Dugan & Meyers Construction Co. v. Ohio Department of Administrative Services

864 N.E.2d 68, 113 Ohio St. 3d 226
CourtOhio Supreme Court
DecidedApril 25, 2007
DocketNo. 2005-1698
StatusPublished
Cited by30 cases

This text of 864 N.E.2d 68 (Dugan & Meyers Construction Co. v. Ohio Department of Administrative Services) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dugan & Meyers Construction Co. v. Ohio Department of Administrative Services, 864 N.E.2d 68, 113 Ohio St. 3d 226 (Ohio 2007).

Opinions

Moyer, C.J.

{¶ 1} This case concerns a $20.9 million contract for construction of three buildings to be part of the Fisher College of Business of the Ohio State University. The parties to the contract are the appellees, Ohio Department of Administrative Services (“the department”) and The Ohio State University (“OSU”) (collectively, “the state”), and the appellant, Dugan & Meyers Construction Co., Inc. (“Dugan & Meyers”).

The Contract

{¶ 2} In 1997, Dugan & Meyers submitted a successful competitive bid to serve as the lead contractor for the construction of three buildings to be part of the Fisher College of Business at OSU: an undergraduate building, a resource center, and an executive-education building. Dugan & Meyers and the department, which served as the authorized contracting agent for OSU, executed a written contract in which the department agreed to pay Dugan & Meyers $20,932,500 and Dugan & Meyers agreed to complete construction work according to plans and specifications prepared by the associate architect on the project, Karlsberger Companies. During construction the associate architect monitored construction and processed change orders under the terms of the contract.

{¶ 3} The contract provided that Dugan & Meyers was to complete the work “on or before 660 consecutive days, following the date set forth in the Notice to Proceed, unless an extension of time [was] granted by the Director [of the department] in accordance with the Contract Documents.” The contract further provided that if Dugan & Meyers did not complete the work within the 660-day period, the department would be “entitled to retain or recover from [Dugan & [227]*227Meyers], as liquidated damages, and not as a penalty, the amount of $3,000 per day for each and every calendar day thereafter until such Work [was] completed and accepted.”

{¶ 4} The contract included general conditions (“GCs”), including the following:

{¶ 5} “Article 6 — Time

{¶ 6} “6.1 Time is of the essence to the Contract Documents and all obligations thereunder. By executing the Contract, the Contractor acknowledges that the time for Contract Completion and any specified milestone completion dates are reasonable * * *.

{¶ 7} “ * * *

{¶ 8} “6.2 If the Contractor is delayed at any time in the progress of the Work by any of the following causes, the Contract time shall be extended for such reasonable time which the Associate [architect] determines, in consultation with the Department and the Owner, has been caused by the delay in the Work:

{¶ 9} “6.2.1 Delay due to suspension of the Work for which the Contractor is not responsible; * * *

{¶ 10} “ * * *

{¶ 11} “6.2.3 By any unforeseeable cause beyond the control and without fault or negligence of the Contractor.

{¶ 12} “6.3 Any extension of time granted pursuant to paragraph GC 6.2 shall be the sole remedy which may be provided by the Department. In no event shall the Contractor be entitled to additional compensation or mitigation of Liquidated Damages for any delay listed in paragraph GC 6.2, including, without limitation, costs of acceleration, consequential damages, loss of efficiency, loss of productivity, lost opportunity costs, impact damages, lost profits or other similar remuneration.”

{¶ 13} The contract also provided that the contractor’s failure to request in writing an extension of time within ten days after the occurrence of a condition necessitating an extension of time “shall constitute a waiver by the Contractor of any claim for extension or for mitigation of Liquidated Damages.”

{¶ 14} On August 15, 1997, the department sent a letter authorizing Dugan & Meyers to commence work “within one week from the date of [the] letter and to fully complete the work on or before 660 consecutive calendar days or by June 13, 1999.” The completion dates for the three buildings were subsequently modified by agreement of the parties to June 11, 1999, for the resource center and to July 11, 1999, for the undergraduate building and executive-education budding.

