Kaiser Aluminum & Chemical Corporation v. The United States

388 F.2d 317, 181 Ct. Cl. 902, 66 L.R.R.M. (BNA) 2495, 1967 U.S. Ct. Cl. LEXIS 156
CourtUnited States Court of Claims
DecidedDecember 15, 1967
Docket49-63
StatusPublished
Cited by24 cases

This text of 388 F.2d 317 (Kaiser Aluminum & Chemical Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kaiser Aluminum & Chemical Corporation v. The United States, 388 F.2d 317, 181 Ct. Cl. 902, 66 L.R.R.M. (BNA) 2495, 1967 U.S. Ct. Cl. LEXIS 156 (cc 1967).

Opinion

OPINION

PER CURIAM:

This case was referred to Trial Commissioner Roald A. Hogenson with directions to make findings of fact and recommendation for conclusions of law. The commissioner has done so in an opinion and report filed on November 21, 1966. Plaintiff filed exceptions to the commissioner’s findings and the defendant filed exceptions to the commissioner’s findings and recommended conclusion of law. The case has been submitted to the court on oral argument of counsel and the briefs of the parties.

The defendant now stresses one argument with which the commissioner did not treat, i. e., that plaintiff is guilty of laches in waiting until 1963 to file this suit and should therefore be barred from all recovery. (It is admitted that the suit is not foreclosed by limitations.) The main answer is that this court has not accepted the defense of laches as applying to contract actions against the Government; that defense has been confined to personnel suits for unlawful removal, suspension, or demotion from a federal position, and the court has given special reasons for its application to that area. See e. g., Henry v. United States, 153 F.Supp. 285, 139 Ct.Cl. 362, 366-370 (1957); Bovard v. United States, 160 Ct.Cl. 619, 620-622 (1963), cert, denied 374 U.S. 830, 83 S.Ct. 1872, 10 L.Ed.2d 1053; Alpert v. United States, 161 Ct.Cl. 810, 820-821 (1963). So far as the court is aware, no case in this court has applied the doctrine as a defense to a contract action. B-W Construction Co. v. United States, 100 Ct.Cl. 227, 236 (1943), on which de *320 fendant relies, merely said that the long unexplained delay in bringing suit in that instance cast upon that plaintiff “a somewhat heavier burden in proving its case than usual.” That was an evidentiary ruling, not an invocation of laches as such. We see no reason, now for the first time, to carry over laches as such to the contract field, and, as an evidentiary matter, we are not persuaded that the defendant’s ability to make its case was materially harmed by the lapse of time before this action was begun.

Since the court agrees with the commissioner’s findings, opinion, and recommended conclusion of law, it hereby adopts the same as supplemented by the preceding paragraph, as the basis for its judgment in this case. Plaintiff is, therefore, entitled to recover and judgment is entered for plaintiff in the sum of $7,198,655.55, with defendant’s counterclaims and plaintiff’s reply thereto dismissed.

OPINION OF COMMISSIONER *

HOGENSON, Commissioner:

This is a suit for breach of four contracts, in which it is claimed by plaintiff, Kaiser Aluminum & Chemical Corporation (hereinafter Kaiser), that defendant unilaterally terminated its market guaranty commitments prior to plaintiff’s completed contract performance. Two theories of recovery are presented. One is based upon contract terms, the other upon a so-called “most favored nation” right. In question are four contracts, essentially identical, each providing in substance for the private financing, construction and operation, by Kaiser, of aluminum reduction facilities (hereinafter the “additional facilities”), and for the production, at said facilities, of specified quantities of primary aluminum pig. 1 In exchange for these commitments, defendant undertook to guarantee the disposition, by purchase, of that portion of Kaiser’s contract production in the additional facilities, which Kaiser would be unable to sell to others or utilize for its own fabricating purposes.

The parties have by formal stipulation withdrawn defendant’s counterclaim and contingent counterclaim and plaintiff’s claim for affirmative relief contained in its reply to such counterclams, agreeing that such withdrawal constitutes a full release of the matters set forth in such counterclaims and reply thereto, which pertain to transportation costs of aluminum purchased under the supply contracts, and defendant’s counterclaims and plaintiff’s reply thereto should be dismissed.

