Jurgensen Co. v. Fairborn

2015 Ohio 5478
Ohio Court of Appeals·Decided December 30, 2015·No. C-140556·Published·Cited by 1 cases

Opinion

IN THE COURT OF APPEALS

FIRST APPELLATE DISTRICT OF OHIO HAMILTON COUNTY, OHIO

JOHN R. JURGENSEN COMPANY, : APPEAL NO. C-140556 TRIAL NO. A-0800003

Plaintiff-Appellant, :

vs. : O P I N I O N.

CITY OF FAIRBORN, OHIO, :

Defendant-Appellee. :

Civil Appeal From: Hamilton County Court of Common Pleas Judgment Appealed From Is: Affirmed Date of Judgment Entry on Appeal: December 30, 2015

Frantz Ward LLP, Andrew J. Natale and Nora E. Loftus, for Plaintiff-Appellant,

Williams & Petro Co. LLC, John P. Petro and Susan S. R. Petro, for Defendant- Appellee.

Please note: this case has been removed from the accelerated calendar.

C UNNINGHAM , Presiding Judge.

{¶1} Plaintiff-appellant, the John R. Jurgensen Company, appeals from the trial court’s entry denying it summary judgment on its claims that defendant- appellee, the City of Fairborn, Ohio, had breached its road-improvement contract when it refused to pay Jurgensen an asphalt-binder price adjustment found in an Ohio Department of Transportation (“ODOT”) construction and material specification. Because the parties’ agreement did not incorporate the asphalt-binder price adjustment and did not modify the express pricing and payment terms found elsewhere in the contract documents, we affirm the trial court’s judgment.

{¶2} In 2006, Fairborn sought bids for improvements to a number of its streets. It issued a proposal including 65 tasks for completion in what became known as the 2006 Street Program, Project Nos. 2502, 2601, 5104, and 5109. In April 2006, Jurgensen became the successful bidder. Its $1,106,881.80 bid was based in part on the general and project specifications and the bid and contract forms (“the contract documents”) that Fairborn had made available to each bidder. The contract documents included Fairborn Construction and Material Specification Item 400 which provided specific guidance on how some of the project tasks were to be performed. Because of the highly detailed nature of many construction specifications, the contract documents, including Fairborn Item 400, incorporated by reference the construction and material specifications promulgated by ODOT and required bidding contractors like Jurgensen to comply with them. The 2005 ODOT Construction and Material Specifications were in effect at the time of bidding.

{¶3} The price of asphalt is based largely on the price of oil, which can fluctuate widely. Many road contracts include an “asphalt binder price adjustment” to address this issue. Although the contract documents for Fairborn’s road- improvement project did not include any specific reference to it, Jurgensen believed that the parties’ agreement included an asphalt-binder price adjustment as found in

ODOT Item 401.20. That provision required a project owner to equably adjust the contract price and pay the contractor for any increase in the price of asphalt between the time of its successful bid and the time that the asphalt is purchased and the work is performed. ODOT Item 401.20 provided detailed instructions for measuring and calculating any price adjustment.

{¶4} Jurgensen performed the asphalt work from August through November 2006. During the time between bidding and completion of the work, the price of asphalt increased significantly. At the completion of the project, Jurgensen submitted claims to Fairborn for additional compensation to reflect an asphalt- binder price adjustment of $92,395.66.

{¶5} Fairborn refused to pay the adjustment. Fairborn also refused to release interest earned on the amounts retained from progress payments made to Jurgensen. See R.C. Chapter 153. Jurgensen brought suit seeking money damages and a declaration that Fairborn’s refusal to pay the asphalt-binder price adjustment and to pay interest had breached its duties under the contract documents.

{¶6} Fairborn answered and raised a counterclaim seeking $2,000 due for damage to a catch basin, along with a declaration that the price described in the winning bid—$1,106,881.80—was all the compensation due to Jurgensen.

