Phillips Construction Co., Inc. v. The United States

440 F.2d 429, 194 Ct. Cl. 695, 1971 U.S. Ct. Cl. LEXIS 158
CourtUnited States Court of Claims
DecidedApril 16, 1971
Docket357-62
StatusPublished

This text of 440 F.2d 429 (Phillips Construction Co., Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phillips Construction Co., Inc. v. The United States, 440 F.2d 429, 194 Ct. Cl. 695, 1971 U.S. Ct. Cl. LEXIS 158 (cc 1971).

Opinion

ON DEFENDANT’S MOTION AND PLAINTIFF’S CROSS - MOTION FOR SUMMARY JUDGMENT, AS AMENDED

PER CURIAM:

This case was referred to Trial Commissioner Lloyd Fletcher with directions to prepare and file his opinion on the issues of defendant’s motion and plaintiff’s cross-motion for summary judgment, as amended, under the order of reference and Rule 166(c). The commissioner has done so in an opinion and report filed on January 15, 1971. Neither party has filed a request for review by the court of the commissioner’s opinion and report and the time for so filing under the rules of the court has expired. On March 4, 1971, defendant filed a motion under Rule 54(b) (3) (iii) that the court adopt the commissioner’s report and recommendation as the basis for its judgment in this case.

Since the court agrees with the opinion and recommended conclusion of the trial commissioner, it hereby adopts the same, as hereinafter set forth, as the basis for its judgment in this case. Therefore, plaintiff’s cross-motion for summary judgment is granted only to the extent of the $25,877.25 not contested by defendant as to which sum judgment is entered for plaintiff and plaintiff’s motion is otherwise denied. Defendant’s motion for summary judgment is granted, except as to the $25,877.25, and plaintiff's petition is otherwise dismissed.

OPINION OF COMMISSIONER

FLETCHER, Commissioner:

In its final decision of June 24, 1970, the Armed Services Board of Contract Appeals, speaking through Member Harris J. Andrews, Jr., referred, with melancholic accuracy, to the “long and tortuous history of this claim.” It constitutes a classic example of the sometimes “ping-pong” nature of a Wunderlich Act review case. The contract in dispute has been the subject of five opinions issued by the ASBCA, and two opinions by this court (374 F.2d 538, 179 Ct.Cl. 54 (1967); 394 F.2d 834, 184 Ct.Cl. 249 (1968)), plus an order promulgated by the court, following briefing and oral argument, on June 13, 1969, 188 Ct.Cl. 1157. Hence, one cannot help but join Member Andrews in his expressed hope that, at long last, the case may be brought “to a final conclusion.”

The detailed facts surrounding this long dispute have been set forth in this court’s two prior decisions cited above, and thus need not be repeated here. A brief summary thereof, coupled with a description of relatively recent developments at the ASBCA level, should be sufficient for an understanding of the narrow remaining issue.

Pursuant to a fixed-price contract entered into with defendant, plaintiff constructed some 800 housing units for the United States Air Force at Myrtle Beach, South Carolina. Financing of the project was accomplished under the Capehart Housing Act, all as described *431 by the court in its first Phillips decision, swpra. Some of the heaviest rainfall in the history of the area seriously delayed plaintiff’s construction work with the result that completion of the project required some 286 days longer than originally contemplated. Contributing to this delay were deficiencies in the Government-designed drainage system which caused quagmire conditions at various work areas.

In its first decision, the ASBCA held (1) that the inadequate drainage system constituted a “changed condition” for which plaintiff was entitled to an equitable adjustment computed, however, on the further finding that the changed condition had affected only about 10.2 percent of the entire work-site. The Board also held (2) that plaintiff’s claim for additional interest paid for the extended contract period must be disallowed because of there being no contractual or statutory authority for the payment of such interest.

Each of these two holdings was the subject of two separate decisions by this court. In the first of these the court held, on cross-motions for summary judgment, that if the Board’s finding of a changed condition should be sustained, 1 then additional interest costs were properly a part of the equitable adjustment. Phillips Construction Co. v. United States, 374 F.2d 538, 179 Ct.Cl. 54 (1967). Thereafter, in its second decision, the court considered and sustained the Board’s finding that the defective drainage system constituted a changed condition. Phillips Construction Co. v. United States, 394 F.2d 834, 184 Ct.Cl. 249 (1968).

In an order dated August 6, 1968, I allowed defendant’s motion to stay proceedings in this court to the end that, as required by the Supreme Court’s decision in United States v. Anthony Grace & Sons, Inc., 384 U.S. 424, 86 S.Ct. 1539, 16 L.Ed.2d 662 (1966), the amount of plaintiff’s recovery under its interest claim might be determined in the first instance by the ASBCA. At the Board, plaintiff asserted that it was entitled to recover all its increased interest costs whether or not such costs were specifically related to the changed condition. In a decision dated January 21, 1969, the Board denied plaintiff’s contention. Whereupon plaintiff filed a motion for judgment in this court on the ground that the ASBCA opinion was erroneous and that the amount of interest overpayment had already been decided by the Board. In an order dated June 13,1969, the court denied plaintiff’s motion stating at 188 Ct.Cl. 1157:

* # * * * *
* * * the court concludes that the Armed Services ' Board of Contract Appeals is correct (in its opinion of January 21, 1969) in its view that the court's prior decisions in this matter (374 F.2d 538, 179 Ct.Cl. 54; 394 F.2d 834, 184 Ct.Cl. 249) held that plaintiff is entitled to the interest paid only insofar as the delay-period was attributable to the changed conditions, and that the court did not hold that plaintiff is entitled to all of the interest sought by it. The court also agrees with the ASBCA that the question of how much of the entire delay and the resulting interest costs were caused by the changed condition and how much, if any, were caused by other conditions is now properly before the Board. The court intimates no position on that question which cannot properly be before it until after the Board decides, but the court does reject plaintiff’s new contention that the defendant is automatically liable for all additional interest paid by the contractor in a Capehart Act project as a result of delays or time-extensions, regardless of the Government’s fault or responsibility. The court denies plaintiff’s motion for reconsideration.

In an opinion dated April 10, 1970, the Board found that there had been a payment by plaintiff of $79,554.09 *432

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Anthony Grace & Sons, Inc.
384 U.S. 424 (Supreme Court, 1966)
Banks Construction Company, Inc. v. The United States
364 F.2d 357 (Court of Claims, 1966)
Phillips Construction Co., Inc. v. The United States
394 F.2d 834 (Court of Claims, 1968)
John A. Johnson Contracting Corp. v. United States
132 F. Supp. 698 (Court of Claims, 1955)
John A. Johnson Contracting Corp. v. United States
132 F. Supp. 698 (Court of Claims, 1955)
Wunderlich Contracting Co. v. United States
351 F.2d 956 (Court of Claims, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
440 F.2d 429, 194 Ct. Cl. 695, 1971 U.S. Ct. Cl. LEXIS 158, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phillips-construction-co-inc-v-the-united-states-cc-1971.