Entergy Nuclear Vermont Yankee, LLC v. United States

95 Fed. Cl. 160, 72 ERC (BNA) 2119, 2010 U.S. Claims LEXIS 756
CourtUnited States Court of Federal Claims
DecidedSeptember 24, 2010
DocketNo. 03-2663C
StatusPublished
Cited by17 cases

This text of 95 Fed. Cl. 160 (Entergy Nuclear Vermont Yankee, LLC v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Entergy Nuclear Vermont Yankee, LLC v. United States, 95 Fed. Cl. 160, 72 ERC (BNA) 2119, 2010 U.S. Claims LEXIS 756 (uscfc 2010).

Opinion

OPINION AND ORDER

WHEELER, Judge.

Plaintiff Entergy Nuclear Vermont Yankee, LLC (“ENVY”)2 is claiming damages caused by the failure of the Department of Energy (“DOE”) to collect and dispose of spent nuclear fuel generated at the Vermont Yankee Nuclear Power Station (“VYNPS”), a commercial power plant currently owned by ENVY. In June 1983, Vermont Yankee Nuclear Power Corporation (“Vermont Yankee”), the prior owner of the VYNPS, entered into a Standard Contract for Disposal of Spent Nuclear Fuel and/or High-Level Radioactive Waste (“Standard Contract”) with DOE, whereby DOE agreed to begin collecting and disposing of spent fuel from the VYNPS not later than January 31, 1998. To date, DOE has yet to collect and dispose of any spent fuel. In 2002, ENVY purchased the VYNPS from Vermont Yankee. Under their purchase and sale agreement, Vermont Yankee assigned certain Standard Contract rights and duties to ENVY. ENVY filed its complaint in this Court on November 12, 2003, seeking damages for DOE’s partial breach of the Standard Contract. (Compl. 1.)

Initially, the Court consolidated this case with Vermont Yankee Nuclear Power Corporation v. United States, No. 02-898C, a case brought by Vermont Yankee asserting claims arising from its ownership and operation of the VYNPS. On October 19, 2006, the Court granted ENVY’s motion for summary judgment on liability, following Federal Circuit precedent that DOE had breached every utility’s Standard Contract when it failed to accept spent fuel beginning on January 31, 1998. See Vermont Yankee Nuclear Power Corp. v. United States, 73 Fed.Cl. 236, 245 (2006) (citing Maine Yankee Atomic Power Co. v. United States, 225 F.3d 1336, 1342 (Fed.Cir.2000); Northern States Power Co. v. United States, 224 F.3d 1361, 1367 (Fed.Cir.2000)). ENVY later moved for partial summary judgment regarding its ownership and right to pursue damages claims against DOE for partial breach of the Standard Contract. The Court granted ENVY’s motion on October 21, 2008, holding that Vermont Yankee’s purchase and sale agreement with ENVY did not reserve for Vermont Yankee any damages or diminution-in-value claims. The Court dismissed Vermont Yankee’s claims with prejudice. Vermont Yankee Nuclear Power Corp. v. United States, 84 Fed.Cl. 339 (2008). Thus, in the present posture, only ENVY’s damages claims remain to be decided. The Tucker Act grants this Court jurisdiction to hear these claims. See PSEG Nuclear, LLC v. United States, 465 F.3d 1343, 1349-50 (Fed.Cir.2006).

ENVY claims $47,443,881 in damages for costs it incurred through April 30, 2008. ENVY also seeks recovery of $7,472,866 for the cost of capital, raising its total claim to $54,916,747. Defendant concedes liability of $34,895,467, but argues that ENVY is not entitled to recover the following: (1) $9,608,189 in costs related to ENVY’s legislative efforts to acquire a Certificate of Public Good from the State of Vermont; (2) $2,008,727 in overhead costs; (3) $276,980 in costs to transport and dispose of contaminated soil and asphalt; and (4) $654,518 in costs related to ENVY’s purchase of a work platform, characterization of spent fuel, preparatory activities for cask loading, and loading mobilization. Defendant also argues that ENVY is not entitled to recover the cost of capital.

Defendant contends that the costs ENVY incurred in obtaining a Certificate of Public Good from the State of Vermont were not foreseeable as a result of DOE’s partial breach. Defendant further argues that Vermont is federally preempted from regulating nuclear power plants, and that ENVY failed to challenge the State legislature’s demands on such grounds. Defendant also asserts that ENVY’s other costs are unrelated to DOE’s delay or otherwise would have been incurred even if DOE had timely commenced accepting spent fuel in January 1998.

[168]*168The Court conducted a four-day trial in Washington, D.C. from March 28 through April 1, 2010. During trial, the Court received the testimony of fourteen witnesses, two of whom were experts. The parties filed their post-trial briefs on May 20, 2010, and reply briefs on June 25, 2010. The Court heard closing arguments on July 28, 2010.