{¶7} In December 2008, Jurgensen moved for summary judgment on its claims based on the affidavits of Peter W. Flora, its Dayton Division manager, and the contract documents. Fairborn also moved for summary judgment on all of Jurgensen’s claims. Fairborn’s motion was supported by the affidavits of Michael A. Mayer, Fairborn’s city solicitor, and the attached documents.

{¶8} The trial court heard the arguments of counsel. On June 18, 2013, it journalized an entry denying Jurgensen’s motion for summary judgment on its breach-of-contract claims relating to the asphalt-binder price adjustment and granted Fairborn’s summary-judgment motion on those claims. The trial court

denied Fairborn’s summary-judgment motion on Jurgensen’s retained-interest claim.

{¶9} The trial court then scheduled a trial date to resolve the remaining issues. Prior to trial, Jurgensen and Fairborn reached an agreement to dismiss Jurgensen’s interest claim and Fairborn’s property-damage counterclaim, and the parties submitted a proposed consent entry to the court. The trial court approved the entry. It journalized the entry on September 10, 2014, rendering its earlier summary-judgment ruling final and appealable. Jurgensen appealed.

{¶10} In two interrelated assignments of error, Jurgensen now asserts that the trial court erred in denying its motion for summary judgment and in granting, in part, Fairborn’s motion for summary judgment. Civ.R. 56(A) makes summary judgment available to a party like Jurgensen, seeking to recover upon its own claim. See Capital Fin. Credit, LLC v. Mays, 191 Ohio App.3d 56, 2010-Ohio-4423, 944 N.E.2d 1184, ¶ 4 (1st Dist.). A party moving for summary judgment bears the burden of establishing that (1) no genuine issue of material fact remains to be litigated, (2) the moving party is entitled to summary judgment as a matter of law, and (3) it appears from the evidence, when viewed in a light most favorable to the nonmoving party, that reasonable minds can only come to a conclusion adverse to that party. See Civ.R. 56.

{¶11} The interpretation of clear, unambiguous contract terms is a question of law particularly appropriate for resolution by summary judgment. See Costanzo v. Nationwide Mut. Ins. Co., 161 Ohio App.3d 759, 2005-Ohio-3170, 832 N.E.2d 71, ¶ 19 (1st Dist.). If the language in a contract is clear and unambiguous, there is no issue of fact to be determined. See Physicians Anesthesia Serv. v. Burt, 1st Dist. Hamilton No. C-060761, 2007-Ohio-6871, ¶ 10. An appellate court reviews the trial court’s summary-judgment rulings de novo. See Comer v. Risko, 106 Ohio St.3d 185, 2005-Ohio-4559, 833 N.E.2d 712, ¶ 8.

{¶12} Here, neither Jurgensen nor Fairborn has asserted that genuine issues of material fact remained for resolution. Both moved for summary judgment as a matter of law on Jurgensen’s claims. We have previously questioned the wisdom of resolving declaratory-judgment actions by summary judgment. But the parties’ election to address the issues by cross-motions for summary judgment demonstrates that both sides believed that there was no genuine issue of material fact in dispute, and that the court was free to render a decision as a matter of law. E.g., Cincinnati v. Ohio Council 8, Am. Fedn. of State, Cty. & Mun. Emps., AFL-CIO, 93 Ohio App.3d 162, 164, 638 N.E.2d 94 (1st Dist.1994).

{¶13} To prevail on its claims, Jurgensen would have to establish the existence of a contract, performance on its part, breach of a duty by Fairborn, and its own damage or loss. See Brunsman v. W. Hills Country Club, 151 Ohio App.3d 718, 2003-Ohio-891, 785 N.E.2d 794, ¶ 11 (1st Dist.).

Free access — add to your briefcase to read the full text and ask questions with AI

Jurgensen Co. v. Fairborn, 2015 Ohio 5478 (Ohio Ct. App. 2015).

2015 Ohio 5478 (Jurgensen Co. v. Fairborn) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Guaranteed Constr. Servs., L.L.C. v. Grand Communities, Ltd.
2017 Ohio 9288 (Ohio Court of Appeals, 2017)