John A. Johnson Contracting Corp. v. United States

132 F. Supp. 698, 132 Ct. Cl. 645, 1955 U.S. Ct. Cl. LEXIS 165
CourtUnited States Court of Claims
DecidedJuly 12, 1955
DocketNo. 47607
StatusPublished
Cited by45 cases

This text of 132 F. Supp. 698 (John A. Johnson Contracting Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John A. Johnson Contracting Corp. v. United States, 132 F. Supp. 698, 132 Ct. Cl. 645, 1955 U.S. Ct. Cl. LEXIS 165 (cc 1955).

Opinion

Madden, Judge,

delivered the opinion of the court:

The plaintiff, on December 15,1942, made a contract with the Government, which acted through the War Department’s Corps of Engineers, to construct the U. S. Army General Hospital at Utica, New York. There were to be 122 buildings, with connecting enclosed walkways, and the contractor was to install all utilities, place the surfacing on the roads, and do the finished grading and seeding of the grounds. The Government was to furnish various items of material which would be incorporated in the structures. Other items, including lumber and nails, were to be obtained by the plaintiff from sources and through allocations to be designated by the Government.

The work was divided into four groups, one group to be completed by each of the following dates: March 1, March 15, April 15, and May 15, 1948. Especially in view of the extreme cold weather which prevails in the area, the completion of the work within the specified times was hardly to be expected, though it was not impossible.

The whole project had been thought up in a hurry, in the fall of 1942. The site selected was a sloping hillside, with a drop of some 50 feet in elevation in the 2,000 feet of its north to south dimension. The plan called for terracing the hillside and for placing roads and buildings on a [649]*649succession of levels. In order to get the work started, a contract for the grading for the roads and terraces, the construction of the roads, except for their final smooth surfacing, and the construction of the drains, was let to the Winkleman Company on November 4, 1942, which was before the plans for the buildings had been completed. Winkleman’s work was to be completed by December 5, subject to the usual provisions about excusable delays. Winkleman was delayed by wet weather. Priority was given to the construction of roads, which involved the making of cuts and fills. The fills were placed on wet ground, the earth placed in the fills was wet, and there were drenching rains while the work was being done. The ground froze at night and some frozen ground was placed in the fills. A 12-inch course of bank gravel was placed by Winkleman on the roads, but, as we have said, the final smooth surface of the roads was to be placed by the building contractor after the completion of the buildings.

When bids for the construction of the hospital were invited, the plaintiff’s representatives visited the site, on December 10 and 11,1942, and observed but paid no particular attention to the road and grading work which was in progress.

Both parties assumed that the plaintiff would use the roads, as constructed by Winkleman, as haul roads in connection with its building operations.

On December 21, 1942, the plaintiff was given notice to proceed. By that time Winkleman had completed the grading of 41 building sites, and was still working on the roads and the grading, and continued to work through January and until February 27, 1943, when that work was suspended because of the cold weather. By the time of the suspension, all the main access roads and most of the drainage ditches were built.

During January and February the ground froze so hard that trucks could travel anywhere on it. Holes for foundation piers for the buildings had to be dug, but the digging was difficult and expensive because of the frozen ground and the plaintiff did not place as many piers as it might have. The same was true as to the digging of trenches for the plac[650]*650ing of pipes for tbe utilities. The plaintiff anticipated, probably with reason, that much of the work would not in any event be completed before spring, and it therefore sought to avoid the expense of digging in the frozen ground. There had also been delays in the furnishing of materials to be furnished by the Government, or to be obtained upon Government allocation.