[228]*228Delays in Construction

{¶ 15} Construction progressed virtually on schedule during the first year. By June 1998, however, the project began to fall behind schedule. As summarized by the Court of Claims referee, “As the interior work progressed numerous omissions, inaccuracies, and conflicts in the design documents * * * were discovered that required the contractors, before proceeding with their work, to seek a determination by the associate as to what was intended or required.” By February 1999 it was apparent that the project was unlikely to be completed in time to ensure completion of that portion of the project that was needed for fall 1999 classes. Dugan & Meyers did not make any written requests for extensions of time after January 1998.

{¶ 16} Attempts to bring the project back on schedule failed, and OSU1 ultimately relieved Dugan & Meyers of its responsibilities as lead contractor, substituting the Gilbane Building Company (“Gilbane”).2 OSU discharged Dugan & Meyers for the stated reason that Dugan & Meyers “failed or neglected to prosecute the Work with the necessary diligence so as to complete the work by the applicable milestones and the time specified in the Contract.” According to the referee’s report, under Gilbane’s direction, the undergraduate building was completed in time for fall classes in September 1999 and the last of the three buildings was completed on January 16, 2000, six months after the modified deadline.

{¶ 17} Dugan & Meyers sought payment from OSU for services rendered under the contract. In determining the amount due, OSU deducted the amount paid to Gilbane for completing the lead-contractor duties. OSU also assessed Dugan & Meyers liquidated damages based on 188 days of delay in completion. OSU determined the liquidated damages by apportioning responsibility for the 188 days of delay between three subcontractors and Dugan & Meyers and charged Dugan & Meyers for its contribution to the project delay.

The Litigation

{¶ 18} Dugan & Meyers filed a complaint in the Court of Claims of Ohio seeking an award of nearly $3.4 million based on breach of contract or, alternatively, unjust enrichment. The complaint acknowledged that Dugan & Meyers began to have problems with the project, which led to delays, beginning in the second year of the project, but asserted that the delays were due in large part to the fact that the plans for the project provided by OSU were inaccurate and [229]*229incomplete. The complaint claimed, in summary, that Dugan & Meyers had issued in excess of 700 requests for information, many of which produced no timely response; associate architect Karlsberger had issued over 250 field work orders and 85 architectural supplemental instructions directing Dugan & Meyers to perform work outside the contract; and Dugan & Meyers was “entitled to time extensions for delays and impacts outside of its control,” which the state had refused to grant. The complaint concluded that the state had breached its duty to provide Dugan & Meyers with plans that were buildable, accurate, and complete, and had unreasonably rejected legitimate time-extension requests.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

G.A.I. Capital Group v. Lisowski
2023 Ohio 4802 (Ohio Court of Appeals, 2023)
Accurate Elec. Constr., Inc. v. Ohio State Univ.
2019 Ohio 4992 (Ohio Court of Appeals, 2019)
Oberlin v. Lorain Cty. Joint Vocational School Dist. Bd. of Edn.
2019 Ohio 3977 (Ohio Court of Appeals, 2019)
Manley Architecture Group, L.L.C. v. Santanello
2018 Ohio 2200 (Ohio Court of Appeals, 2018)
McGarry & Sons, Inc. v. Constr. Resources One, L.L.C.
2018 Ohio 528 (Ohio Court of Appeals, 2018)
Guaranteed Constr. Servs., L.L.C. v. Grand Communities, Ltd.
2017 Ohio 9288 (Ohio Court of Appeals, 2017)
IPS Elec, Servs., L.L.C. v. Univ. of Toledo
2016 Ohio 361 (Ohio Court of Appeals, 2016)
IPS Elec. Servs., L.L.C. v. Univ. of Toledo
2015 Ohio 5556 (Ohio Court of Claims, 2015)
Jurgensen Co. v. Fairborn
2015 Ohio 5478 (Ohio Court of Appeals, 2015)
Boone Coleman Constr., Inc. v. Village of Piketon
2014 Ohio 2377 (Ohio Court of Appeals, 2014)
U.S. Bank, N.A. v. Gotham King Fee Owner, L.L.C.
2013 Ohio 1983 (Ohio Court of Appeals, 2013)
Jess Howard Electric Co. v. Ohio School Facilities Comm.
2013 Ohio 3642 (Ohio Court of Claims, 2013)
MJMT, Inc. v. Geier
2012 Ohio 813 (Ohio Court of Appeals, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
864 N.E.2d 68, 113 Ohio St. 3d 226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dugan-meyers-construction-co-v-ohio-department-of-administrative-ohio-2007.