The contracts involved were executed in behalf of defendant by the General Services Administration (hereinafter GSA), acting under the authority of the Defense Production Act of 1950, 64 Stat. 798 (1950), 50 U.S.C. App. §§ 2061-2166 (1952), as implemented by Executive Order. In addition to Kaiser’s contracts, defendant also entered into like agreements with the Reynolds Metals Company (hereinafter Reynolds) and the Aluminum Company of America (hereinafter Alcoa). These agreements, collectively designated as the aluminum expansion program, resulted from administrative implementation of the statutory purpose to meet the nation’s heightened need for an expanded production of strategic materials during the Korean War emergency.

*321 The contracts in question are the following :

(1) GS-OOP(D) — 12006 dated as of December 19, 1950, calling for the production of 1 billion pounds of primary aluminum pig at reduction facilities to be constructed by Kaiser at Chalmette, Louisiana (hereinafter Chalmette I contract) .

(2) GS-OOP(D) — 12213 dated as of October 31, 1951, calling for the production of 200 million pounds of primary aluminum pig at reduction facilities to be constructed by Kaiser at Mead, Washington (hereinafter Mead contract).

(3) GS-OOP(D) — 12143 dated as of November 6, 1951, and calling for the production of 1 billion pounds of primary aluminum pig at reduction facilities to be constructed by Kaiser at Chalmette, Louisiana (hereinafter Chalmette II contract) .

(4) GS-OOP(D) — 12192 dated as of February 28, 1952, and calling for the production of 82 million pounds of primary aluminum pig at additional reduction facilities to be constructed by Kaiser at Tacoma, Washington (hereinafter Tacoma contract).

Under its four supply contracts, Kaiser was obligated to produce 2 billion 282 million pounds of primary aluminum pig, and the ultimate question at issue here is whether this amount of production was achieved, as defendant claims, or whether, as Kaiser contends, completed performance demands the production of an additional 84,407,143 pounds. The controversy arises because the parties disagree as to the standard to be used in measuring production prior to April 1, 1957. 2 3

Kaiser’s basic premise is that Article I of the contracts clearly establishes both the quality and the quantity of the aluminum to be produced; hence, the computation of production prior to April 1, 1957, must be determined in accordance with Article I, which reads in pertinent part as follows : 3

Subject to the terms and conditions hereof, Contractor agrees to produce and to sell Five Hundred Thousand (500,000) short tons of 2,000 pounds each, of primary aluminum pig, said primary aluminum to be of minimum grade of ninety-nine percent (99%) aluminum, which primary aluminum is herein called the “additional production.” The Contractor will produce such aluminum from facilities which the contractor agrees hereafter to construct, herein called the “additional facilities.” * * *

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coast Federal Bank, FSB v. United States
48 Fed. Cl. 402 (Federal Claims, 2000)
Cray Research, Inc. v. United States
44 Fed. Cl. 327 (Federal Claims, 1999)
Clements v. Gabriel
472 N.W.2d 480 (South Dakota Supreme Court, 1991)
Travelers Indemnity Co. v. United States
35 Cont. Cas. Fed. 75,607 (Court of Claims, 1988)
Pathman Construction Co. v. United States
33 Cont. Cas. Fed. 74,394 (Court of Claims, 1986)
S.E.R., Jobs for Progress, Inc. v. United States
759 F.2d 1 (Federal Circuit, 1985)
Peterson-Sharpe Engineering Corp. v. United States
32 Cont. Cas. Fed. 72,873 (Court of Claims, 1984)
Aluminum Co. v. United States
31 Cont. Cas. Fed. 71,310 (Court of Claims, 1983)
Standard Oil Co. of California v. United States
685 F.2d 1322 (Court of Claims, 1982)
Sumner v. United States
678 F.2d 202 (Court of Claims, 1982)
Johnston v. First National Bank & Trust Co. of Joplin
624 S.W.2d 500 (Missouri Court of Appeals, 1981)
Carruth v. United States
627 F.2d 1068 (Court of Claims, 1980)
H & M Moving, Inc. v. United States
499 F.2d 660 (Court of Claims, 1974)
Spatz v. Nascone
364 F. Supp. 967 (W.D. Pennsylvania, 1973)
Consumers Ice Co. v. United States
475 F.2d 1161 (Court of Claims, 1973)
Reynolds Metals Company v. The United States
438 F.2d 983 (Court of Claims, 1971)
National By-Products, Inc. v. The United States
405 F.2d 1256 (Court of Claims, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
388 F.2d 317, 181 Ct. Cl. 902, 66 L.R.R.M. (BNA) 2495, 1967 U.S. Ct. Cl. LEXIS 156, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kaiser-aluminum-chemical-corporation-v-the-united-states-cc-1967.