute involves the large residential condominium in the Scarlett Place complex in the Inner Harbor area of Baltimore City. For purposes of this opinion we shall consider that Scarlett Place was developed by the respondents, Scarlett Harbor Associates Limited Partnership and its general partners, Leroy Merritt and Merritt Operations Corporation (collectively, SHALP). 1 The construction with which we are concerned utilized the construction manager process. Leonard A. Kraus Co., Inc. (Kraus) was engaged by SHALP to furnish and install metal framing and Gypsum sheathing and to perform other work. Their August 1986 contract refers to SHALP as “Owner” and to Kraus as “Contractor.” 2

General Conditions ¶ 7.9.1 of the SHALP-Kraus contract provided in part for arbitration under the American Arbitration Association Construction Industry Rules of “[a]ll claims, disputes and other matters in question between the Contractor and the Owner arising out of or relating to the Contract Documents or the breach thereof____” 3

*125 The contract required Kraus to obtain a performance bond in the amount of 100% of the contract price. Petitioner, Hartford Accident & Indemnity Company (The Hartford), issued the bond to Kraus on its “Subcontract Performance Bond Form A.” All parties to this certiorari review have treated SHALP as the obligee of the bond, and we shall do the same. 4 The bond contains, in relevant part, the following recital:

“Whereas, Principal has by written agreement ... entered into a subcontract with Obligee for Renovation and addition to Scarlett Seed Building—Light Gauge Metal Framing (Scarlett Place Phase II & III) ... which subcontract is by reference made a part hereof, and is hereinafter referred to as the subcontract.”

(Emphasis added).

In January 1993 the action out of which the issue before us arose was brought against SHALP and others in the Circuit Court for Baltimore County by Scarlett Place Residential *126 Condominium, Inc., the council of unit owners of the residential condominium. SHALP impleaded a number of third-party defendants, including Kraus and The Hartford. Both moved to compel SHALP to arbitrate its claims against them while proceedings in the circuit court on the third-party claims against them were stayed. The circuit court ordered arbitration between SHALP and Kraus, but the court denied The Hartford’s motion to compel arbitration on the third-party claim against it. The Hartford appealed from that denial to the Court of Special Appeals. 5

The Hartford’s appeal was consolidated with the appeals from the final judgment disposing of the remaining claims in the action. Hartford Accident & Indem. Co., 109 Md.App. 217, 674 A.2d 106. The Hartford contended that incorporating by reference the SHALP-Kraus contract into the bond “ ‘clearly’ shows that the parties intended that claims under the bond would be decided in arbitration.” Id. at 292, 674 A.2d at 143. The Court of Special Appeals disagreed, taking the view that “Kraus’s subcontract was incorporated simply to establish the primary obligation on which Hartford’s secondary obligation would depend.” Id. Although recognizing that a majority of decisions from other jurisdictions had reached a different result, the court was not persuaded by either the number or the rationale of those decisions and affirmed the circuit court. Id. at 295-96, 674 A.2d at 144.

We granted The Hartford’s petition for certiorari which presents the following question:

“May a surety that issued a performance bond which incorporated by reference a mandatory arbitration provision from a subcontract between the obligee and the principal *127 enforce the arbitration agreement against the obligee in an action on the bond?”

The question presented is answered by a return to the fundamentals recently restated for the Court by Judge Chasanow in Curtis G. Testerman Co. v. Buck, 340 Md. 569, 667 A.2d 649 (1995). There we said:

“Arbitration is a ‘process whereby parties voluntarily agree to substitute a private tribunal for the public tribunal otherwise available to them. * * * A party cannot be required to submit any dispute to arbitration that it has not agreed to submit.’ Gold Coast Mall v. Larmar Corp., 298 Md. 96, 103, 468 A.2d 91, 95 (1983) (emphasis added). Accord United Steelworkers of America v. Warrior & Gulf Navigation Co., 363 U.S. 574, 582-83, 80 S.Ct. 1347, 1353, 4 L.Ed.2d 1409, 1417 (1960). Arbitration is ‘consensual; a creature of contract. As such, only those who consent are bound. * * * In the absence of an express arbitration agreement, no party may be compelled to submit to arbitration in contravention of its right to legal process.’ Thomas J. Stipanowich, Arbitration and the Multiparty Dispute: The Search for Workable Solutions, 72 Iowa L. Rev. 473, 476 (1987) (citing Martin K. Eby Constr. Co. v. City of Arvada, 522 F.Supp. 449, 451 (D.Colo.1981)). Accord Messersmith, Inc. v. Barclay Townhouse, 313 Md. 652, 658, 547 A.2d 1048, 1051 (1988) (‘ “No one is under a duty to resort to ... [arbitral] tribunals, however helpful their processes, except to the extent that he has signified his willingness.” ’) (citation omitted). An arbitration agreement cannot impose obligations on persons who are not a party to it and do not agree to its terms. See A.B. Engineering Co. v. RSH Intern., Inc., 626 F.Supp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Selective Way Ins. v. Fireman's Fund Ins.
Court of Special Appeals of Maryland, 2023
Pulliam v. Dyck-O'Neal, Inc.
243 Md. App. 134 (Court of Special Appeals of Maryland, 2019)
Schneider Elect. Build. Critical Systems v. Western Surety Co.
Court of Special Appeals of Maryland, 2016
Schneider Electric Buildings Critical Systems, Inc. v. Western Surety Co.
149 A.3d 778 (Court of Special Appeals of Maryland, 2016)
FutureCare NorthPoint, LLC v. Peeler
143 A.3d 191 (Court of Special Appeals of Maryland, 2016)
Shutter v. CSX Transportation, Inc.
130 A.3d 1143 (Court of Special Appeals of Maryland, 2016)
Fox v. Fidelity First Home Mortgage Co.
117 A.3d 76 (Court of Special Appeals of Maryland, 2015)
Asphalt & Concrete Services, Inc. v. Perry
108 A.3d 558 (Court of Special Appeals of Maryland, 2015)
Zurich American Insurance v. Uninsured Employers' Fund
13 A.3d 98 (Court of Special Appeals of Maryland, 2011)
Williams v. Orentlicher
939 N.E.2d 663 (Indiana Court of Appeals, 2010)
Dickerson v. Longoria
995 A.2d 721 (Court of Appeals of Maryland, 2010)
Granite State Insurance v. Hernandez
992 A.2d 528 (Court of Special Appeals of Maryland, 2010)
Injured Workers' Insurance Fund v. Orient Express Delivery Service, Inc.
988 A.2d 1120 (Court of Special Appeals of Maryland, 2010)
John Crane, Inc. v. Linkus
988 A.2d 511 (Court of Special Appeals of Maryland, 2010)
SAXON MORTGAGE SERVICES, INC. v. Harrison
973 A.2d 841 (Court of Special Appeals of Maryland, 2009)
TWH, INC. v. Binford
898 N.E.2d 451 (Indiana Court of Appeals, 2008)
Bean v. Department of Health & Mental Hygiene
959 A.2d 778 (Court of Appeals of Maryland, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
695 A.2d 153, 346 Md. 122, 1997 Md. LEXIS 78, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartford-accident-indemnity-co-v-scarlett-harbor-associates-ltd-md-1997.