Northern States Power Co. v. United States

78 Fed. Cl. 449, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20259, 2007 U.S. Claims LEXIS 307
CourtUnited States Court of Federal Claims
DecidedSeptember 26, 2007
DocketNo. 98-484C
StatusPublished
Cited by24 cases

This text of 78 Fed. Cl. 449 (Northern States Power Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northern States Power Co. v. United States, 78 Fed. Cl. 449, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20259, 2007 U.S. Claims LEXIS 307 (uscfc 2007).

Opinion

OPINION

WIESE, Senior Judge.

This case is before the court following a trial on contract damages. Plaintiff, Northern States Power Company, seeks to recover $172,154,000 in costs allegedly incurred to mitigate the Department of Energy’s (“DOE”) partial breach of a contract requiring DOE to begin the pick-up and storage of plaintiffs spent nuclear fuel and other high-level radioactive waste no later than January 31, 1998.1 For the reasons set forth below, we conclude that plaintiff is entitled to recover $116,485,000 in contract damages through December 31, 2004.2

FACTS

Plaintiff is a public utility that is engaged in the generation of electrical power from fissionable materials.3 The utility operates three nuclear reactors in Minnesota, two of which are located at the Prairie Island nuclear power plant and the other at the Montieello nuclear power plant. The power generated from these reactors is distributed throughout the mid-west and western regions of the United States.

On June 20, 1983, plaintiff entered into a contract with DOE that required plaintiffs payment of an annual fee in return for DOE’s acceptance, transfer, and permanent storage of the spent nuclear fuel and other hazardous waste produced by the utility’s generation of electricity at Prairie Island.4 The industry-wide contract, formally titled “Standard Contract for the Disposal of Spent Nuclear Fuel and/or High-Level Radioactive Waste” (“Standard Contract”), was executed under the authority of the Nuclear Waste Policy Act of 1982 (the “Act”), Pub.L. No. 97-425, 96 Stat. 2201 (codified as amended at 42 U.S.C. §§ 10101-10270), which authorized the Secretary of DOE to “enter into contracts with any person who generates or holds title to high-level radioactive waste, or spent nuclear fuel, of domestic origin for the acceptance of title, subsequent transportation, and disposal of such waste or spent nuclear fuel.” 42 U.S.C. § 10222(a)(1).

Although both the Act and plaintiffs contract identified January 31, 1998, as the required starting date for DOE’s pick-up of spent nuclear fuel (42 U.S.C. § 10222(a)(5)(B); 10 C.F.R. § 961.11), the contract contained no other schedule identifying the timing of DOE’s performance. DOE recognized from the start, however, that fulfillment of the Act’s purpose dictated a waste acceptance rate that would eliminate the need for any utility to provide its own at-reactor storage after January 31, 1998. Thus, in a December 20, 1983, draft of its [452]*452statutorily required “Mission Plan,”5 DOE advised the nuclear energy industry of its contemplated waste acceptance strategy as follows:

[W]aste materials will be accepted in accordance with a Waste Acceptance Schedule designed to provide an acceptance rate in the first five years such that no utility will have to provide additional storage capacity after January 31, 1998. Subsequently, the acceptance rate will be equal to or greater than the actual discharge rate of spent fuel each year.

The draft Mission Plan went on to advise that even in the event of a delay in the opening of a permanent waste repository, DOE anticipated that timely performance would be achieved through the use of temporary alternative storage facilities, including a “Monitored Retrievable Storage” (“MRS”) facility.6 Specifically, the draft Mission Plan provided:

[DOE] does not intend to delay or postpone the acceptance of civilian radioactive wastes even if a permanent geologic repository is not completed by 1998. The planning approach adopted by [DOE] has been designed to assure that an acceptable facility will be available when needed, as in the case of Federal Interim Storage, or within eight to eleven years after Congressional approval (1993 to 1996) in the case of Monitored Retrievable Storage.