By March 10, the plaintiff was getting ready for the big push toward getting the job forward. Heavily loaded trucks were moving lumber on to the site in great volume. Surveys had been made for the utility trenches and equipment to dig them was available. On March 11, the spring thaw began, some weeks earlier than usual. There was rain, off and on for several days. The heavy hauling continued, and within a week or ten days after March 11, the whole road system disintegrated. Trucks sank in the mire to the cab. Tractors, sent to pull out the trucks, had to be pulled out by caterpillars. What happened to the roads was that, as the frost came out of the ground, the moisture, because of the depth to which the ground was frozen, could not drain downward, hence it was carried toward the surface by capillary action. It thus soaked the soil under the 12-inch gravel course of the roads, and the loads crushed the gravel into the mud. The fact that the earth bases under the gravel had been wet and frozen when the gravel was placed, the fact that the drainage ditches at the sides of the road were not adequate, and had in some instances been obstructed by the plaintiff, and the unusual capillarity of the soil, all made their contribution to the collapse of the road system. The only thing that would have saved the roads would have been to keep loaded vehicles off them for several weeks. Neither party even seriously thought of doing that. Both were intent on getting the work forward. The contracting officer took the position that it was the plaintiff’s responsibility to keep the roads passable, or to get its work done somehow. The plaintiff’s position was that the failure of the roads was a breach of contract by the Government, for which the plaintiff would make a claim.

At very great extra expense, by unloading, hand handling, hauling in brickbats, slag, and cinders, miring down and [651]*651digging out, placing equipment on pontoons, the work proceeded, greatly delayed, of course. After the frost was out of the ground the month of April was wet and cloudy, and May and June were rainy. The site did not dry out enough for grading operations to be resumed by Winkleman until July.

On April 19, 1948, the plaintiff notified the Government that a formal claim would be filed. It filed such a claim on May 24. In the statement the plaintiff said, among other things, that it had “encountered unforeseen conditions beyond its control and not due to its fault or negligence.” It requested the contracting officer to make findings of fact and presented 122 proposed findings of fact in separate, numbered paragraphs.

On July 5, 1943, the plaintiff filed a supplementary statement. This and the earlier statement, considered together, gave adequate notice to the contracting officer that the plaintiff was asking for compensation for the expense incurred because the plaintiff had “encountered unknown conditions of an unusual nature differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the plans and specifications.” Article 4 of the contract provided for additional compensation in such a situation.

On October 19, 1943, the contracting officer denied the plaintiff’s claim. He did not make findings of fact with regard to the plaintiff’s claim that it had encountered unknown conditions, and apparently gave no consideration to that claim. On November 16, 1943, the plaintiff appealed the decision of the contracting officer to the Secretary of War, stating that the appeal was made pursuant to Article 15 of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rda Construction Corp. v. United States
132 Fed. Cl. 732 (Federal Claims, 2017)
Manuel Bros. v. United States
55 Fed. Cl. 8 (Federal Claims, 2002)
McDonnell Douglas Corp. v. United States
40 Cont. Cas. Fed. 76,912 (Federal Claims, 1996)
Modern Systems Technology Corp. v. United States
37 Cont. Cas. Fed. 76,249 (Court of Claims, 1992)
Youngstown Steel Equipment Sales, Inc. v. United States
36 Cont. Cas. Fed. 75,870 (Court of Claims, 1990)
Gregory Timber Resources, Inc. v. The United States
855 F.2d 841 (Federal Circuit, 1988)
Baltimore Contractors, Inc. v. United States
34 Cont. Cas. Fed. 75,267 (Court of Claims, 1987)
Martin J. Simko Construction, Inc. v. United States
33 Cont. Cas. Fed. 74,888 (Court of Claims, 1986)
Timberland Paving & Construction Co. v. United States
33 Cont. Cas. Fed. 73,781 (Court of Claims, 1985)
Fairfield Scientific Corp. v. United States
611 F.2d 854 (Court of Claims, 1979)
United States v. Amtraco Commodity Corp.
389 F. Supp. 1084 (S.D. New York, 1974)
Hunkin Conkey Construction Co. v. United States
461 F.2d 1270 (Court of Claims, 1972)
Phillips Construction Co., Inc. v. The United States
440 F.2d 429 (Court of Claims, 1971)
L. B. Samford, Inc. v. The United States
410 F.2d 782 (Court of Claims, 1969)
Ray D. Bolander Co. v. United States
186 Ct. Cl. 398 (Court of Claims, 1968)
Lula A. McGlasson v. The United States
397 F.2d 303 (Court of Claims, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
132 F. Supp. 698, 132 Ct. Cl. 645, 1955 U.S. Ct. Cl. LEXIS 165, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-a-johnson-contracting-corp-v-united-states-cc-1955.