Jurgensen Co. v. Fairborn

2015 Ohio 5478
CourtOhio Court of Appeals
DecidedDecember 30, 2015
DocketC-140556
StatusPublished
Cited by1 cases

This text of 2015 Ohio 5478 (Jurgensen Co. v. Fairborn) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jurgensen Co. v. Fairborn, 2015 Ohio 5478 (Ohio Ct. App. 2015).

Opinion

[Cite as Jurgensen Co. v. Fairborn, 2015-Ohio-5478.] IN THE COURT OF APPEALS FIRST APPELLATE DISTRICT OF OHIO HAMILTON COUNTY, OHIO

JOHN R. JURGENSEN COMPANY, : APPEAL NO. C-140556 TRIAL NO. A-0800003 Plaintiff-Appellant, :

vs. : O P I N I O N.

CITY OF FAIRBORN, OHIO, :

Defendant-Appellee. :

Civil Appeal From: Hamilton County Court of Common Pleas

Judgment Appealed From Is: Affirmed

Date of Judgment Entry on Appeal: December 30, 2015

Frantz Ward LLP, Andrew J. Natale and Nora E. Loftus, for Plaintiff-Appellant,

Williams & Petro Co. LLC, John P. Petro and Susan S. R. Petro, for Defendant- Appellee.

Please note: this case has been removed from the accelerated calendar. OHIO FIRST DISTRICT COURT OF APPEALS

C UNNINGHAM , Presiding Judge.

{¶1} Plaintiff-appellant, the John R. Jurgensen Company, appeals from the

trial court’s entry denying it summary judgment on its claims that defendant-

appellee, the City of Fairborn, Ohio, had breached its road-improvement contract

when it refused to pay Jurgensen an asphalt-binder price adjustment found in an

Ohio Department of Transportation (“ODOT”) construction and material

specification. Because the parties’ agreement did not incorporate the asphalt-binder

price adjustment and did not modify the express pricing and payment terms found

elsewhere in the contract documents, we affirm the trial court’s judgment.

{¶2} In 2006, Fairborn sought bids for improvements to a number of its

streets. It issued a proposal including 65 tasks for completion in what became

known as the 2006 Street Program, Project Nos. 2502, 2601, 5104, and 5109. In

April 2006, Jurgensen became the successful bidder. Its $1,106,881.80 bid was

based in part on the general and project specifications and the bid and contract

forms (“the contract documents”) that Fairborn had made available to each bidder.

The contract documents included Fairborn Construction and Material Specification

Item 400 which provided specific guidance on how some of the project tasks were to be

performed. Because of the highly detailed nature of many construction specifications,

the contract documents, including Fairborn Item 400, incorporated by reference the

construction and material specifications promulgated by ODOT and required bidding

contractors like Jurgensen to comply with them. The 2005 ODOT Construction and

Material Specifications were in effect at the time of bidding.

{¶3} The price of asphalt is based largely on the price of oil, which can

fluctuate widely. Many road contracts include an “asphalt binder price adjustment”

to address this issue. Although the contract documents for Fairborn’s road-

improvement project did not include any specific reference to it, Jurgensen believed

that the parties’ agreement included an asphalt-binder price adjustment as found in

2 OHIO FIRST DISTRICT COURT OF APPEALS

ODOT Item 401.20. That provision required a project owner to equably adjust the

contract price and pay the contractor for any increase in the price of asphalt between

the time of its successful bid and the time that the asphalt is purchased and the work

is performed. ODOT Item 401.20 provided detailed instructions for measuring and

calculating any price adjustment.

{¶4} Jurgensen performed the asphalt work from August through

November 2006. During the time between bidding and completion of the work, the

price of asphalt increased significantly. At the completion of the project, Jurgensen

submitted claims to Fairborn for additional compensation to reflect an asphalt-

binder price adjustment of $92,395.66.

