Banks Construction Company, Inc. v. The United States

364 F.2d 357, 176 Ct. Cl. 1302, 1966 U.S. Ct. Cl. LEXIS 67
CourtUnited States Court of Claims
DecidedJuly 15, 1966
Docket17-64
StatusPublished
Cited by16 cases

This text of 364 F.2d 357 (Banks Construction Company, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Banks Construction Company, Inc. v. The United States, 364 F.2d 357, 176 Ct. Cl. 1302, 1966 U.S. Ct. Cl. LEXIS 67 (cc 1966).

Opinion

*360 OPINION

PER CURIAM:

This case was referred to Chief Trial Commissioner Marion T. Bennett with directions to make findings of fact and recommendation for conclusions of law. The commissioner has done so in an opinion and report filed on March 1, 1966. Plaintiff has filed no exceptions to or brief on this report and the time for so filing, pursuant to the rules of the court, has expired. On May 2, 1966, defendant filed a motion that the court adopt the report of the commissioner and that plaintiff’s petition be dismissed accordingly. Since the court agrees with the trial commissioner’s opinion, findings and recommendation, with one slight modification, it hereby adopts the same as the basis for its judgment in this case, as hereinafter set forth. Plaintiff is therefore not entitled to recover and the petition is dismissed.

OPINION OF COMMISSIONER *

BENNETT, Chief Commissioner:

Plaintiff, Banks Construction Company, Inc., was awarded a contract (No. DA-38-081-ENG-547) by the United States Government, acting through the contracting officer, Charleston (S.C.) District, Corps of Engineers, United States Army, for the construction of secondary roads, a storage or salvage area and drainage ditches at Myrtle Beach Air Force Base, Myrtle Beach, South Carolina. Additional costs were incurred throughout the performance of the contract. Plaintiff contends that these extra costs were not within the contemplation of the contract but were due solely to defendant’s breach of the contract. A claim for these additional costs was submitted to the contracting officer pursuant to the procedure provided by the “Disputes” clause of the contract but was denied in all but one respect. 1

Successive appeals to the U. S. Corps of Engineers’ Board of Contract Appeals, hereinafter referred to as Eng. BCA, and the Armed Services Board of Contract Appeals, hereinafter referred to as ASB CA, were denied in all but one respect. 2

The case is before the court on an assignment of errors filed by the plaintiff challenging the administrative decision as not supported by substantial evidence. 3 The assignment of errors is to the administrative record. No de novo evidence has been taken before the court. 4

Plaintiff has concluded its assignment with a prayer that the “entire case be heard de novo by this Court, and in the alternative, that this Court * * * award * * * judgment against the defendant in the amount of One Hundred Forty Thousand Two Hundred Eighty-Five and 67/100 ($140,285.67) Dollars * * * ” plus interest, attorney’s fees and costs. For reasons hereinafter dis *361 cussed in the first assignment, plaintiff is not entitled to a trial de novo. The reasons believed to bar judgment for plaintiff will be discussed in connection with the remainder of its assigned errors.

The facts pertinent to the determination of the case are related fully in each assignment hereinafter discussed, but a general recitation of the facts as developed by the record will afford a background for the discussion to follow.

Pursuant to an invitation for bids, plaintiff’s contract was executed on December 31, 1956, and was to be performed within 300 calendar days after receipt of notice. The notice to proceed was acknowledged on January 15, 1957, and the original completion date was November 11, 1957. Eighteen modifications were issued, increasing the contract price and extending the time for completion to August 19, 1958.

The Air Base is located on the narrow strip of land between the Atlantic Ocean and the Atlantic Intracoastal Waterway. The area is flat and swampy. The elevation within the area of construction was between 12 and 13 feet above sea level at those points nearest the ocean and waterway, with a maximum elevation of 23 feet above sea level. The Air Base is completely bounded by private or state and county property.

Prior to the submission of its bid and in accordance with the site-investigation requirement of the invitation and specification GC-3 of the general conditions, plaintiff’s president visited the site of the work before bidding. In pertinent part that provision provided that the contractor satisfy himself “as to the nature and location of the work, the general and local conditions, including but not restricted to those bearing upon * * * uncertainties of weather, river stages, tides or similar physical conditions at the site, the conformation and conditions of the ground, * * It also provided that the contractor was not relieved from responsibility for estimating properly the difficulty or cost of successfully performing the work as a result of failure to acquaint himself with all available information as to obstacles to be encountered insofar as the information was reasonably ascertainable from an inspection of the site, all exploratory work done by the Government and the information presented by the drawings and specifications.

Plaintiff was to construct roads designated as A, B, F, J, Y, Z and one designated as Patrol Road. As an integral part of the construction of the roads, plaintiff was to construct parallel ditches. The ditches were to provide drainage for the newly constructed roads. The plans furnished the plaintiff contained information concerning the existing terrain features of the Air Base and the work to be performed. The existing terrain features included an existing road network, certain facilities already in place, and existing drainage ditches. Arrows indicating the direction of the flow of water were placed on the drawings alongside the existing ditches as well as the ditches to be constructed by the plaintiff. The information relating to the work to be constructed by the plaintiff was minutely detailed and precise in that it showed required elevations of roads, depth of drainage ditches, grades of roads and ditches, direction of flow of water in the ditches, readings in metes and bounds of the roads, slopes of road shoulders, and configuration of ditches. The work prescribed was to be performed in strict accordance with the general provisions, specifications, schedules, drawings, and conditions, all of which were part of the contract.

The drawings further showed that the ditches to be constructed by plaintiff were to connect with existing ditches and canals, so that the water flowed through the former into the latter which led off the military reservation. The plans also refer to the location of points of outfall, the points where water was to drain beyond the military reservation.

The existing ditches within the plaintiff’s work area and those outside the boundaries of the Air Base and not within the work area were somewhat overgrown with vegetation. This was readily *362 apparent from an examination of the site of construction and was noted by plaintiff’s president, Mr. Gary Banks on the occasion of his prebid visit. At that time he had walked about the work area with particular interest focused on the availability of drainage.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Gas & Electric Co. v. United States
73 Fed. Cl. 333 (Federal Claims, 2006)
Hardwick Bros. v. United States
41 Cont. Cas. Fed. 76,972 (Federal Claims, 1996)
Portable Rock Production Co. v. United States
31 Cont. Cas. Fed. 72,053 (Court of Claims, 1984)
Turnkey Enterprises, Inc. v. United States
597 F.2d 750 (Court of Claims, 1979)
McGovney & McKee, Inc. v. City of Berea, Ky.
448 F. Supp. 1049 (E.D. Kentucky, 1978)
Broome Construction, Inc. v. United States
492 F.2d 829 (Court of Claims, 1974)
Hardeman-Monier-Hutcherson v. United States
458 F.2d 1364 (Court of Claims, 1972)
Wertheimer Construction Corp. v. United States
406 F.2d 1071 (Court of Claims, 1969)
Phillips Construction Co., Inc. v. The United States
394 F.2d 834 (Court of Claims, 1968)
WRB Corp. v. United States
183 Ct. Cl. 409 (Court of Claims, 1968)
Amino Brothers Company, Inc. v. The United States
372 F.2d 485 (Court of Claims, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
364 F.2d 357, 176 Ct. Cl. 1302, 1966 U.S. Ct. Cl. LEXIS 67, Counsel Stack Legal Research, https://law.counselstack.com/opinion/banks-construction-company-inc-v-the-united-states-cc-1966.