Conti Corp. v. Ohio Department of Administrative Services

629 N.E.2d 1073, 90 Ohio App. 3d 462, 1993 Ohio App. LEXIS 4537
CourtOhio Court of Appeals
DecidedSeptember 21, 1993
DocketNo. 93AP-10.
StatusPublished
Cited by16 cases

This text of 629 N.E.2d 1073 (Conti Corp. v. Ohio Department of Administrative Services) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Conti Corp. v. Ohio Department of Administrative Services, 629 N.E.2d 1073, 90 Ohio App. 3d 462, 1993 Ohio App. LEXIS 4537 (Ohio Ct. App. 1993).

Opinion

Petree, Judge.

This is an appeal from the Court of Claims of Ohio, which awarded plaintiff, contractor Conti Corporation, damages against defendants, Ohio Department of Administrative Services (“DAS”) and Youngstown State University (“YSU”) as follows: $117,951.59 against YSU and $229,782.50 against DAS and YSU jointly *465 and severally. DAS assigns five errors on appeal (numbered one through five hereafter). YSU joins as to assignments of error three, four and five, and also raises a sixth assignment of error, which is designated as assignment of error three in its brief.

Defendants contracted with plaintiff for renovation and reconstruction of Ward Beecher Science Hall on the YSU campus, and plaintiff began work on August 23, 1984. The project was halted from early 1986 to July 1986 after asbestos was discovered on the site. From that time until the end of the project in March 1987, other conditions were discovered requiring all contractors to perform extra work. After the project ended, plaintiff had several claims for payments, all of which were denied in the administrative review procedures established by Article 8 of the contract. About one year later, plaintiff submitted two additional claims for Article 8 review, then, on November 21, 1988, filed this action in the Court of Claims. Judgment was entered on November 30,1992 and defendants separately filed timely notices of appeal.

I. “The trial court erred in assessing monetary liability against the Ohio Department of Administrative Services since the Department was acting as a disclosed agent and contract administrator for Youngstown State University.”

II. “The trial court erred in assessing liability jointly and severally against two state agencies.”

These first two assignments of error are related and will be considered jointly. Defendant DAS argues that it is not liable on the contract because DAS is the statutory agent of defendant YSU. DAS’s attempts to define the relationship between itself and YSU are in vain due to the decision in Ohio Dept. of Human Serv. v. Ohio Dept. of Transp. (1992), 78 Ohio App.3d 658, 605 N.E.2d 1007. In that case, this court held that all state governmental agencies are members of the “state” as that term is defined and used in R.C. Chapter 2743. That is, state governmental agencies are not distinct entities within the meaning of R.C. Chapter 2743. “The only defendant in original actions in the court of claims is the state.” R.C. 2743.02(E). “It is axiomatic that a party cannot sue itself.” Ohio Dept. of Human Serv., supra, at 661, 605 N.E.2d at 1009. We agree with the recent holding of the Court of Claims that DAS is such a governmental agency: “DAS does not act on behalf of any particular agency, but on behalf of the State of Ohio.” Royal Elec. Constr. Corp. v. Ohio State Univ. (Feb. 19, 1993), Court of Claims No. 90-05520, unreported.

DAS argues that R.C. 2743.19(A) forbids-the Court of Claims from assigning joint and several liability against multiple state agencies. The statute contains no such prohibition; it merely provides that “the court of claims shall determine and specify in the judgment the department * * * against which a determination of *466 liability has been made.” This the Court of Claims has done, specifying DAS and YSU. R.C. 2743.19(A) cannot be read as prohibiting judgments of joint and several liability. Because only “the state” can be a defendant, such an interpretation would be tantamount to charging the judiciary with the task of allocating costs among departments of the executive, which would violate the implied principle of separation of powers. In the absence of express constitutional provisions, the General Assembly cannot assign nonjudicial function to the judiciary. Thompson v. Redington (1915), 92 Ohio St. 101, 106, 110 N.E. 652, 654.

Therefore, it was not error for the Court of Claims to assess damages in the form of joint and several liability against DAS. The first and second assignments of error are overruled.

III. “The trial court erred in determining that the state’s obligation under R.C. 153.14 to make payment on a construction contractor’s approved estimates within 30 days means within 30 days after approval by the associate architect rather than by the State Architect.”

