American Contractor's Indemnity v. Nicole Gas, 07ap-1039 (9-30-2008)

2008 Ohio 5056
CourtOhio Court of Appeals
DecidedSeptember 30, 2008
DocketNo. 07AP-1039.
StatusPublished
Cited by13 cases

This text of 2008 Ohio 5056 (American Contractor's Indemnity v. Nicole Gas, 07ap-1039 (9-30-2008)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Contractor's Indemnity v. Nicole Gas, 07ap-1039 (9-30-2008), 2008 Ohio 5056 (Ohio Ct. App. 2008).

Opinion

OPINION
{¶ 1} Defendants-appellants, Nicole Gas Production, Ltd. ("Nicole Gas"), Freddie L. Fulson ("Fulson"), Nicole Energy Marketing, Inc. ("Nicole Energy"), and Seaburyson Properties, Ltd. ("Seaburyson"), appeal from the judgment of the Franklin County Court of Common Pleas, in favor of plaintiffs-appellees, American Contractors *Page 2 Indemnity Company ("ACIC") and Goldleaf Financial, Ltd. ("Goldleaf"), on appellees' claim for breach of an indemnity contract.

{¶ 2} The relevant factual and procedural history follows. Nicole Gas is a party to several natural gas contracts with Columbia Gas of Ohio, Inc. ("Columbia Gas") and with several Columbia Gas subsidiaries. In 2003, Nicole Gas and Columbia Gas were engaged in litigation in the Franklin County Court of Common Pleas over whether Nicole Gas underdelivered gas under the contracts. While this litigation was pending, Nicole Gas filed a petition with the Federal Energy Regulatory Commission ("FERC"), seeking a declaration that Columbia Gas was required to install meters at each well subject of the contracts. On June 11, 2003, the FERC issued an order declaring that such installations were indeed the responsibility of Columbia Gas. Upon being informed of the FERC ruling, the Franklin County Court of Common Pleas ordered Columbia Gas to comply with the FERC's ruling by installing the meters. Columbia Gas refused, whereupon Nicole Gas filed suit in the United States District Court for the Eastern District of Virginia, seeking injunctive relief to enforce the FERC ruling.

{¶ 3} On September 22, 2003, the district court granted the requested injunctive relief, but conditioned same upon Nicole Gas posting a bond in the amount of $200,000, later reduced to $150,000. The district court's order specifies that the bond will be paid "[i]f Defendant [Columbia Gas] ultimately prevails in reversing the June 11, 2003 Order entered by the Federal Energy Regulatory Commission (FERC) in Docket No. RP03-243-000, or FERC issues an Order finding that Defendant had no obligation to install and pay for meters as of June 11, 2003 * * *" *Page 3

{¶ 4} Through its surety agency, Goldleaf, ACIC posted a surety bond in the amount of $150,000, on behalf of Nicole Gas. As collateral for the bond, Nicole Gas provided $112,330 in cash (held by Goldleaf), and liens on two trucks and an all-terrain vehicle. On October 1, 2003, Nicole Gas, Nicole Energy, Fulson, and Seaburyson all signed a general indemnity agreement in which they agreed to hold ACIC harmless as to any payments made on the bond. Nicole Gas, Nicole Energy, Fulson, and Seaburyson also signed a Pledge of Indemnity in favor of Goldleaf, in which they agreed to hold harmless both Goldleaf and the surety with which Goldleaf had privity, for any payments on the bond, plus attorney fees associated therewith.

{¶ 5} Meanwhile, Columbia Gas appealed the FERC's ruling to the United States Court of Appeals for the District of Columbia Circuit, arguing that the FERC lacked jurisdiction to interpret or enforce the tariff provision upon which FERC's ruling had been based. On April 15, 2005, the court of appeals ruled "[b]ecause the Natural Gas Act unambiguously denies FERC jurisdiction to issue the orders challenged in the petition for review, we grant the petition and vacate the orders." The court of appeals specifically declined to reach a review of the substantive issue that FERC had decided, that is, whether the tariff at issue required Columbia Gas to pay for the installation of meters at certain wells.

