J&H Reinforcing & Structural Erectors, Inc. v. Ohio School Facilities Comm.

2012 Ohio 5308
CourtOhio Court of Claims
DecidedJune 6, 2012
Docket2010-07644
StatusPublished

This text of 2012 Ohio 5308 (J&H Reinforcing & Structural Erectors, Inc. v. Ohio School Facilities Comm.) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J&H Reinforcing & Structural Erectors, Inc. v. Ohio School Facilities Comm., 2012 Ohio 5308 (Ohio Super. Ct. 2012).

Opinion

[Cite as J&H Reinforcing & Structural Erectors, Inc. v. Ohio School Facilities Comm., 2012-Ohio-5308.]

Court of Claims of Ohio The Ohio Judicial Center 65 South Front Street, Third Floor Columbus, OH 43215 614.387.9800 or 1.800.824.8263 www.cco.state.oh.us

J & H REINFORCING & STRUCTURAL ERECTORS, INC.

Plaintiff/Counter Defendant

v.

OHIO SCHOOL FACILITIES COMMISSION

Defendant/Counter Plaintiff

Case No. 2010-07644

Judge Joseph T. Clark Referee Thomas R. Yocum

JUDGMENT ENTRY

{¶ 1} Plaintiff/counter defendant, J&H Reinforcing & Structural Erectors, Inc. (J&H), brought this action against defendant/counter plaintiff, Ohio School Facilities Commission (OSFC), alleging breach of contract. OSFC asserted a counterclaim for breach of contract and breach of express and implied warranties. The case was tried to a referee pursuant to R.C. 2743.03(C)(3) and 153.12. {¶ 2} On February 10, 2012, the referee issued a decision recommending judgment for J&H on its complaint in the amount of $959,232.00, and in favor of OSFC on its counterclaim in the amount of $180,332.67. The referee further found that the complaint and counterclaim arose from the same transaction or occurrence, and that the award to OSFC was to be offset against the award to J&H. Accordingly, judgment was recommended in favor of J&H in the total amount of $778,899.33, plus prejudgment interest and costs. {¶ 3} Civ.R. 53(D)(3)(b)(i) states, in part: “A party may file written objections to a magistrate’s decision within fourteen days of the filing of the decision, whether or not the court has adopted the decision during that fourteen-day period as permitted by Civ.R. Case No. 2010-07644 -2- ENTRY

53(D)(4)(e)(i).” On February 24, 2012, both OSFC and J&H timely filed objections.1 On March 5, 2012, the parties filed responses.

FACTS RELEVANT TO THE COMPLAINT {¶ 4} In 2007, OSFC and the Wheelersburg Local Schools Board of Education (Wheelersburg) solicited bids for the construction of a school that was to house grades K-12. OSFC had previously contracted with Tanner Stone Holsinger Donges & Company (Tanner Stone) to act as project architect and Bovis Lend Lease Company (Bovis) to act as its construction manager. {¶ 5} J&H secured two separate contracts for the project. The first involved the pre-construction site work (Joint Exhibit O - Joint Exhibits are referred to herein as “JX”), and the second (the “Contract” which is subject of this litigation) involved the combination of general trades work, masonry, and interior case work (JX F). Notice to J&H to proceed was issued by Bovis on October 2, 2006. (Plaintiff’s Exhibit 91 - Plaintiff’s Exhibits are referred to herein as “PX.”) However, shortly after work was to begin, J&H encountered soil conditions which were unexpected and which proved to be too unstable to support the structure. J&H subsequently performed lime stabilization work pursuant to a contract change order. (JX P.) According to J&H, the delay caused by the poor soil conditions pushed the start of building construction out to December 26, 2006. {¶ 6} The masonry and general trades work progressed at a steady pace from July 2008 through the fall of 2008. However, J&H learned that several Air Handling Units (AHUs) supplied by another contractor which were originally scheduled to be delivered in May of 2007, were not going to arrive until September 2007. The late delivery of the AHUs altered the sequence of the masonry and roofing work.

