Complete Gen. Constr. Co. v. Ohio Dept. of Transp.

2002 Ohio 59, 94 Ohio St. 3d 54
CourtOhio Supreme Court
DecidedJanuary 16, 2002
Docket2000-1267
StatusPublished
Cited by10 cases

This text of 2002 Ohio 59 (Complete Gen. Constr. Co. v. Ohio Dept. of Transp.) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Complete Gen. Constr. Co. v. Ohio Dept. of Transp., 2002 Ohio 59, 94 Ohio St. 3d 54 (Ohio 2002).

Opinion

[This decision has been published in Ohio Official Reports at 94 Ohio St.3d 54.]

COMPLETE GENERAL CONSTRUCTION COMPANY, APPELLEE AND CROSS- APPELLANT, v. OHIO DEPARTMENT OF TRANSPORTATION, APPELLANT AND CROSS-APPELLEE. [Cite as Complete Gen. Constr. Co. v. Ohio Dept. of Transp., 2002-Ohio-59.] Public construction — Modified Eichleay formula is one way of determining unabsorbed home office overhead damages in public construction delay cases — Courts applying modified Eichleay formula must allow owners opportunity to dispute particular items contractor submits in an overall overhead cost presentation. (No. 00-1267—Submitted May 16, 2001—Decided January 16, 2002.) APPEAL and CROSS-APPEAL from the Court of Appeals for Franklin County, No. 98AP-1619. __________________ SYLLABUS OF THE COURT The Eichleay formula, modified for use in Ohio courts, is one way of determining unabsorbed home office overhead damages in public construction delay cases. Courts applying the formula must allow owners the opportunity to dispute particular items a contractor submits in an overall overhead cost presentation. __________________ PFEIFER, J. {¶ 1} This case evolved out of a contractor’s claim for additional costs on a highway construction project as a result of delays caused by the Ohio Department of Transportation (“ODOT”). The bulk of this case concerns the method of calculating unabsorbed home office overhead—the cost of running a contractor’s home office during the delay period—and whether Ohio should adopt the “Eichleay SUPREME COURT OF OHIO

formula,” an equation employed by federal courts in determining such costs. The formula acquired its name from the Armed Services Board of Contract Appeals decision in Eichleay Corp. (1960), ASBCA No. 5183, 60-2 BCA ¶ 2688, 1960 WL 538, and “is the most well-known formula for calculating unabsorbed overhead” costs arising out of government-caused delay. Shapiro & Worthington, Use of the Eichleay Formula to Calculate Unabsorbed Overhead for Government Caused Delay Under Manufacturing Contracts (1996), 25 Pub.Contr.L.J. 513, 514. We hold that Ohio courts may use the Eichleay formula, with certain important modifications, in calculating such costs. We do not find that the Eichleay formula is the exclusive manner of determining unabsorbed home office overhead. Factual Background {¶ 2} This action arises out of the construction of a stretch of I-670 from just north of downtown Columbus to Port Columbus International Airport. Construction of that portion of I-670 was broken into five sections, with each section being bid as a separate project. Appellee and cross-appellant, Complete General Construction Company (“Complete General”), successfully bid on four of those five projects. One of those four, Project 56-91 (“the Project”), is the focus of this action. {¶ 3} The Project provided for the construction of I-670 from the Greater Columbus Convention Center to a point just west of I-71. The contract called for the construction of that stretch of highway, including the erection of three new bridges and the widening of another. Work on the Project began on March 15, 1991, with a slated completion date of August 31, 1992. {¶ 4} However, early on in the Project, design errors relating to the bridges and attributable to ODOT caused a seven-month delay. Due to the delay, on May 13, 1992, ODOT granted Complete General a twelve-month work extension, moving the completion date to August 31, 1993. While the actual delay was seven months, an extension to March 31, 1993, automatically triggered an additional five-