{¶ 6} Following the court of appeals' ruling vacating the FERC's order, Nicole Gas sent a letter to ACIC requesting that it not pay any amounts on the surety bond. Therein, Nicole Gas contended that because the court of appeals vacated the FERC's order, the condition of Columbia Gas obtaining an order "reversing" FERC's order had not occurred, and the obligation to pay on the surety bond had not been triggered. On July 26, 2005, *Page 4 however, upon application filed by Columbia Gas, the district court ordered that ACIC and Nicole Gas were jointly and severally liable to pay Columbia Gas $150,000 by August 1, 2005. On July 29, 2005, ACIC tendered payment in full to Columbia Gas. Subsequently, appellees brought the present action seeking to recover the amount of the bond less the value of the collateral, plus attorney fees and expenses associated with enforcement of the general indemnity agreement.

{¶ 7} Appellees moved for partial summary judgment. Appellants opposed the motion, arguing that ACIC breached its duty to file an appeal of the district court's order before paying on the bond. ACIC responded that, under the terms of the indemnity agreement, it had sole and absolute discretion to decide whether to appeal or to simply pay on the bond. The trial court concluded that ACIC had an implied duty to act in good faith, which included the duty to conduct a reasonable investigation into whether to appeal the district court's order. The court denied the motion for summary judgment because the record, at that time, lacked evidence as to whether ACIC took any actions to conduct an investigation before paying on the bond.

{¶ 8} The action was referred for a bench trial before a magistrate. Twelve days before the scheduled trial date, appellants filed a motion for leave to amend their answer and to assert a counterclaim for recovery of the collateral for the bond. The trial court referred that motion to the magistrate. Following trial on March 26 and March 27, 2007, the magistrate denied appellants' motion for leave to amend their answer and assert a counterclaim, finding that it was untimely and that granting it would be prejudicial to ACIC and Goldleaf. The magistrate also found in favor of appellees on their claim for breach of the indemnity agreement. *Page 5

{¶ 9} The trial court overruled appellants' objections to the magistrate's decision, adopted the magistrate's decision, and awarded appellees their requested attorney fees. The court determined that ACIC did not take opportunistic advantage of appellants and did nothing to injure appellants' rights under the indemnity agreement in deciding to pay on the bond rather than appeal the district court's order, and, therefore, ACIC did not breach its duty to act in good faith. Having concluded that ACIC acted in good faith and could not be estopped from enforcing the indemnity agreement, the court agreed with the magistrate's conclusion that appellants had clearly breached the express terms of the indemnity agreement and were liable for that breach.

{¶ 10} Appellants timely appealed and present three assignments of error for our review, as follows:

1. The Trial Court erred in finding, contrary to law, that Defendants-Appellants were liable under an indemnity agreement by applying the wrong standard in determining that Plaintiffs-Appellees did not breach their duty of good faith and fair dealing.

2. The Trial Court erred, contrary to law, in denying Defendants-Appellants Motion to Amend Answer and to Assert Counterclaim.

3. The Trial Court erred in awarding attorney fees, contrary to law, to Plaintiffs-Appellees.

{¶ 11}

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Accurate Elec. Constr., Inc. v. Ohio State Univ.
2019 Ohio 4992 (Ohio Court of Appeals, 2019)
Williams v. Natl. Assn. for the Advancement of Colored People
2019 Ohio 1897 (Ohio Court of Appeals, 2019)
Cleveland Hearing & Balance Ctr., Inc. v. N.E. Ohio Med. Univ.
2017 Ohio 8838 (Ohio Court of Appeals, 2017)
B&J Resources, L.L.C. v. 28925 Lorain Inc.
2017 Ohio 7248 (Ohio Court of Appeals, 2017)
Cleveland Hearing & Balance Ctr., Inc. v. N.E. Ohio Med. Univ.
2017 Ohio 2699 (Ohio Court of Claims, 2017)
Kish v. Magyar
2016 Ohio 7355 (Ohio Court of Appeals, 2016)
CosmetiCredit, L.L.C. v. World Fin. Network Natl. Bank
2014 Ohio 5301 (Ohio Court of Appeals, 2014)
Pertoria, Inc. v. Bowling Green State Univ.
2014 Ohio 3793 (Ohio Court of Appeals, 2014)
Reinhart v. Fostoria Plumbing, Heating & Elec. Supply, Inc.
2010 Ohio 4825 (Ohio Court of Appeals, 2010)
Homewood Homes, Inc. v. Helwig, 08ap-406 (4-9-2009)
2009 Ohio 1699 (Ohio Court of Appeals, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
2008 Ohio 5056, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-contractors-indemnity-v-nicole-gas-07ap-1039-9-30-2008-ohioctapp-2008.