Southern Nuclear Operating Co. v. United States

637 F.3d 1297, 2011 U.S. App. LEXIS 4966
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 11, 2011
Docket2008-5020
StatusPublished
Cited by53 cases

This text of 637 F.3d 1297 (Southern Nuclear Operating Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Nuclear Operating Co. v. United States, 637 F.3d 1297, 2011 U.S. App. LEXIS 4966 (Fed. Cir. 2011).

Opinion

DYK, Circuit Judge.

Plaintiffs Southern Nuclear Operating Company, Alabama Power Company, and Georgia Power Company (collectively, “plaintiffs”) filed suit in the Court of Federal Claims (“Claims Court”) against the United States, alleging that the United States Department of Energy (“Energy”) had partially breached contracts by failing to accept spent nuclear fuel (“SNF”) for storage beginning on January 31, 1998. The Claims Court granted summary judgment for plaintiffs on liability. It then held a trial to determine damages for storage costs incurred that would not have been necessary if Energy had fulfilled its obligation to begin accepting SNF in 1998. S. Nuclear Operating Co. v. United States, 77 Fed.Cl. 396, 460 (2007). The Claims Court also determined that the United States waived its defense that the “unavoidable delays” clause of its contracts precluded expectancy damages. Id. at 452-59. We vacate-in-part the damage award and remand to the Claims Court for further consideration with respect to two of three power plants. We affirm the damage award as to one plant. We also affirm the Claims Court’s conclusion that the United States waived its “unavoidable delays” defense.

BACKGROUND

In January 1983, Congress passed the Nuclear Waste Policy Act of 1982, Pub.L. *1299 No. 97-425, 96 Stat. 2201 (codified as amended at 42 U.S.C. §§ 10101-270 (1987)) [hereinafter NWPA], under which all nuclear utilities entered into a Standard Contract with Energy. These contracts obligated the utilities to pay fees into the Nuclear Waste Fund. In return, Energy was obligated to pick up and store the utilities’ SNF and high-level radioactive waste (“HLW”). The NWPA and Standard Contract obligated Energy to begin pick up by January 31, 1998. However, the contracts also contained an unavoidable delays clause. In 1987, Congress amended the NWPA, requiring Energy to develop only one permanent geologic repository for nuclear waste and forbidding Energy from constructing an interim storage facility until the Nuclear Regulatory Commission authorized the permanent facility. In part because of these constraints, Energy was unable to begin accepting SNF in 1998 as required by the statute and by contract.

On July 29, 1998, plaintiffs filed their complaint in the Claims Court, alleging partial breach of contract. In 2004, the court granted summary judgment on liability, finding that the government had partially breached the Standard Contract by failing to begin accepting SNF in January 1998. There is no issue on appeal as to liability; liability in these SNF cases has been established. See Neb. Pub. Power Dist. v. United States, 590 F.3d 1357 (Fed.Cir.2010) (en banc). The facts revolve around two main issues — the calculation of plaintiffs’ damage award and the government’s alleged waiver of its “unavoidable delays” defense with respect to expectancy damages.

I

In 2005, the Claims Court held a trial on damages. The plaintiffs sought “reimbursement of their actual costs spent mitigating [Energy’s] delays.” S. Nuclear, 77 Fed.Cl. at 399. These costs were for construction of on-site storage at their plants that would not have been necessary had Energy performed its contractual obligations. In essence, the parties agreed that damages were the costs the plaintiffs actually incurred to store SNF in the real world less the costs that the plaintiffs would have incurred to store SNF had Energy performed.

The plaintiffs alleged that they incurred additional storage costs at three different power plants: Plant Hatch, Plant Farley, and Plant Vogtle. 1 At Plant Hatch, they sought damages for the cost of constructing an Independent Spent Fuel Storage Installation (“ISFSI”) as well as the cost of dry storage casks for the ISFSI and the expenses incurred in loading the casks onto the ISFSI. ISFSIs are essentially concrete pads constructed to store dry storage casks and located adjacent to (rather than inside) reactor buildings. Dry storage casks are steel containers designed to hold (and prevent leakage of) SNF when it is removed from the reactor. At Plant Farley, plaintiffs also sought reimbursement for an ISFSI as well as for storage casks and loading costs. Lastly, at Plant Vogtle, plaintiffs sought damages for the cost of “reracking.” Reracking is a method of increasing wet storage (i.e., storage inside the reactor pool), as opposed to using dry storage casks. It involves purchasing higher density storage *1300 racks so that more SNF can be stored in the wet pools adjacent to the core rather than transferred to a dry storage installation (like an ISFSI) outside of the reactor building. The United States argued that these storage costs at all three plants would also have been incurred in the non-breach world (i.e., if Energy had performed) and that, therefore, the government’s breach did not cause the plaintiffs to make these expenditures.