The trial court found plaintiff to be entitled to $4,722 for interest on late payments due to the state’s delay in paying plaintiffs invoices. Defendants allege that the trial court erred in awarding this amount, arguing that many of the invoice payments were not late, as they were not due until approved by the state architect. Defendants maintain that the majority of the invoices were paid in a timely manner if the time is calculated from the date of the state architect’s approval. In the alternative, defendants argue even if the associate architect’s approval was all that was needed, the evidence in the record does not support the trial court’s decision.

The parties’ contract provides that “payment of approved contractor’s pay requests shall be made within thirty days from the date of approval by the Deputy Director of Public Works.” R.C. 153.14, which applies to all public improvement contracts, reads in part:

“Payment on approved estimates filed with the owner or its representative shall be made within thirty days. Upon the failure * * * to make such payments within thirty days * * * there shall be allowed to the contractor, in addition to any other remedies allowed by law, interest on such moneys not paid within thirty days.”

Initially, defendants argue that the contract provision requiring approval by the Deputy Director should be enforced. However, in Ernst v. Ohio Dept. of Adm. Serv. (1990), 69 Ohio App.3d 330, 337, 590 N.E.2d 812, 817, this court determined that R.C. 153.14 preempted a nearly identical contract provision. A state agency may not, by contract or otherwise, avoid one of the conditions *467 imposed by the General Assembly for the construction of public improvements. Therefore, R.C. 153.14 is controlling over the contract provision.

Defendants argue that the approval referred to in R.C. 153.14 is the approval of the state architect, not the associate architect for the project. We disagree. In Ernst, this court determined that the approval required by R.C. 153.14 is the approval of the “architect or engineer” referred to in R.C. 153.12. Ernst, 69 Ohio App.3d at 337-338, 590 N.E.2d at 817. “Architect” in the phrase “architect or engineer” must mean the associate architect because there is no such “state engineer” to parallel the state architect. Therefore, the thirty-day period begins to run once the payment request has been both submitted to the owner and approved by the associate architect. However, approval by the associate architect must be made within a reasonable time. Id. at 338, 590 N.E.2d at 817. Where approval is not given within a reasonable time, the thirty-day period will be deemed to expire at the end of the reasonable time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

IPS Elec, Servs., L.L.C. v. Univ. of Toledo
2016 Ohio 361 (Ohio Court of Appeals, 2016)
Stanley Miller Constr. Co. v. School Facilities Comm.
2012 Ohio 3995 (Ohio Court of Claims, 2012)
Stanley Miller Constr. Co. v. State
2010 Ohio 1488 (Ohio Court of Claims, 2010)
Stanley Miller Constr. Co. v. Ohio School Facilities Comm.
2010 Ohio 1528 (Ohio Court of Claims, 2010)
Gmac Mortgage v. Titch, Unpublished Decision (3-2-2005)
2005 Ohio 868 (Ohio Court of Appeals, 2005)
Fairfax County Redevelopment & Housing Authority v. Worcester Bros.
514 S.E.2d 147 (Supreme Court of Virginia, 1999)
United Telephone Co. v. Williams Excavating, Inc.
707 N.E.2d 1188 (Ohio Court of Appeals, 1997)
Julian Speer Co. v. Ohio State University
680 N.E.2d 254 (Ohio Court of Claims, 1997)
Domestic Linen Supply & Laundry Co. v. Kenwood Dealer Group, Inc.
672 N.E.2d 184 (Ohio Court of Appeals, 1996)
Royal Electric Constr. Corp. v. Ohio State Univ.
1995 Ohio 131 (Ohio Supreme Court, 1995)
Royal Electric Construction Corp. v. Ohio State University
73 Ohio St. 3d 110 (Ohio Supreme Court, 1995)
Yaroma v. Griffiths
662 N.E.2d 867 (Ohio Court of Appeals, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
629 N.E.2d 1073, 90 Ohio App. 3d 462, 1993 Ohio App. LEXIS 4537, Counsel Stack Legal Research, https://law.counselstack.com/opinion/conti-corp-v-ohio-department-of-administrative-services-ohioctapp-1993.