Entergy Nuclear Fitzpatrick, LLC v. United States

101 Fed. Cl. 464, 2011 U.S. Claims LEXIS 2131, 2011 WL 5248339
United States Court of Federal Claims·Decided November 3, 2011·No. No. 03-2627 C·Published·Cited by 3 cases

Opinion

OPINION AND ORDER

DAMICH, Judge.

At issue is Defendant’s motion for reconsideration of this Court’s August 3, 2010, [465]*465Order, striking Defendant’s Unavoidable Delays defense. Entergy Nuclear FitzPatrick, LLC v. United States, 93 Fed.Cl. 739 (2010). Based on a writ of mandamus issued by the United States Court of Appeals for the D.C. Circuit in Northern States Power Co. v. Dep’t of Energy, 128 F.3d 754 (D.C.Cir.1997) (“Northern States I”), which the United States Court of Appeals for the Federal Circuit has held was within the D.C. Circuit’s jurisdiction to issue and therefore entitled to preclusive effect in proceedings before the Court of Federal Claims, Nebraska Public Power Dist. v. United States, 590 F.3d 1357, 1359, 1363 (Fed.Cir.2010) (en banc) (“Nebraska Public Power ” or “NPPD ”), this Court granted Plaintiffs motion to strike.

The Government’s motion to reconsider is based on the more recent decision of the Federal Circuit in Southern Nuclear Operating Co. v. United States, 637 F.3d 1297 (Fed. Cir.2011) (“Southern Nuclear”), which Defendant avers “unequivocally” holds that the Northern States I writ of mandamus “does not bar” assertion of the unavoidable delays defense in the Court of Federal Claims.

In supplemental briefing requested by the court, the Government has clarified that “the United States does not propose to use the unavoidable delays defense as a get-out-of-jail-free card” respecting liability, but rather as a means to “circumseribe[ ] the amount of expectation damages.” Def.’s Suppl. Br. at 4, 5. Specifically, the Government argues that costs incurred by Plaintiffs due to one particular source of delay — Nevada’s efforts to prevent licensing of a repository — are covered by the clause. “[Plaintiffs’ recovery should be reduced only by the amount that plaintiff would have expended had the United States accepted SNF on a schedule delayed only by the length of time attributable to Nevada’s dilatory conduct.” Id. at 6. More specifically, the Government asserts, “the unavoidable delays that DOE has encountered as a result of the [sic] Nevada’s conduct would have delayed the commencement of SNF acceptance by at least 31 months, or from January 30, 1998 through at least August 2000.” Id. at 7 (emphasis in original). Thus, it argues that Plaintiffs’ damages for SNF storage due to the Government’s delay in performance “did not commence until September 2000 — the earliest that performance could have begun given the Unavoidable Delays that DOE encountered.” Id.

For the reasons set forth below, Defendant’s motion for reconsideration is DENIED.

I. Background

The procedural history of this ease is discussed in greater detail in Entergy Nuclear FitzPatrick, 93 Fed.Cl. at 740-742. In 1983, Congress enacted the Nuclear Waste Policy Act (“NWPA”) in order to provide a safe, secure, and permanent disposal facility for spent nuclear fuel (“SNF”) and other radioactive by-products of the operation of nuclear power plants. See 42 U.S.C. §§ 10101-10270 (2006). Accordingly, the NWPA authorized the Department of Energy (“DOE”) to contract with utilities and other producers of nuclear waste to collect and store their SNF. See 42 U.S.C. § 10222(a)(1). However, the producers of SNF were to bear responsibility for the costs of disposal. See 42 U.S.C. § 10131(a)(4). Pursuant to this authorization, DOE drafted and issued a contract for use in negotiations with utilities, termed the Standard Contract. 10 C.F.R. § 961.11. In accordance with section 302(a)(5)(B) of the NWPA, the Standard Contract provided that DOE would accept and dispose of commercially-generated SNF beginning no later than January 31,1998, and that, in return, utilities would pay fees to cover the costs of removal. Id.1

In 1983, Power Authority of the State of New York (“NYPA”), the original owner of the James A. FitzPatrick Nuclear Power Station and the Indian Point 3 Nuclear Power Station, entered into a Standard Contract with DOE for the removal of SNF from both plants. The plants were sold in November 2000 to Entergy Nuclear FitzPatrick, LLC [466]*466and Entergy Nuclear Indian Point 3, LLC, respectively. After the purchase, DOE was notified by letter that the Standard Contract had been assigned to Entergy Nuclear Operations, Inc. as agent for the new plant owners, Entergy Nuclear FitzPatrick and Enter-gy Nuclear Indian Point 3.

In 1994, DOE noted in the Federal Register its projection that the “earliest possible date for acceptance of waste for disposal at a repository is 2010.” 59 Fed.Reg. 27,007, 27,-008 (May 25, 1994). In 1995, DOE issued a Final Interpretation of Nuclear Waste Acceptance Issues concluding that it did not have an unconditional obligation under the NWPA or the Standard Contract to accept SNF by January 31,1998, in the absence of a repository or interim storage facility by that date. 60 Fed.Reg. 21,793, 21,794-95 (May 3, 1995).

A number of utilities, states, and state agencies subsequently filed a petition in the United States Court of Appeals for the District of Columbia Circuit for review of DOE’s Final Interpretation, pursuant to 42 U.S.C. § 10139. The D.C. Circuit concluded that “section 302(a)(5)(B) creates an obligation in DOE, reciprocal to the utilities’ obligation to pay, to start disposing of the SNF no later than January 31, 1998.” Ind. Mich. Power Co., 88 F.3d at 1277. Notwithstanding that ruling, DOE subsequently advised the utilities that it would not begin accepting nuclear waste by the 1998 statutory deadline. The utilities returned to the D.C. Circuit seeking a writ of mandamus to compel DOE to comply with its statutory obligation to begin SNF acceptance on time. While that action was pending, DOE asserted that, under the Unavoidable Delays clause in Article IX of the Standard Contract,2 it was not obligated to provide a financial remedy for the delay in accepting the nuclear waste. See Northern States I, 128 F.3d at 757.

The D.C. Circuit denied the utilities’ request for a writ requiring DOE to begin accepting nuclear waste as of the statutory deadline. Id. at 756. The appellate court, however, rejected DOE’s argument that it was not obligated to accept nuclear waste because its failure to do so was “unavoidable” within the meaning of the Unavoidable Delays clause. Id. at 757. Accordingly, the D.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Entergy Nuclear Fitzpatrick, LLC v. United States, 101 Fed. Cl. 464, 2011 U.S. Claims LEXIS 2131, 2011 WL 5248339 (uscfc 2011).

101 Fed. Cl. 464 (Entergy Nuclear Fitzpatrick, LLC v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Entergy Nuclear Fitzpatrick, LLC. v. United States
711 F.3d 1382 (Federal Circuit, 2013)
Dairyland Power Cooperative v. United States
106 Fed. Cl. 102 (Federal Claims, 2012)