{¶5} Fairborn refused to pay the adjustment. Fairborn also refused to

release interest earned on the amounts retained from progress payments made to

Jurgensen. See R.C. Chapter 153. Jurgensen brought suit seeking money damages

and a declaration that Fairborn’s refusal to pay the asphalt-binder price adjustment

and to pay interest had breached its duties under the contract documents.

{¶6} Fairborn answered and raised a counterclaim seeking $2,000 due for

damage to a catch basin, along with a declaration that the price described in the

winning bid—$1,106,881.80—was all the compensation due to Jurgensen.

{¶7} In December 2008, Jurgensen moved for summary judgment on its

claims based on the affidavits of Peter W. Flora, its Dayton Division manager, and

the contract documents. Fairborn also moved for summary judgment on all of

Jurgensen’s claims. Fairborn’s motion was supported by the affidavits of Michael A.

Mayer, Fairborn’s city solicitor, and the attached documents.

{¶8} The trial court heard the arguments of counsel. On June 18, 2013, it

journalized an entry denying Jurgensen’s motion for summary judgment on its

breach-of-contract claims relating to the asphalt-binder price adjustment and

granted Fairborn’s summary-judgment motion on those claims. The trial court

3 OHIO FIRST DISTRICT COURT OF APPEALS

denied Fairborn’s summary-judgment motion on Jurgensen’s retained-interest

claim.

{¶9} The trial court then scheduled a trial date to resolve the remaining

issues. Prior to trial, Jurgensen and Fairborn reached an agreement to dismiss

Jurgensen’s interest claim and Fairborn’s property-damage counterclaim, and the

parties submitted a proposed consent entry to the court. The trial court approved

the entry. It journalized the entry on September 10, 2014, rendering its earlier

summary-judgment ruling final and appealable. Jurgensen appealed.

{¶10} In two interrelated assignments of error, Jurgensen now asserts that

the trial court erred in denying its motion for summary judgment and in granting, in

part, Fairborn’s motion for summary judgment. Civ.R. 56(A) makes summary

judgment available to a party like Jurgensen, seeking to recover upon its own claim.

See Capital Fin. Credit, LLC v. Mays, 191 Ohio App.3d 56, 2010-Ohio-4423, 944

N.E.2d 1184, ¶ 4 (1st Dist.). A party moving for summary judgment bears the burden

of establishing that (1) no genuine issue of material fact remains to be litigated, (2)

the moving party is entitled to summary judgment as a matter of law, and (3) it

appears from the evidence, when viewed in a light most favorable to the nonmoving

party, that reasonable minds can only come to a conclusion adverse to that party.

See Civ.R. 56.

{¶11} The interpretation of clear, unambiguous contract terms is a question

of law particularly appropriate for resolution by summary judgment. See Costanzo v.

Nationwide Mut. Ins. Co., 161 Ohio App.3d 759, 2005-Ohio-3170, 832 N.E.2d 71, ¶

19 (1st Dist.). If the language in a contract is clear and unambiguous, there is no

issue of fact to be determined. See Physicians Anesthesia Serv. v. Burt, 1st Dist.

Hamilton No. C-060761, 2007-Ohio-6871, ¶ 10. An appellate court reviews the trial

court’s summary-judgment rulings de novo. See Comer v. Risko, 106 Ohio St.3d 185,

2005-Ohio-4559, 833 N.E.2d 712, ¶ 8.

4 OHIO FIRST DISTRICT COURT OF APPEALS

{¶12} Here, neither Jurgensen nor Fairborn has asserted that genuine

issues of material fact remained for resolution. Both moved for summary judgment

as a matter of law on Jurgensen’s claims. We have previously questioned the wisdom

of resolving declaratory-judgment actions by summary judgment. But the parties’

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guaranteed Constr. Servs., L.L.C. v. Grand Communities, Ltd.
2017 Ohio 9288 (Ohio Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2015 Ohio 5478, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jurgensen-co-v-fairborn-ohioctapp-2015.