Eggers & Higgins and Edwin A. Keeble Associates, Inc. (A Joint Venture) v. The United States

403 F.2d 225, 185 Ct. Cl. 765, 1968 U.S. Ct. Cl. LEXIS 166
CourtUnited States Court of Claims
DecidedNovember 15, 1968
Docket290-66
StatusPublished
Cited by23 cases

This text of 403 F.2d 225 (Eggers & Higgins and Edwin A. Keeble Associates, Inc. (A Joint Venture) v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eggers & Higgins and Edwin A. Keeble Associates, Inc. (A Joint Venture) v. The United States, 403 F.2d 225, 185 Ct. Cl. 765, 1968 U.S. Ct. Cl. LEXIS 166 (cc 1968).

Opinion

OPINION

PER CURIAM:

This case was referred to trial Commissioner Roald A. Hogenson, with directions to make findings of fact and recommendation for conclusions of law under the order of reference and Rule 57(a). The commissioner has done so in an opinion and report filed on February 29, 1968, wherein such facts as are necessary to the opinion are set forth. Exceptions to the commissioner’s opinion, findings and recommended conclusion of law were filed by plaintiff and the case has been submitted to the court on oral argument of counsel and the briefs of the parties. The commissioner’s views and recommendation are fully consistent with the principles announced in Crown Coat Front Co. v. United, States, 386 U.S. 503, 518-519, 87 S.Ct. 1177, 18 L.Ed.2d 256 (1967); Nager Electric Co. v. United States, 368 F.2d 847, 864, 177 Ct.Cl. 234, 259-260 (1966), and Schlesinger v. United States, 383 F.2d 1004, 1008, 181 Ct.Cl. 21, 28-29 (1967). Since the court agrees with the commissioner’s opinion, findings and recommended conclusion of law, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. Therefore, it is concluded that plaintiff’s assignment of errors of the Veterans Administration Contract Appeals Board should not be sustained; that the Board’s findings of fact are supported by substantial evidence; that the Board’s decision was not fradulent, capricious, arbitrary, or so grossly erroneous as necessarily to imply bad faith, but correct as a matter of law; that the ruling of the Board should be sustained that plaintiff failed timely to present to defendant’s contracting officer its claim under the Changes in Service article of its contract with defendant; and plaintiff’s petition is dismissed.

OPINION OF COMMISSIONER

HOGENSON, Commissioner:

Plaintiff seeks a ruling by this court that it timely presented its claim under the Changes in Service article of its contract to defendant’s contracting officer and that it is entitled to an administrative hearing on the merits pursuant to the Disputes article. Obviously, if plaintiff did not timely present its claim, the petition will have to be dismissed. If the court sustains plaintiff’s position, proceedings will have to be suspended to permit plaintiff an opportunity to present its claim on the merits within the administrative agency involved, as provided by the Disputes article. United States v. Anthony Grace & Sons, Inc., 384 U.S. 424, 86 S.Ct. 1539, 16 L.Ed.2d 662 (1966). For the reasons hereinafter stated, it is my opinion that plaintiff’s petition should be dismissed.

Plaintiff is a joint venture comprised of two architectural firms, Eggers, and Higgins of New York, N.Y.„ and Edwin A. Keeble Associates, Inc., of Nashville, Tennessee. On April 22, 1959, plaintiff entered into a contract (V1006C-386) with the Veterans Administration for the lump sum fee of $445,000 to provide architect-engineer services for a new VA 500-bed General Medical and Surgical Hospital and Regional Medical clinics to be constructed at Nashville, Tennessee, *227 at an estimated cost of $10,400,000. On the same day, defendant issued notice to proceed to plaintiff. In addition to subsequent drafting and related services to be performed after bidding and award of a construction contract, plaintiff undertook to provide certain special studies and to design the hospital and provide the drawings and specifications within 12 months of notice to proceed, and plaintiff timely complied on April 22, 1960. The construction contract was awarded on June 27, 1960, and plaintiff’s work under its contract ended when construction was completed in January 1963.

