AAB Joint Venture v. United States

75 Fed. Cl. 123, 2007 U.S. Claims LEXIS 14, 2007 WL 259896
CourtUnited States Court of Federal Claims
DecidedJanuary 26, 2007
DocketNos. 04-1719C, 06-49 C, 05-114 C, 05-1172 C
StatusPublished
Cited by2 cases

This text of 75 Fed. Cl. 123 (AAB Joint Venture v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AAB Joint Venture v. United States, 75 Fed. Cl. 123, 2007 U.S. Claims LEXIS 14, 2007 WL 259896 (uscfc 2007).

Opinion

OPINION

DAMICH, Chief Judge.

This case is before the Court on Defendant’s Motion to Dismiss Plaintiffs Claim Concerning Subgrade Material, Asserted in Paragraph 37 of the Amended Complaint in No. 04-1719. In paragraph 37, Plaintiff seeks to recover $412,239 in additional costs it allegedly incurred, during performance of a construction contract, for replacement of subgrade material under structures as a result of differing site conditions. In its motion, Defendant requests that the Court dismiss paragraph 37 for lack of subject matter jurisdiction, pursuant to Rule 12(b)(1) of the Rules of the U.S. Court of Federal Claims (“RCFC”), because the claim was not previously certified and presented to the contracting officer for final decision. For the reasons set forth below, Defendant’s Motion to Dismiss is hereby GRANTED.

I. Background

On June 5, 2001, AAB Joint Venture (“AAB”) entered into Contract No. DACA9001-C0043 (the “Contract”) with the U.S. Army Engineer Corps-Europe (“USACE”) to design and construct a storage and logistics base complex, known as the Nachshonim Military Storage Base, near Elad, Israel for use by the Israeli Defense Force. Am. Compl. 114, 6.

Attached to the government’s Request for Proposals was a Geotechnical Report. Id. 117. The Contract specifications contained numerous references to the Geotechnical Report in its instructions on design and placement of piles and beams in construction of the foundations for buildings. Id. H11. The Geotechnical Report characterized the subsurface material in most of the building areas as “limy dolomite rock, mostly massive and hard.” Id. H 7. The Geotechnical Report also contained extensive directions and recommendations for construction, including recommendations on spread footings and pile design. Id. 118. Amendment No. 3 to the Request for Proposals referred bidders to the Geotechnical Report, stating that “sub-grade and excavation requirements are well defined in the Geotechnical Report.” Id. 1110. During the bidding process, the government directed bidders to nearby existing quarries for comparison of similar subsurface conditions. Id. H14.

AAB prepared its bid, and its calculations for earthwork and structure foundations, in reliance on the Geotechnical Report. Id. 1112.

After entering into the Contract, AAB performed exploratory borings, which revealed different subsurface conditions from those shown in the Geotechnical Report. Id. 1116. On January 22, 2002, AAB gave written notice to the government of differing site conditions, noting that the subsurface conditions encountered differed materially from those indicated in the contract (Type I), and from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract (Type II). Id. 1117.

On July 23, 2003, AAB submitted a certified claim to the contracting officer for an equitable adjustment of $6,885,115 (which it later revised to $6,510,301) for the unanticipated costs relating to excess material disposal on the site. Id. 1133. The costs .were attributed to the unrealized commercial value of the excess excavated material, the added costs of processing materials for reuse, and the added costs of removing the excess usa[125]*125ble material. Id. U 32. The contracting officer failed to issue a final decision within 60 days of receipt of the certified claim. Id. 1135.

During July-August 2003, AAB also submitted certified claims to the contracting officer for an equitable adjustment for the unanticipated costs relating to added pile lengths in Segments # 67, # 45, # 56, # 34, # 10, # 78, # 89, # 91, # 11, # 12, and # 23.1 Id. TUI 57, 76, 95, 114, 152, 171, 190, 209. The contracting officer failed to issue a final decision within 60 days of receipt of each of the certified claims. Id. 111159, 78, 97, 116, 133, 135,154,173,192, 211.

In Count I of its Amended Complaint, AAB requests $11,588,813 total compensation as a result of differing site conditions. Id. 1142. The total includes the previously requested $6,510,301 in the certified claim for excess material disposal, as well as:(l) $412,239 to replace unsuitable subgrade material under structures required as a result of the differing site conditions; (2) $4,037,203 to compensate subcontractor Rolider for its added costs and delay costs due to the differing site conditions; and (3) $629,070 to compensate subcontractor Barashi for delays in its operations due to the required removal of unsuitable subsurface material. Id. 1137-39.

The claim on behalf of subcontractor Barashi was dismissed by this Court in an opinion issued November 1, 2005. AAB Joint Venture v. United States, 74 Fed.Cl. 367 (2005).

The claim for $412,239 to replace unsuitable subgrade material under structures is the subject of the pending motion. Specifically, in paragraph 37 of Count I, Plaintiff alleges:

In addition, due to the conditions described in Paragraph 23,2 the subgrade material under many of the structures could not be used for foundation support and had to be replaced with suitable subgrade material. In areas under some roads and slopes, USACE issued change orders to compensate the Contractor for the cost of replacing the unsuitable subgrade material, the content of which contained significantly more clay than represented in the Geo-technical Report. USACE agreed to compensate the Contractor for subgrade replacement under some roads and slopes but refused to compensate the Contractor for replacement of unsuitable subgrade material under structures. Contractor incurred additional costs of $412,239 to replace unsuitable material under structures, which material was not as represented in the Geotechnical Report. The replacement of this unsuitable material under the structures was a differing site condition/change to the Contract, and is based on the same underlying operative [sic] set forth herein; that is, the actual subsurface material differed materially from the conditions represented in the Geotechnical Report.

Am. Compl. 1137.

In Counts II-X, AAB requests compensation in the amount of $114,963; $99,679; $117,205; $118,836; $292,089; $117,828; $91,123; $417,471; and $89,360, respectively, for the additional pile lengths. Id. ¶¶ 61, 80, 99, 118, 156, 175, 194, 213.

In the motion pending before the Court, Defendant asks the Court to dismiss paragraph 37 of Count I of the Amended Complaint for lack of subject matter jurisdiction pursuant to RCFC 12(b)(1).

II. Standard of Review

Subject matter jurisdiction may be challenged at any time by a party. Fanning, Phillips & Molnar v. West, 160 F.3d 717, 720 (Fed.Cir.1998); Booth v. United States, 990 [126]*126F.2d 617, 620 (Fed.Cir.1993); United States v. Newport News Shipbuilding & Dry Dock Co., 933 F.2d 996, 998 n. 1 (Fed.Cir.1991). When deciding Defendant’s motion to dismiss for lack of subject matter jurisdiction, the Court must accept as true all of Plaintiffs well-pleaded facts alleged in the complaint, and draw all reasonable inferences in the Plaintiffs favor. Godwin v. United States,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northrop Grumman Computing Systems, Inc. v. United States
99 Fed. Cl. 651 (Federal Claims, 2011)
AAB Joint Venture v. United States
75 Fed. Cl. 448 (Federal Claims, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
75 Fed. Cl. 123, 2007 U.S. Claims LEXIS 14, 2007 WL 259896, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aab-joint-venture-v-united-states-uscfc-2007.