DOE issued its finalized Mission Plan in June 1985. Thereafter, in March 1987, DOE submitted a report to Congress identifying an MRS facility as the only means by which DOE could begin to take spent nuclear fuel from utilities in 1998 and proposing the construction and operation of an MRS facility on the Clinch River in Tennessee. In order to address concerns that an MRS facility would diminish the resolve to develop a permanent geologic repository, DOE additionally proposed, over utility industry objection, that Congress link the start-up of an MRS facility to the schedule of a permanent repository by requiring that radioactive waste not be accepted at the MRS facility until DOE received construction authorization for a permanent repository from the Nuclear Regulatory Commission (“NRC”). In addition, DOE recommended that the total storage capacity of the MRS facility be limited to 15,000 metric tons uranium (“MTU”).

In June 1987, DOE issued an amendment to its Mission Plan advising that it was unlikely that DOE would construct a permanent repository and begin pick-up of spent nuclear fuel by January 31, 1998. Specifically, the 1987 amendment included waste acceptance schedules that anticipated DOE’s receipt of spent nuclear fuel at a permanent repository in 2003, five years later than originally expected. Additionally, the amendment projected an acceptance schedule for the proposed MRS facility that included a six-year ramp-up period beginning in 1998, followed in 2004 by a steady-state acceptance rate roughly equivalent to the nuclear energy industry’s annual average waste output of 2650 MTU. The amendment provided, however, that the proposed schedule was “only an approximation of how the system may operate and is subject to considerable variation.” The amendment further cautioned that “[i]f the Congress does not approve the MRS facility, the transfer of the waste to DOE facilities may not be able to begin in 1998.”

Later that year, on December 22, 1987, Congress authorized the proposed MRS facility, but the same concerns that had thwarted the construction of a permanent repository— political opposition borne of environmental concerns — ultimately prevented the MRS facility from being built.7 Indeed, by 1988, [453]*453DOE recognized that linking the construction of a permanent repository to the construction of an MRS facility made it highly unlikely that DOE could begin any waste acceptance earlier than 2008. Thus, by 1987-88, DOE, although continuing to plan for contract performance, was also very much aware that the fulfillment of its contract obligations depended upon decisions yet to be made by Congress concerning possible modifications to the linkages between the permanent repository and the MRS facility.

It was against this background that plaintiff began to focus on its future spent fuel storage needs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vistas Construction of Illinois, Inc.
Armed Services Board of Contract Appeals, 2016
Energy Northwest v. United States
115 Fed. Cl. 69 (Federal Claims, 2014)
Carolina Power & Light Co. v. United States
115 Fed. Cl. 57 (Federal Claims, 2014)
Portland General Electric Co. v. United States
107 Fed. Cl. 633 (Federal Claims, 2012)
Niagara Mohawk Power Corp. v. United States
98 Fed. Cl. 313 (Federal Claims, 2011)
Kansas Gas & Electric Co. v. United States
95 Fed. Cl. 257 (Federal Claims, 2010)
Entergy Nuclear Vermont Yankee, LLC v. United States
95 Fed. Cl. 160 (Federal Claims, 2010)
Yankee Atomic Power Co. v. United States
94 Fed. Cl. 678 (Federal Claims, 2010)
Southern California Edison Co. v. United States
93 Fed. Cl. 337 (Federal Claims, 2010)
Dairyland Power Cooperative v. United States
90 Fed. Cl. 615 (Federal Claims, 2009)
Wisconsin Electric Power Co. v. United States
90 Fed. Cl. 714 (Federal Claims, 2009)
Consumers Energy Co. v. United States
84 Fed. Cl. 670 (Federal Claims, 2008)
Dominion Resources, Inc. v. United States
84 Fed. Cl. 259 (Federal Claims, 2008)
Boston Edison Co. v. United States
80 Fed. Cl. 468 (Federal Claims, 2008)
Southern Nuclear Operating Co. v. United States
79 Fed. Cl. 135 (Federal Claims, 2007)
System Fuels, Inc. v. United States
78 Fed. Cl. 769 (Federal Claims, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
78 Fed. Cl. 449, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20259, 2007 U.S. Claims LEXIS 307, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northern-states-power-co-v-united-states-uscfc-2007.