Mech-Con Corporation v. Togo D. West, Jr., Secretary of the Army

61 F.3d 883, 40 Cont. Cas. Fed. 76,812, 1995 U.S. App. LEXIS 20650, 1995 WL 457820
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 4, 1995
Docket95-1048
StatusPublished
Cited by26 cases

This text of 61 F.3d 883 (Mech-Con Corporation v. Togo D. West, Jr., Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mech-Con Corporation v. Togo D. West, Jr., Secretary of the Army, 61 F.3d 883, 40 Cont. Cas. Fed. 76,812, 1995 U.S. App. LEXIS 20650, 1995 WL 457820 (Fed. Cir. 1995).

Opinion

LOURIE, Circuit Judge.

Mech-Con Corporation appeals from a decision of the Armed Services Board of Contract Appeals denying Meeh-Con’s appeal from a contracting officer’s final decision. Mech-Con Corp., ASBCA No. 45105, 94-3 BCA ¶ 27252. In his decision, the contracting officer denied Meeh-Con’s claim for unabsorbed home office overhead costs. Because part of the board’s decision is not supported by substantial evidence, we affirm-in-part and reverse-in-part.

BACKGROUND

The United States Army awarded Mech-Con a contract to upgrade the fire alarm system at Fort Belvoir, Virginia. This system was intended to operate by sending a signal along a transmission line from a building in which a fire is detected to the post firehouse, where an alarm sounds. Although the contract required Mech-Con to do most of the work to install and test the system, it also provided that the government would install the transmission lines for the upgraded system. Mech-Con was to complete its work by April 16, 1985, 180 days after the government issued a Notice to Proceed. For reasons unrelated to this appeal, Modification P00001 extended the completion date to July 9, 1985.

On April 19, 1985, the government informed Mech-Con that it was unable to install the required transmission lines. At that time, the contracting officer (“CO”) wrote Mech-Con that the government “will advise you at the earliest possible date as to what action will be required with respect to connection [of the new system] to the transmission lines.” By July 25,1985, Mech-Con had completed all the work it could complete without a decision concerning the transmission lines. The remaining work, including connecting and testing the system, could not be completed and Mech-Con left the work site. 1

After considering several alternatives, the government sent a letter to Mech-Con instructing the contractor to complete the project without the specified transmission lines. A subsequent meeting was held on April 23, 1986, to discuss completion of the contract. At that meeting, the government instructed Mech-Con as to the work required to complete the contract. Mech-Con did not remo-bilize on the work site until the beginning of August. The work was completed shortly after that, and the government accepted it on August 11, 1986.

Mech-Con submitted a properly certified claim for an equitable adjustment for unabsorbed home office overhead costs during the 399-day delay in completing the contract. Mech-Con calculated that the unabsorbed overhead totaled $60,847.50 based on the “Ei-chleay” formula. See Eichleay Corp., ASBCA No. 5183, 60-2 BCA ¶2688, 1960 WL 538, aff'd on reconsideration, 61-1 BCA ¶ 2894, 1960 WL 684. The CO denied the claim. However, the CO issued Modification P00003, which allowed $2,000 in direct costs “for other miscellaneous home office costs incurred by the contractor as a result of the delay.”

Mech-Con appealed to the board and the parties agreed to submit the case on the record. For purposes of the appeal, the parties filed a “Joint Stipulation of Facts,” which included the following stipulations:

20. The suspension of work from July 9, 1985 through April 23, 1986 [289 days] was unexpected, and Mech-Con *885 did not know how long it would last. Mech-Con had to stand ready to return, install equipment, make final connections, and maintain a presence for the testing by ADT.
21. Mech-Con was a small company, with a minimal home office staff. The home office staff could not be effectively reduced during the indefinite suspension period.
22. Mech-Con was required to supply statutory Miller Act payment and performance bonds on this project. Although the Government had no notice of the fact, Mech-Con had limited bonding capacity. Mech-Con’s bonds remained outstanding during the extended performance, including the suspension period.
26. Using the Eichleay formula, Mech-Con’s daily rate for allowable home office overhead allocable to this project is $152.50 per calendar day. Applying the formula, the entire amount of the claim in this appeal is $152.50 X 399 = $60,847.50.