In brief summary, the Court finds that ENVY is entitled to recover $46,645,454 in mitigation damages. The Court calculated these damages by starting with the uncontested amount of $34,895,467, and awarding additional recovery for the following contested items: (1) $9,608,189 in costs related to the Certificate of Public Good, including contributions to the Clean Energy Development Fund, the visual barrier costs, the river flood analysis cost, and the legal and lobbying fees ENVY incurred toward the enactment of Vermont legislation; (2) $654,518 in costs associated with the Holtee dry fuel storage project, including costs incurred in characterizing spent nuclear fuel, constructing a work platform, and developing procedures and internal labor costs; (3) $276,980 for the removal of radioactive soil and asphalt; and (4) $1,210,300 in “material loader” overhead costs. The Court denies recovery for $788,414 in “capital suspense” and $10,013 in “payroll loader” overhead costs as being too attenuated and not proven with reasonable certainty. The Court further denies ENVY’s $7,472,866 cost of capital claim as prohibited by law. Each of ENVY’s claims will be addressed in detail below.

Factual Background,3 A. Vermont Yankee Nuclear Power Station

The VYNPS is located in Vernon, Vermont, approximately five miles south of Brat-tleboro, Vermont. (Stip. ¶ 1.)4 The VYNPS began commercial operations in 1972, and consists of one Boiling Water Reactor (“BWR”) unit, designed and manufactured by General Electric. Id.; see also Thayer, Tr. 64. The VYNPS currently is licensed to operate until 2012. (Stip. ¶ 2.) ENVY submits ted an application to the Nuclear Regulatory Commission (“NRC”) in January 2006 to extend the current license through 2032. Id. The application currently is pending. Id.

A BWR, unlike a pressurized water reactor, is a type of “direct cycle nuclear plant” whereby water in a reactor vessel is heated and boiled to generate steam. (Thayer, Tr. 64.) The steam drives a turbine, mechanically powering a generator to produce electricity. (Thayer, Tr. 64; Brewer, Tr. 1013-14.) Eventually, the water coming out of the turbine is condensed and returned back into the reactor vessel where the process repeats. (Brewer, Tr. 1013-14.)

Nuclear fuel at the VYNPS consists of cylindrically shaped pellets, measured in Metric Tons of Uranium, or “MTUs.” (Stip. ¶ 9.) The uranium pellets are filled in zirconium tubes or rods, which are put together in a “rectangular array” to form an individual fuel assembly. (Stip. ¶ 9; Brewer, Tr. 1015.) Each fuel assembly contains approximately 70 to 80 fuel rods, each rod about the diameter of a finger and ten to eleven feet long. (Thayer, Tr. 68.) The VYNPS reactor core holds 368 fuel assemblies. (Stip. ¶ 7; Thayer, Tr. 68.)

While the fuel assemblies are used to generate electricity, nuclear plants eventually must “refuel,” or change out a portion of the fuel in the reactor core when it is no longer efficient to generate electricity from the burning of that fuel. See generally Pac. Gas & Elec. Co. v. State Energy Res. Conservation & Dev. Comm’n,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dairyland Power Cooperative v. United States
128 Fed. Cl. 499 (Federal Claims, 2016)
Entergy Gulf States, Inc. v. United States
125 Fed. Cl. 678 (Federal Claims, 2016)
System Fuels, Inc. v. United States
125 Fed. Cl. 331 (Federal Claims, 2016)
Yankee Atomic Electric Company v. United States
113 Fed. Cl. 323 (Federal Claims, 2013)
Entergy Nuclear Vermont Yankee, LLC v. Shumlin
733 F.3d 393 (Second Circuit, 2013)
Kansas Gas and Electric Co. v. United States
685 F.3d 1361 (Federal Circuit, 2012)
Entergy Nuclear Vermont Yankee, LLC v. Shumlin
838 F. Supp. 2d 183 (D. Vermont, 2012)
Power Authority v. United States
99 Fed. Cl. 661 (Federal Claims, 2011)
Entergy Nuclear Fitzpatrick, LLC v. United States
101 Fed. Cl. 305 (Federal Claims, 2011)
Carolina Power & Light Co. v. United States
98 Fed. Cl. 785 (Federal Claims, 2011)
Gaylord v. United States
98 Fed. Cl. 389 (Federal Claims, 2011)
Kansas Gas & Electric Co. v. United States
95 Fed. Cl. 257 (Federal Claims, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
95 Fed. Cl. 160, 72 ERC (BNA) 2119, 2010 U.S. Claims LEXIS 756, Counsel Stack Legal Research, https://law.counselstack.com/opinion/entergy-nuclear-vermont-yankee-llc-v-united-states-uscfc-2010.