Carolina Power & Light Co. v. United States

115 Fed. Cl. 57, 2014 U.S. Claims LEXIS 320, 2014 WL 940583
CourtUnited States Court of Federal Claims
DecidedMarch 10, 2014
Docket1:11-cv-00869
StatusPublished
Cited by4 cases

This text of 115 Fed. Cl. 57 (Carolina Power & Light Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carolina Power & Light Co. v. United States, 115 Fed. Cl. 57, 2014 U.S. Claims LEXIS 320, 2014 WL 940583 (uscfc 2014).

Opinion

OPINION AND ORDER

WHEELER, Judge.

Plaintiffs Carolina Power & Light Company (“CP & L”) and Florida Power Corporation (“FPC”) claim damages of $104,991,508 from Defendant caused by the failure of the Department of Energy (“DOE”) to collect and dispose of spent nuclear fuel beginning January 31, 1998 under the terms of the DOE Standard Contract.

This is a “Round 2” spent nuclear fuel (“SNF”) damages case. See Indiana Michigan Power Co. v. United States, 422 F.3d 1369, 1378 (Fed.Cir.2005) (utilities required to file successive actions for damages related to DOE’s breach within six years of incurring such damages). “Round 1” of this ease covered Plaintiffs’ claims for damages incurred through December 31, 2005. The Round 1 litigation was resolved by this Court in 2008 and upon remand in 2011. Carolina Power & Light Co. v. United States, 82 Fed.Cl. 23 (2008); Carolina Power & Light Co. v. United States, 98 Fed.Cl. 785 (2011). This proceeding covers damages sustained from January 1, 2006 through December 31, 2010, and covers the same four nuclear power plant sites as Round 1: the Harris, Brunswick, Robinson, and Crystal River sites.

CP & L and FPC are wholly-owned subsidiaries of Progress Energy, Inc., a public utility in the southeast United States. Progress Energy, Inc. completed a merger with Duke Energy Corporation on July 2, 2012. CP & L is now known as Duke Energy Progress, Inc. 1 Plaintiffs’ damages consist of costs incurred in mitigation of DOE’s partial breach of the Standard Contract. This Court has jurisdiction over Plaintiffs’ claims pursuant to the Tucker Act, 28 U.S.C. § 1491(a). See PSEG Nuclear, LLC v. United States, 465 F.3d 1343 (Fed.Cir.2006). Defendant’s liability for partial breach of contract has already been established. See Maine Yankee Atomic Power Co. v. United States, 225 F.3d 1336, 1337-40 (Fed.Cir.2000) (“Maine Yankee”). Thus, the questions currently before the Court are limited to the calculation and allocation of damages incurred from the DOE’s continuing breach.

Plaintiffs’ damages claims fall into five broad categories: (1) $66,375,235 to complete construction of an Independent Spent Fuel Storage Installation 2 at Brunswick; (2) $7,760,680 to expand and load spent fuel onto the dry storage facility at Robinson; (3) $21,143,250 to design, engineer, and develop *60 a dry storage facility at Crystal River; (4) $4,291,417 for the procurement and installation of additional racks in the Harris C spent fuel pool; and (5) $5,420,926 to conduct transshipments of spent fuel from the Brunswick to Harris plant. However, of this approximately $105 million claim, only $23 million is contested by the Government.

The Court conducted a three-day trial in Washington, D.C. during September 23-25, 2013. Plaintiffs called the following witnesses: Allen Brittain, manager of nuclear security at Brunswick; Steve Edwards, manager of dry fuel storage at Duke Energy; David Guseman, manager of nuclear information technology at Brunswick; Denise Hards, business planning manager for customer operations at Progress Energy; and Richard Tripp, project manager for the dry storage facility project at Brunswick. Counsel for the Defendant called Larry Johnson and Gregory A. Maret as expert witnesses.

For the reasons explained below, the Court finds that Plaintiffs are entitled to recover $103,748,230.14 in mitigation damages through December 31, 2010. The Court has disallowed three elements of Plaintiffs’ damages claims. For these items: the Brunswick computer system replacement; the Brunswick crane studies; and the Crystal River 3 mobile BRE, the Court concludes that Plaintiffs would have incurred these expenses for other reasons absent DOE’s partial breach.

Findings of Fact

On April 30, 2013, the Court ordered the parties to undergo a comprehensive pretrial accounting review process to reach agreement, as much as possible, on the costs associated with each of Progress Energy’s mitigation efforts. See Pretrial Order on Damages (Dkt. No. 12). With Progress Energy’s cooperation, Defendant reviewed invoices, purchase orders and contracts, accounting records and work orders, and other electronic data. As a result of this process, the Government does not dispute that Progress Energy incurred the costs it claims as damages for the period from January 1, 2006 through December 31, 2010.

The pretrial accounting review substantially narrowed the issues before the Court. Defendant acknowledges that Plaintiffs are entitled to recover approximately $82 million. Defendant’s primary objection to the approximately $23 million in dispute is that these costs were not caused by the breach. The following facts are relevant to deciding the remaining issues of disagreement.

A. The Standard Contract for the Disposal of Spent Nuclear Fuel

On January 7, 1983, Congress passed the Nuclear Waste Policy Act of 1982 (“NWPA”), Pub.L. 97-425, 96 Stat. 2201, codified at 42 U.S.C. §§ 10101-10270 (1982). 3 In adopting the NWPA, Congress recognized that “radioactive waste creates potential risks and requires safe and environmentally acceptable methods of disposal,” and that “a national problem has been created by the accumulation of [spent nuclear fuel].” 42 U.S.C. § 10131(a)(1)-(2).

DOE, acting on behalf of the Government, entered into a “Contract for Disposal of Spent Nuclear Fuel and/or High Level Radioactive Waste” (the “Standard Contract”) with both CP & L and FPC. (StipJI9). The contract CP & L executed covered the SNF generated at the Brunswick, Harris, and Robinson plants, and the contract FPC executed covered the SNF generated at the Crystal River plant. (Stip-¶ 10).

Under the Standard Contract, CP & L and FPC have paid quarterly fees to DOE since April 7, 1983, based on electricity production from nuclear fuel in exchange for DOE’s obligation to dispose of spent nuclear fuel and high level waste beginning no later than January 31, 1998. (Stip-¶ 13). Through December 31, 2010, Progress Energy paid approximately $820 million in fees for the disposal of spent fuel under the contracts. (Stip-¶ 14). To date, DOE has not provided for the transportation of any SNF or high level radioactive waste from Progress Energy’s sites to a DOE facility.

*61 B. Progress Energy’s Causation Model

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
115 Fed. Cl. 57, 2014 U.S. Claims LEXIS 320, 2014 WL 940583, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carolina-power-light-co-v-united-states-uscfc-2014.