1 For good cause shown, OSFC’s February 24, 2012 motion for leave to exceed the court’s page limitation for its brief is GRANTED, instanter, as is J&H’s March 5, 2012 motion to supplement its objections. Case No. 2010-07644 -3- ENTRY

{¶ 7} On February 19, 2008, the parties executed Change Order 29 (CO 29) whereby J&H agreed to extend the project completion date from March 17, 2008 to July 15, 2008 in return for a one time payment in the amount of $113,479.04. (JX G-303.) Bovis project manager, Ron Palonis, drafted a new project schedule incorporating the agreed July 15, 2008 completion date. On February 14, 2008, after reviewing the new schedule, J&H project manager, Mark Rollins, began sending letters to Palonis informing Bovis that the schedule did not accurately reflect the progress that was being made in the field and asking Bovis either for additional time to complete specific tasks or for a corresponding extension of the project completion date. Rollins estimated that he sent 12-14 such letters over the next four months. In his last such letter dated April 7, 2008, Rollins requested an extension of the completion date to September 28, 2008. None of the requested extensions of time were granted. {¶ 8} Over the course of the next several months, J&H repeatedly complained to Bovis that its work was being impacted by the presence of other contractors in its work space. {¶ 9} The referee found that Bovis had deliberately manipulated its own scheduling software so that a schedule could be produced with a July 15, 2008 completion date, even though Bovis knew that such a schedule was both unrealistic and unmanageable. The referee also found that the unrealistic schedule caused the stacking of trades experienced by J&H. {¶ 10} In June of 2009, with the start of the school year looming and progress on the project slowing, Bovis brought in Bruce Wilson as its new project superintendent. Under Wilson’s leadership and what Wilson described as a “heroic effort” by J&H, the project was substantially completed in time for the school year. Case No. 2010-07644 -4- ENTRY

THE PARTIES’ OBJECTIONS {¶ 11} In its first objection, J&H argues that the referee erred in concluding that J&H was not entitled to an equitable adjustment to the contract to account for the delay caused by the poor site conditions. The court disagrees. {¶ 12} The referee found that J&H was not entitled to an equitable adjustment for the site delay inasmuch as J&H failed to timely request an extension of time, in writing, as required by Article 6 of the contract, and failed to provide timely notice of its claim for an equitable adjustment pursuant to Article 8.1. {¶ 13} Article 6 of the General Conditions provides: {¶ 14} “6.4.1 Any request by the Contractor for an extension of time shall be made in writing to the Construction Manager no more than ten (10) days after the initial occurrence of ay condition which, in the Contractor’s opinion, entitles the Contractor to an extension of time. Failure to timely provide such notice to the Construction Manager shall constitute a waiver by the Contractor of any claim for extension, damages or mitigation of Liquidated Damages, to the fullest extent permitted by law.” (Emphasis added.) {¶ 15} Article 8.1 provides: {¶ 16} “Any request for equitable adjustment of Contract shall be made in writing to the Architect, through the Construction Manager, and filed prior to Contract Completion, provided the Contractor notified the Architect, through the Construction Manager, no more than ten (10) days after the initial occurrence of the facts which are the basis of the claim. To the fullest extent permitted by law, failure of the Contractor to timely provide such notice and a contemporaneous statement of damages shall constitute a waiver by the Contractor of any claim for additional compensation or for mitigation of Liquidated Damages.” (Emphasis added.) {¶ 17} Although OSFC argues in objection II(B) that a written 10-day notice is required pursuant to Article 8.1, the plain language of Article 8.1.1 contains no writing Case No. 2010-07644 -5- ENTRY

requirement either for the 10-day notice or the contemporaneous statement of damages.2 Similarly, the case law does not support J&H’s claim that compliance with the 10-day notice was unnecessary. See Stanley Miller Constr. Co. v. Ohio School Facilities Comm., 10th Dist. Nos.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tritonservices, Inc. v. Univ. of Cincinnati
2011 Ohio 7010 (Ohio Court of Claims, 2011)
Phillips v. Sharp
185 N.E. 562 (Ohio Court of Appeals, 1932)
Conti Corp. v. Ohio Department of Administrative Services
629 N.E.2d 1073 (Ohio Court of Appeals, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
2012 Ohio 5308, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jh-reinforcing-structural-erectors-inc-v-ohio-school-facilities-comm-ohioctcl-2012.