Koga Engineering & Construction, Inc. v. State

222 P.3d 979, 122 Haw. 60, 2010 Haw. LEXIS 16
CourtHawaii Supreme Court
DecidedJanuary 14, 2010
Docket28278
StatusPublished
Cited by8 cases

This text of 222 P.3d 979 (Koga Engineering & Construction, Inc. v. State) is published on Counsel Stack Legal Research, covering Hawaii Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Koga Engineering & Construction, Inc. v. State, 222 P.3d 979, 122 Haw. 60, 2010 Haw. LEXIS 16 (haw 2010).

Opinion

Opinion of the Court by

ACOBA J.

On July 8, 2009, both Petitioner & Respondent/Defendant-Appellant State of Hawai'i (the State) and Respondent & Petitioner/Plaintiff-Appellee Koga Engineering & Construction, Inc. (Koga) filed separate Applications for Writ of Certiorari, 1 requesting that this court review the judgment of the Intermediate Court of Appeals (the ICA) filed pursuant to its March 13, 2009 Summary Disposition Order (SDO) 2 affirming in part and reversing in part the October 24, 2006 final judgment of the circuit court of the first circuit (the court). 3 See Koga Eng’g & Const., Inc. v. State, No. 28278, 2009 WL 641461, *1 (Haw.App. Mar. 13, 2009). On July 23, 2009, Koga filed a Response to the State’s Application (Koga’s Response), and on the same day, the State filed a Response to Koga’s Application (State’s Response). On August 27, 2009, Koga filed a supplemental memorandum as requested by this court’s order filed on August 12, 2009. This court held oral argument on October 13, 2009.

Briefly, this case involved a construction contract dispute. The court denied the State’s motion for summary judgment on the ground that Koga’s claim for damages was untimely, but granted Koga’s motion for partial summary judgment to the effect that its late claim for damages was not barred under the contract. The case proceeded to a bench trial on the issue of damages. The court inter alia concluded Koga was entitled to damages and payment of that part of the contract price retained because of incomplete work. The court issued final judgment in favor of Koga. On appeal, the ICA affirmed the court’s final judgment, except as to the portion regarding retainage. Part I of this opinion relates the relevant facts in this case. Part II addresses the State’s Application, which asserts that the ICA gravely erred in upholding the court’s denial of its motion for summary judgment. Part III addresses Koga’s Application, which maintains that the ICA erred in reversing the court’s final judgment on the retainage issue. As to Part II, we hold that the court was wrong in granting Koga’s motion for partial summary judgment but right in denying the State’s motion for summary judgment, inasmuch as there were genuine issues of material fact as to the question of prejudice. The case with respect to damages is remanded for trial. As to Part III, we hold that the court lacked jurisdiction to consider the retainage fee, inasmuch as the retainage claim must be processed through HRS chapter 103D as noted herein.

*63 PART I

I.

A.

1.

On July 18, 1997, Koga entered into a contract 4 with the State to widen a road in Hilo, Hawaii (the Project). 5 In relevant part, the contract provided as follows with respect to damages: 6

105.18 Claims for Adjustment and Disputes. The Contractor may give notice in writing to the Engineer for claims that extra compensation, damages, or an extension of time for completion is due the Contractor for one or more of the following reasons:
(1) Requirements not clearly covered in the contract, or not ordered by the Engineer as an extra work;
(2) Failure between the State and the Contractor to an adjustment in price for a contract change order issued by the State;
(3) An action or omission on the pari of the Engineer requiring performance changes within the scope of the contract. The Contractor shall continue with performance of the contract in compliance with the directions or orders of the Engineer, but by so doing, the Contractor shall not be deemed to have prejudiced any claim for additional compensation, damages, or an extension of time for completion, ’provided:
(1) The notice in uniting be given:
(a) Before the commencement of the work involved, if at that time the Contractor knotus of such requirements or the occurrence of such act or omission; or
(b) Within SO calendar days after the Contractor knorvs of such requirements or the occurrence of such action or omission if the Contractor did not have such knowledge before the commencement of the work; or
(e) Within 30 calendar days after receipt of the written contract change order that was not agreed upon by both parties; or (d) Within such furiher time as may be allowed by the Engineer in uniting.
(2) The notice shall clearly state the Contractor’s intention to make claim and the reasons why the Contractor believes that additional compensation changes or an extension of time may be remedies to which the Contractor is entitled; and afford the Engineer every facility for the keeping of records of the actual cost of work. Failure on the pari of the Contractor to give such notification or to afford the Engineer proper facilities for keeping strict account of actual cost shall constitute waiver of the claim for such extra compensation. The filing of such notice by the Contractor and the keeping of the costs by the Engineer shall not in any way be construed to prove the validity of the claim.
The Engineer will review the notice and render a decision. The Engineer’s decision shall be final and conclusive unless, within 30 calendar days from the date of the decision, the Contractor mails or otherwise furnishes a mitten appeal to the Director. The decision of the Director shall be final. Later notification of such claims shall not bar the Contractor’s claim unless the State is prejudiced by the delay in notification. No claim by the Contractor for an adjustment hereunder shall be allowed if notice is not given before final payment under this contract. Any adjust *64 ment in the contract price pursuant this clause shall be determined according to Subsection 104.09—Price Adjustment.

(Emphases added.)

Based on plans provided by the State, Koga prepared an “Original Project Schedule” which called for completion of the work in three phases, known as Phases I, II, and III. As part of the work, Koga was required to install a “drain line.” The Original Project Schedule called for “the installation of a waterline” in Phase II of the Project, but not in Phase I. On September 8, 1997, the State issued a letter to Koga stating that it was “hereby given notice to proceed as of September 15, 1997, and to complete the project on or before December 2, 1998 [ (First Notice to Proceed) ].”

According to the State, “[t]he controversy arose as a result of an error in the State’s construction plans.” On September 8, 1997, “prior to the commencement of its work on the Project,” Koga discovered a “discrepancy” in the plans between the “proposed installation of the new drain line” and an existing waterline.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ohana Control Systems, Inc. v. Hayashi
Hawaii Intermediate Court of Appeals, 2025
In re: AA
529 P.3d 710 (Hawaii Intermediate Court of Appeals, 2023)
Arbles v. Merit Appeals Board.
515 P.3d 217 (Hawaii Intermediate Court of Appeals, 2022)
Malulani Group, Ltd. v. Kaupo Ranch, Ltd.
329 P.3d 330 (Hawaii Intermediate Court of Appeals, 2014)
Evergreen Engineering, Inc. v. Green Energy Team LLC
884 F. Supp. 2d 1049 (D. Hawaii, 2012)
Kutkowski v. Princeville Prince Golf Course, LLC
289 P.3d 980 (Hawaii Intermediate Court of Appeals, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
222 P.3d 979, 122 Haw. 60, 2010 Haw. LEXIS 16, Counsel Stack Legal Research, https://law.counselstack.com/opinion/koga-engineering-construction-inc-v-state-haw-2010.