The board denied the appeal for lack of proof of Mech-Con’s entitlement to damages calculated based on the Eichleay formula. In particular, the board held that Mech-Con failed to prove that the government’s delay precluded Mech-Con from accepting other work to absorb its overhead during the delay period. Moreover, despite the stipulation that Mech-Con had to “stand ready to return,” the board held that Mech-Con failed to prove that it had to remain ready to resume work on short notice. In so holding, the board relied on the government’s failure to object in July 1985 when Mech-Con demobilized from the work site as well as Mech-Con’s failure to remobilize until three months after the government directed it to complete the work. Mech-Con now appeals. We have jurisdiction over the appeal pursuant to 41 U.S.C. § 607(g)(1)(A) (1988).

DISCUSSION

Our review of board decisions is governed by the Contract Disputes Act of 1978, which provides that “the decision of the agency board on any question of law shall not be final or conclusive.” 41 U.S.C. § 609(b) (1988). We defer to the board’s findings of fact “unless the decision is fraudulent, or arbitrary, or capricious, or so grossly erroneous as to necessarily imply bad faith, or if such decision is not supported by substantial evidence.” Id. Substantial evidence “means such relevant evidence as a reasonable mind might accept as adequate to support a conclusion.” United States v. General Elec. Corp., 727 F.2d 1567, 1572 (Fed.Cir.1984).

On appeal, Mech-Con argues that the board erred in its determination that Mech-Con was not entitled to Eichleay formula damages. In particular, Mech-Con asserts that the board disregarded the stipulated facts which, in Meeh-Con’s view, established entitlement to its unabsorbed overhead costs. In support, Mech-Con asserts that our case law indicates that a prima facie case of entitlement to Eichleay formula damages for unabsorbed home office overhead costs can be established by showing that a government-imposed delay was of uncertain duration (“uncertainty”) and that the contractor had to stand by to perform the contract work (“standby”). Mech-Con argues that Joint Stipulation of Fact No. 20 proves “uncertainty” and “standby” and therefore that Mech-Con has established a prima facie case of entitlement to its unabsorbed overhead costs.

The government counters that a prima facie case for Eichleay formula damages cannot be established merely by showing “uncertainty” and “standby.” Rather, the government asserts that the proper test requires proof not only that the contractor was on “standby” during an “uncertain” period of delay, but also that the contractor could not have undertaken any other jobs during this delay period.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brett Noble v. Iowa District Court for Muscatine County
919 N.W.2d 625 (Court of Appeals of Iowa, 2018)
Jmr Construction Corp. v. United States
117 Fed. Cl. 436 (Federal Claims, 2014)
Englewood Terrace Ltd. Partnership v. United States
113 Fed. Cl. 718 (Federal Claims, 2013)
Southern Nuclear Operating Co. v. United States
637 F.3d 1297 (Federal Circuit, 2011)
Orlosky Inc. v. United States
68 Fed. Cl. 296 (Federal Claims, 2005)
P.J. Dick Inc. v. Principi
324 F.3d 1364 (Federal Circuit, 2003)
Gladwynne Const. v. Mayor and City Council of Baltimore
807 A.2d 1141 (Court of Special Appeals of Maryland, 2002)
Sergent Mechanical Systems, Inc. v. United States
54 Fed. Cl. 47 (Federal Claims, 2002)
Pete Vicari, General Contractor, Inc. v. United States
53 Fed. Cl. 357 (Federal Claims, 2002)
Complete Gen. Constr. Co. v. Ohio Dept. of Transp.
2002 Ohio 59 (Ohio Supreme Court, 2002)
Melka Marine, Inc. v. United States
187 F.3d 1370 (Federal Circuit, 1999)
Safeco Credit & Fraley Associates, Inc. v. United States
44 Fed. Cl. 406 (Federal Claims, 1999)
Melka Marine, Inc. v. United States
42 Cont. Cas. Fed. 77,319 (Federal Claims, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
61 F.3d 883, 40 Cont. Cas. Fed. 76,812, 1995 U.S. App. LEXIS 20650, 1995 WL 457820, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mech-con-corporation-v-togo-d-west-jr-secretary-of-the-army-cafc-1995.