On July 16, 1959, defendant’s contracting officer telephoned plaintiff at Nashville, Tennessee, and advised that the Administrator of VA had received a disturbing letter from the Vice Chancellor of Vanderbilt University, which letter was read over the telephone. The letter concerned relocation of the proposed hospital, and a discussion was had concerning the proposed new site in relation to the planned site owned by defendant. The possibility of an exchange of land was discussed. The contracting officer stated that a meeting would have to be held, and suggested that before such meeting, plaintiff confer with the interested parties, and the names of various persons were provided to plaintiff. Plaintiff was instructed to ascertain the areas of agreement and disagreement, and that a meeting would be set sometime after August 3, and that plaintiff’s representatives should come well prepared to avoid the necessity of a second meeting. The contracting officer commented that plaintiff knew that the project was on a tight schedule, and there couldn’t be too much delay.

On September 2, 1959, defendant’s contracting officer telephoned plaintiff and advised that the VA had made the decision to build on the original site, and that letters to that effect had been delivered to the Vice Chancellor or Vanderbilt University and to the Mayor of Nashville. Plaintiff’s representative responded that plaintiff “will go ahead now,” and requested comments from defendant on the five sections of Special Studies forwarded the previous day. By letter dated September 4, 1959, plaintiff acknowledged the telephone advice that the original building site would be” used.

By letter dated September 21, 1959, to defendant’s contracting officer, plaintiff requested an extension of contract performance time as follows:

Our contract for architectural and engineering services on the above named project sets definite dates for successive stages of completion of the working documents.
As you know, our progress toward these objectives was held up while the Administration was considering a new building site, in the investigation of which we took an active part. Because of the uncertain effect of the possible site change on the building plans, our activity on the working drawings was necessarily at a standstill during that period.
This delay began with the July 16th telephone instructions from Mr. Mork to undertake an investigation of the new site and ends on September 1st when we were notified that the original site would be retained.
For this reason, and because of the time required for further study of the Administration’s request for revision of the boiler room and other mechanical areas, we respectfully request a deferment of two months in the various completion dates given in our contract. We assure you, however, that we shall do everything possible to beat the requested new dates.

By letter, dated October 5, 1959, to plaintiff, defendent’s contracting officer replied as follows :

Your letter of September 21, 1959, requesting a two months extension in time of the various completion dates given in your contract, has been reviewed.
Confirming the telephone conversation between Mr. Holderness, Mr. Norton and Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

East Coast Repair & Fabrication, LLC v. United States
199 F. Supp. 3d 1006 (E.D. Virginia, 2016)
Meridian Engineering Company v. United States
122 Fed. Cl. 381 (Federal Claims, 2015)
Koga Engineering & Construction, Inc. v. State
222 P.3d 979 (Hawaii Supreme Court, 2010)
AAB Joint Venture v. United States
75 Fed. Cl. 414 (Federal Claims, 2007)
Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
SIPCO Services & Marine Inc. v. United States
42 Cont. Cas. Fed. 77,277 (Federal Claims, 1998)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Barrow Utilities & Electric Cooperative, Inc. v. United States
36 Cont. Cas. Fed. 75,840 (Court of Claims, 1990)
Big Chief Drilling Co. v. United States
15 Cl. Ct. 295 (Court of Claims, 1988)
H.H.O. Co. v. United States
34 Cont. Cas. Fed. 75,256 (Court of Claims, 1987)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Mingus Constructors, Inc. v. United States
33 Cont. Cas. Fed. 74,407 (Court of Claims, 1986)
New Pueblo Constructors, Inc. v. State
696 P.2d 185 (Arizona Supreme Court, 1985)
Gulf & Western Industries, Inc. v. United States
32 Cont. Cas. Fed. 73,100 (Court of Claims, 1984)
Iconco v. United States
32 Cont. Cas. Fed. 72,720 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
403 F.2d 225, 185 Ct. Cl. 765, 1968 U.S. Ct. Cl. LEXIS 166, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eggers-higgins-and-edwin-a-keeble-associates-inc-a-joint-venture-v-cc-1968.