However, determining what costs would have been incurred absent Energy’s breach proved difficult because the Standard Contract itself did not specify a rate at which Energy was obligated to pick up SNF. Instead, the Standard Contract required Energy to issue annual capacity reports (“ACRs”), stating which plants would be granted pick-up allocations first and projecting how much SNF would be accepted by Energy. The ACRs, issued annually, included both an industry-wide pick-up rate and projected pick-up allocations for each individual plant. In 2008, we held in Pacific Gas & Electric Co. v. United States, 586 F.3d 1282, 1292 (Fed.Cir.2008), that the Standard Contract required Energy to accept SNF at the rates set forth in the 1987 ACR. However, the Claims Court issued its opinions in this case in 2007 (and this appeal was stayed). Therefore, at the time of the 2007 decision, neither the parties nor the Claims Court knew that the 1987 ACR rates were contractually required.

At trial, the government argued that the court should use the 1991 ACR acceptance rates, approximately 900 metric tons of uranium (“MTU”) per year, as the rates required by the Standard Contract. The plaintiffs, conversely, urged the court to use a 3000 MTU per year acceptance rate to determine how much SNF Energy would have picked up in the non-breach world. Neither party advocated for the 1987 ACR rates, which ramped up to approximately 2650 MTU per year. The Claims Court explicitly declined to determine a particular contractual acceptance rate. Instead, the Claims Court concluded that “the reracking at Plant Vogtle and the dry storage at Plants Hatch and Farley would not have occurred if [Energy] had been performing at any reasonable rate [defined as between 2000 and 3000 MTU per year].” S. Nuclear, 77 Fed.Cl. at 439. It then continued that, “[e]ven at the [lower] rates under the December 1991 ACR, ... storage shortages would likely have been accommodated” in the non-breach world (i.e., the additional storage facilities would not have been required). Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Community Health Choice, Inc. v. United States
970 F.3d 1364 (Federal Circuit, 2020)
Supreme Foodservice GmbH
Armed Services Board of Contract Appeals, 2020
Stockton East Water District v. United States
133 Fed. Cl. 204 (Federal Claims, 2017)
Georgia Power Company v. United States
132 Fed. Cl. 412 (Federal Claims, 2017)
Pacific Gas and Electric Co. v. United States
838 F.3d 1341 (Federal Circuit, 2016)
Englewood Terrace Ltd. Partnership v. United States
629 F. App'x 977 (Federal Circuit, 2015)
weston/bean Joint Venture v. United States
123 Fed. Cl. 341 (Federal Claims, 2015)
System Fuels, Inc. v. United States
120 Fed. Cl. 635 (Federal Claims, 2015)
VICI Racing, LLC v. T-Mobile USA, Inc.
87 F. Supp. 3d 697 (D. Delaware, 2015)
Sacramento Municipal Utility District v. United States
120 Fed. Cl. 270 (Federal Claims, 2015)
Alabama Power Company v. United States
119 Fed. Cl. 615 (Federal Claims, 2014)
Energy Northwest v. United States
115 Fed. Cl. 69 (Federal Claims, 2014)
Carolina Power & Light Co. v. United States
115 Fed. Cl. 57 (Federal Claims, 2014)
Englewood Terrace Ltd. Partnership v. United States
113 Fed. Cl. 718 (Federal Claims, 2013)
System Fuels, Inc. v. United States 0
110 Fed. Cl. 583 (Federal Claims, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
637 F.3d 1297, 2011 U.S. App. LEXIS 4966, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-nuclear-operating-co-v-united-states-cafc-2011.