2 January Term, 2002

month extension under the contract because the March date fell within the winter shutdown period. {¶ 5} Later, ODOT granted Complete General an additional sixty-day extension for other work not contemplated by the original contract, moving the completion date to October 31, 1993. {¶ 6} Following the completion of the Project, the parties entered into negotiations to compensate Complete General for costs it incurred as a result of the extension of the completion date. On October 31, 1996, they agreed that ODOT would pay Complete General $177,662.47 as final compensation for all costs related to the contract extensions, except “home office overhead, interest, major equipment costs, and bond costs.” The settlement was a part of Change Order 39. The parties continued negotiating on the unresolved issues. {¶ 7} On January 7, 1997, Complete General sued ODOT to recover unabsorbed home office overhead, idle equipment costs, extended equipment costs, and additional bond costs, as well as interest on all these costs from the time of completion of the Project. ODOT offered to pay Complete General $196,410.34: $182,500 for unabsorbed overhead, $888.31 for bond costs, and $13,022.03 for interest. Complete General accepted the amount as partial payment for the disputed claims, and continued on with its lawsuit. This partial settlement was memorialized in Change Order 40. {¶ 8} The parties tried the case before the Court of Claims beginning on April 13, 1998. On November 18, 1998, the court awarded Complete General $374,231.08. The award broke down as follows: $184,947 for unabsorbed home office overhead, $62,622.50 for idle equipment costs, $115,171.49 in interest on the overhead and idle equipment awards, and $11,490.09 in additional bond costs. The court found for ODOT on Complete General’s claim for extended equipment costs, i.e., costs for additional equipment time required beyond that originally allocated in Complete General’s bid.

3 SUPREME COURT OF OHIO

{¶ 9} Both parties appealed the decision of the Court of Claims. In its decision, the Franklin County Court of Appeals affirmed the judgment of the Court of Claims in part, reversed it in part, and remanded the cause for further proceedings. {¶ 10} The cause is before this court upon the allowance of a discretionary appeal and cross-appeal. Law and Analysis {¶ 11} Both parties appeal aspects of the court of appeals’ decision. We resolve those issues below. Unabsorbed Home Office Overhead {¶ 12} ODOT appeals this part of Complete General’s award based upon the lower courts’ reliance on the Eichleay formula for the calculation of home office overhead during the delay period. {¶ 13} Bids on construction projects incorporate two different kinds of costs. The first type, direct costs, include construction wages and equipment expenses and are attributed to specific projects. The second type, indirect costs, are the expenses involved in generally running a business, not attributable to any one project. The most significant indirect cost is home office overhead. Such costs typically include salaries of executive or administrative personnel, general insurance, rent, utilities, telephone, depreciation, professional fees, legal and accounting expenses, advertising, and interest on loans. See Interstate Gen. Govt. Contrs., Inc. v. West (Fed.Cir.1993), 12 F.3d 1053, 1058. {¶ 14} Each project a contractor undertakes derives benefits from the home office, and each contributes to paying for home office overhead. Contractors typically do not apportion overhead costs among individual projects. Each project in some degree is responsible for the contractor’s costs of simply doing business, and each project plays its proportionate part in paying those costs. When a delay occurs on a particular construction project, that particular project ceases to carry its

4 January Term, 2002

weight in regard to running the business, which can result in damages to the contractor. See Kauffman & Holman, The Eichleay Formula: A Resilient Means for Recovering Unabsorbed Overhead (1995), 24 Pub.Contr.L.J. 319, 320-321. {¶ 15} Assigning a value to a delayed project’s effect on home office overhead can be difficult.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ohio Edison Co. v. Houser
2018 Ohio 4156 (Ohio Court of Appeals, 2018)
1st Natl. Fin. Servs. v. Ashley
2018 Ohio 3134 (Ohio Court of Appeals, 2018)
Illuminatiny Company v. Cochran
2018 Ohio 2514 (Ohio Court of Appeals, 2018)
Tedla v. Al-Shamrookh
2017 Ohio 1021 (Ohio Court of Appeals, 2017)
Illum. Co. v. Burns
2014 Ohio 502 (Ohio Court of Appeals, 2014)
Bryan-Wollmann v. Domonko
854 N.E.2d 1108 (Ohio Court of Appeals, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
2002 Ohio 59, 94 Ohio St. 3d 54, Counsel Stack Legal Research, https://law.counselstack.com/opinion/complete-gen-constr-co-v-ohio-dept-of-transp-ohio-2002.