McGovney & McKee, Inc. v. City of Berea, Ky.

448 F. Supp. 1049, 1978 U.S. Dist. LEXIS 18932
CourtDistrict Court, E.D. Kentucky
DecidedMarch 20, 1978
DocketCiv. A 2158
StatusPublished
Cited by7 cases

This text of 448 F. Supp. 1049 (McGovney & McKee, Inc. v. City of Berea, Ky.) is published on Counsel Stack Legal Research, covering District Court, E.D. Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McGovney & McKee, Inc. v. City of Berea, Ky., 448 F. Supp. 1049, 1978 U.S. Dist. LEXIS 18932 (E.D. Ky. 1978).

Opinion

MEMORANDUM OPINION

SILER, District Judge.

After trial without a jury, the Court has made the following Findings of Facts and Conclusions of Law, pursuant to Rule 52, Fed.R.Civ.P. The case began on July 2, 1970, as a suit for declaratory relief, under 28 U.S.C. §§ 2201, 2202 by McGovney & McKee, Inc. (hereinafter “Contractor”) against the City of Berea, Kentucky (hereinafter “Berea”), to determine if Berea was allowed to terminate the contract involved or if it was the duty of Berea to furnish drawings and specifications to Contractor to complete its contract. Berea filed a counterclaim demanding damages against Contractor for breach of contract in filing a third-party complaint against United States Fidelity & Guaranty Co. (hereinafter “Surety”) as the surety on the construction contract. By the time this came to trial in 1976, the declaration of rights issue was subverted to the counterclaim and third-party claim, as Berea had hired another contractor, Nash & Stewart (hereinafter “N&S”), to finish the project. The Court does not know why it took so long for this case to be set for trial, but it is noted that Contractor’s original counsel, Frank S. Ginoccio, is now dead, and the Judge to whom this case was originally assigned, Honorable Mac Swinford, died in 1975. It was subsequently assigned to Chief Judge Bernard T. Moynahan, Jr., and then to the undersigned Judge. In the meantime, between the fiscal years from the date the case was filed until the trial, the civil case load of this Court increased 179.5% (from 913 pending cases to 2926) without a commensurate increase in the number of Judges. (An additional Judge took office in 1972, but the position had been authorized in 1970.) Perhaps that, to some extent, was a contribu *1052 ting factor to the delay in arriving at a legal solution. An additional problem has arisen in this Court deciding this case once submitted. As it is a diversity case with no priority over criminal and certain other types of cases, it has lain on the docket for about one year from the date submitted. This illustrates the problems of handling diversity cases in federal courts. Cf. Arrow-Hart, Inc. v. Philip Carey Co., 552 F.2d 711 (6th Cir. 1977). This is digressing from the essential facts and legal questions to be decided, but it was thought necessary to explain why there was such a delay in this matter. Had Contractor not chosen the federal forum, and had filed the matter in a state court, or had this Court been able to get to the case immediately; Contractor could have determined its rights before the contract was let to N&S, and much of this litigation could have been avoided.

FINDINGS OF FACTS

Berea is a municipal corporation located in Madison County, Kentucky, and is a citizen of the Commonwealth of Kentucky. Contractor is a corporation incorporated in Ohio with its principal place of business in Portsmouth, Ohio, and is, therefore, a citizen of the State of Ohio. Surety is a corporation incorporated in the State of Maryland, with its principal place of business in Baltimore, Maryland, and is, therefore, a citizen of Maryland. The amount in controversy exceeds $10,000.00, exclusive of interest and costs.

Berea entered into a contract, which is the subject of this controversy, with Contractor for the construction of a sewage treatment plant. The work was to be done according to the plans and specifications provided by Theodore Strunk, an engineer, who died before this case came to trial. The project was bid according to law and Contractor was the low bidder to complete the project at an overall cost of $217,375.00. The contract was entered into on April 24, 1969, and work commenced on July 7, 1969, to be completed by September 11, 1970, or else be subject to liquidated damages in the amount of $100.00 per day until the project was completed. Surety was on the performance bond, the terms of which will be discussed post.

During the construction period, after a concrete aeration tank eighty-eight feet in diameter had been poured and was sitting on the ground in place, there was an accumulation of ground or surface water in the area of the tank, causing it to float out of its original position and to lodge on a rock at a tilt. No one was at the job site when this occurred, but it was discovered sometime between December 29,1969, and January 22, 1970. At that time, River City Construction Co., a subcontractor, whose superintendent was John Clifford, was doing this phase of the work for Contractor. As the water was rising just before the tank floated, Strunk had gone to the job site, and had told Clifford he could shut down the construction work because of bad weather. He further told Clifford that water was flowing into the aeration tank from another tank in the project and the water in the aeration tank was equalizing the pressure on the outside so that the tank would not float. The work was then shut down by Contractor. Shortly thereafter, Strunk told Clifford by telephone that the tank had floated and Clifford the following day went to the job site where he and Strunk took certain measurements on the elevation and alignment, preparatory to placing the tank back into its proper position. As the weather was too .bad to allow work at the time, the actual movement of the tank was postponed until later when the weather cleared.

It was not until April, 1970, that Contractor took some action concerning the tank, when it dewatered the tank and cleaned up the debris in the vicinity. It was discovered that the tank was sitting on a rock ledge and the tank floor was damaged to the extent that it would have to be repoured. Several meetings were held in April and May, 1970, with Clifford, Strunk and Berea *1053 officials in attendance to determine what steps to take to rectify the situation and to complete the contract. Contractor asserted it was ready, willing and able to complete the contract but desired advice from Strunk or Berea as to what it needed to do to complete the project, pursuant to section 3 of the contract, which provided:

The contractor will be furnished additional instructions and detailed drawings as necessary to carry out the work included in the contract.

In April, 1970, Berea accepted the work of Contractor as having been performed up to that time according to the contract. As no work had actually been done after the tank floated, it apparently was approval of the work up to December, 1969. However, in one of the meetings in May, Contractor presented to Berea a study made by another engineering firm, M&W Engineers, as to how the tank could be set back in place and the work continued. Contractor indicated a desire to complete the contract with additional plans and more compensation. Neither Berea nor Strunk gave any consent for Contractor to proceed under any different set of plans nor did either provide additional plans or specifications. Consequently, there was an impasse and no work was being done to complete the job.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown Bros. Inc. v. Metropolitan Government
877 S.W.2d 745 (Court of Appeals of Tennessee, 1993)
Western & Southern Life Insurance v. Crown American Corp.
877 F. Supp. 1041 (E.D. Kentucky, 1993)
Twin River Construction Co. v. Public Water District No. 6
653 S.W.2d 682 (Missouri Court of Appeals, 1983)
McGovney & McKee Inc. v. City of Berea
627 F.2d 1091 (Sixth Circuit, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
448 F. Supp. 1049, 1978 U.S. Dist. LEXIS 18932, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcgovney-mckee-inc-v-city-of-berea-ky-kyed-1978.