Fairfax County Redevelopment & Housing Authority v. Worcester Bros.

514 S.E.2d 147, 257 Va. 382, 1999 Va. LEXIS 48
CourtSupreme Court of Virginia
DecidedFebruary 26, 1999
DocketRecord 980731
StatusPublished
Cited by14 cases

This text of 514 S.E.2d 147 (Fairfax County Redevelopment & Housing Authority v. Worcester Bros.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fairfax County Redevelopment & Housing Authority v. Worcester Bros., 514 S.E.2d 147, 257 Va. 382, 1999 Va. LEXIS 48 (Va. 1999).

Opinion

JUSTICE KOONTZ

delivered the opinion of the Court.

In this appeal, we consider whether the trial court’s award of unabsorbed home office expenses to the contractor on a public construction project following an unreasonable delay by the contracting government agency was based upon sufficient proof of the existence and amount of those damages.

BACKGROUND

Under well established principles, we recount only those facts relevant to our resolution of the appeal. On September 14, 1995, the Fairfax County Redevelopment and Housing Authority (the Authority) entered into a contract with Worcester Brothers Company, Inc. (Worcester Brothers), a general construction contractor, for site reno *385 vations and improvements of Washington Plaza in Lake Anne Village (the project) in Reston.

The Authority had originally solicited bids for the project based on a projected start date in July 1995, with completion of the work in 150 calendar days from the notice to proceed. Thus, the proposed date of substantial completion at the time bids were solicited was mid-December 1995. Worcester Brothers based its bid on these conditions. However, because the Authority did not award the contract to Worcester Brothers until September 14, 1995, the substantial completion date for the project was moved back to mid-February 1996.

It is not disputed that at the time Worcester Brothers commenced work on the project, the Authority had not yet obtained the necessary clearances from an adjoining property owner to allow work to proceed on a portion of the project site. The Authority did not obtain the clearances until March 6, 1996.

After the work was completed, Worcester Brothers filed notice of potential change #15 (NPC 15) with the Authority’s architect seeking additional payment for field office expenses incurred on the job site due to the Authority’s delay in obtaining the clearances. Worcester Brothers also claimed it had unabsorbed home office expenses attributable to the delay. In NPC 15, Worcester Brothers calculated its additional field office expenses based upon its daily field office overhead rate multiplied by the 98 days of delay it attributed to the Authority. 1 To calculate its unabsorbed home office expenses, Worcester Brothers used the so-called “Eichleay formula,” 2 to determine a daily home office overhead rate and multiplied that rate by the same 98 days of delay. The architect, acting on behalf of the Authority, denied the claims made in NPC 15.

On November 4, 1996, Worcester Brothers filed a motion for judgment against the Authority seeking damages for breach of contract based upon the failure to pay NPC 15. 3 The Authority filed an answer denying the allegations of the motion for judgment and rais *386 ing as an affirmative defense the claim that “[h]ome office damages based on the Eichleay formula are prohibited by Virginia law.”

At trial, Worcester Brothers contended that during the delay it incurred both additional field office expenses as a result of having to maintain its personnel at the job site and unabsorbed home office expenses. It presented evidence of its actual field office expenses related to the delay in the amount of $46,359.11. Worcester Brothers’ accounting system did not allocate its home office expenses to particular contracts. However, Joseph P. Noonan, Worcester Brothers’ president, testified that the unabsorbed home office expenses attributable to the delay amounted to $34,495.89. According to Noonan, that figure was calculated from statements prepared by Worcester Brothers’ accountants reflecting the total general and administrative expenses of the company during the relevant contract period and the application of the Eichleay formula to those expenses.

The Authority asserted numerous objections to Worcester Brothers’ evidence of damages. Pertinent to the issue presented on appeal, the Authority contended that Worcester Brothers had proven no actual damages as a result of the delay. It contended that the Eichleay formula calculation did not constitute proof of actual damages to a reasonable degree of certainty, but, rather, is merely a method for determining the amount of unabsorbed home office expenses attributable to a particular contract once the existence of such damages has been proven by other evidence. The Authority contended that Worcester Brothers had not shown that its workforce was actually idle as a result of the delay in obtaining the clearances and, thus, that none of its home office expenses was incurred as a result of the delay. Moreover, the Authority contended that the Eichleay formula was “totally and wholly irrelevant” to “a contract governed by state law.”

At the conclusion of the evidence, the trial court addressed the Authority’s contentions and reasoned that in order to succeed on a breach of contract damage claim for unabsorbed home office expenses resulting from a delay, the contractor was first required to show that it had incurred such damages by establishing that the government had caused the delay; that the contractor’s workforce was placed on standby as a result; and that the contractor was not free to engage in work on other projects during the delay. The trial court then found that the Authority’s delay was “manifest on this record” and was “egregious” and “frankly inexcusable.” The trial court further found that Worcester Brothers’ workforce had been on *387 “standby” because the Authority “never could advise the contractor that the area would not be available until a particular date. Instead it was a rolling deadline.” Finally, the trial court found that the “rolling deadline” also inhibited Worcester Brothers from seeking other contracts, and thereby minimizing the damage caused by the delay, since it could not be assured of the availability of its workforce for another project.

Having found that Worcester Brothers had satisfied its initial “burden of proving [home office] damages with reasonable certainty,” the trial court turned to the question whether the Eichleay formula could be used to calculate the amount of those damages. Recognizing that other courts had found the Eichleay formula to be “a fair way of approximating” such damages, the trial court noted that after auditing Worcester Brothers’ books, the Authority did not contend that any of the specific expenses were inappropriately claimed and that the Authority’s witnesses failed “to present any reasoned analysis of why Eichleay is inappropriate.” Accordingly, the trial court entered judgment for Worcester Brothers for both the field office expenses ($46,359.11) and the unabsorbed home office expenses as calculated by the Eichleay formula ($34,495.89). The trial court granted the Authority’s motion to reconsider, and, after receiving briefs from the parties, sustained its original ruling. We awarded the Authority this appeal.

DISCUSSION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
514 S.E.2d 147, 257 Va. 382, 1999 Va. LEXIS 48, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fairfax-county-redevelopment-housing-authority-v-worcester-bros-va-1999.