Board of Education of Henderson County, Kentucky v. Spinazzolo Systems, Inc.

986 F.2d 1421, 1993 U.S. App. LEXIS 9544, 1993 WL 30493
CourtCourt of Appeals for the Sixth Circuit
DecidedFebruary 9, 1993
Docket92-5013
StatusUnpublished

This text of 986 F.2d 1421 (Board of Education of Henderson County, Kentucky v. Spinazzolo Systems, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Education of Henderson County, Kentucky v. Spinazzolo Systems, Inc., 986 F.2d 1421, 1993 U.S. App. LEXIS 9544, 1993 WL 30493 (6th Cir. 1993).

Opinion

986 F.2d 1421

NOTICE: Sixth Circuit Rule 24(c) states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Sixth Circuit.
BOARD OF EDUCATION OF HENDERSON COUNTY, KENTUCKY, Plaintiff-Appellant,
v.
SPINAZZOLO SYSTEMS, INC., Defendant-Appellee.

No. 92-5013.

United States Court of Appeals, Sixth Circuit.

Feb. 9, 1993.

Before KENNEDY and MILBURN, Circuit Judges, and WELLFORD, Senior Circuit Judge.

WELLFORD, Senior Circuit Judge.

The defendant, Board of Education of Henderson County, Kentucky (the Board), appeals from a district court order awarding damages and prejudgment interest to contractor Spinazzolo Systems, Inc. (Spinazzolo) in this diversity breach of contract action. For the following reasons, we REVERSE.

I. FACTS

In 1982, the Henderson County Board of Education began preparations to remove asbestos fibers discovered in the ceilings and pipe insulation in sixteen schools. It hired Gobbell-Hays Partners, Inc., (Gobbell), an architectural firm, to outline specifications for the project and to prepare a package proposed for use in soliciting bids for this project.

The bid package contained proposed contract provisions and drawings identifying areas of the schools requiring asbestos removal. Gobbell's drawings were computer generated versions of the original blueprints for these schools. Printed on each drawing contained in the bid package was the scale used in the original blueprints: one inch equals eight feet. That scale was accurate for thirteen of the sixteen schools. For three schools, however, the scale was incorrect; Gobbell reduced the original blueprint but failed to adjust the scale to reflect this reduction. As a consequence, the bid package indicated that three schools were substantially smaller than their actual size.1

The plaintiff Spinazzolo received its bid package on May 20, and bids were due by May 25. A company representative briefly visited the schools, including the three now in dispute, and Spinazzolo bid on the contract. Spinazzolo's bid--more than $50,000 lower than the next lowest bid--was accepted by the Board. The district court found that Spinazzolo had relied on the incorrectly scaled drawings when figuring its bid, and, consequently, that Spinazzolo had "substantially" underestimated the amount of work required.

During the course of the project, Spinazzolo discovered the erroneous scale on the three schools and brought the discrepancies to the Board's attention. Spinazzolo contended that language in the bid package invited it to rely on the bid documents, and that the work associated with the discrepancies was "extra work" under the contract. The Board maintained that disclaimers in the bid package adequately warned Spinazzolo not to use the scale on the reproduced drawings when figuring actual dimensions. Without resolving this disagreement, the parties proceeded toward completion of the project.

After Spinazzolo had substantially completed the contract, the Board sued Spinazzolo for certain property losses and for liquidated damages for delay in completion. Spinazzolo counterclaimed, seeking damages for the balance of the contract price allegedly unpaid and for the "extra work" performed as a result of the erroneous drawings.2

Following a bench trial, the district court found the Board liable to Spinazzolo on its counterclaims. The court held that under Kentucky law, an owner impliedly warrants the fitness of the plans and specifications he provides to a contractor and that the contract in this case was ambiguous concerning the extent to which Spinazzolo could rely on the drawings. Accordingly, it awarded Spinazzolo damages for "extra work" and also for the balance of the contract price, less certain set-offs.3 The court awarded prejudgment interest on the contract price award and post-judgment interest on the "extra work" claim.

Arguing that disclaimers in the bid package shield it from liability for the inaccurate scaling, the Board appeals from the district court order awarding damages for "extra work." The Board also contends for the first time on appeal that the award of prejudgment interest violated principles of sovereign immunity applicable under Kentucky law.

II. STANDARD OF REVIEW

This court reviews interpretations of contract language de novo. FDIC v. Aetna Casualty & Surety Co., 903 F.2d 1073, 1077 (6th Cir.1990). The district court's decision to award "extra work" damages to Spinazzolo rested on the conclusion that the Board "warrantied the drawings for fitness." Op. at 8. Implicit in the court's finding that the Board impliedly warranted its drawings is a finding that the contract language permitted Spinazzolo to rely on the drawings for dimensional accuracy. Differentiating between what may and what may not be inferred from particular contract language involves interpretation of the contract. The district court's decision to award "extra work" rested on its interpretation of the contract, and is therefore reviewable de novo. See Aetna, 903 F.2d at 1077, 1079 (reviewing de novo a district court finding that certain losses were "discovered" by the defendant within the meaning of the contract); Messer v. Paul Revere Life Ins. Co., 884 F.2d 939, 940-41 (6th Cir.1989) (reviewing on the de novo standard a district court ruling that a conversion provision in insurance contract did not entitle decedent to double indemnity death benefits); Davis v. Sears, Roebuck & Co., 873 F.2d 888 (6th Cir.1989) (whether action allegedly conflicting with oral representations and past practices gave rise to breach of implied covenant of good faith and fair dealing involved contract interpretation and was reviewable de novo).

Because of the error in scaling on the bid package documents, the district court found that the three schools involved in this controversy appeared to be "substantially smaller than their actual size." Spinazzolo concededly had five days to prepare and submit a bid. Spinazzolo, or its representative, visited each of the schools, and the district court found that project "specifications also indicated that contractors preparing bids should make a thorough examination of the sites and verify all dimensions contained within the documents." The district court's finding that "asbestos cannot be identified in the field" is irrelevant to the extra work claim, because, for each building, the plans and specifications accurately identified the areas containing asbestos. Even though the plans were schematically correct,4 the district court noted that the plans were "defective" because they were improperly scaled,5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
Hormel v. Helvering
312 U.S. 552 (Supreme Court, 1941)
United States v. Keith Pickett
941 F.2d 411 (Sixth Circuit, 1991)
Powell v. Board of Education of Harrodsburg
829 S.W.2d 940 (Court of Appeals of Kentucky, 1991)
Codell Construction Co. v. Commonwealth
566 S.W.2d 161 (Court of Appeals of Kentucky, 1977)
McGovney & McKee, Inc. v. City of Berea, Ky.
448 F. Supp. 1049 (E.D. Kentucky, 1978)
Dravo Corp. v. Commonwealth, Department of Highways
564 S.W.2d 16 (Court of Appeals of Kentucky, 1977)
Commonwealth, Department of Highways v. Young
380 S.W.2d 239 (Court of Appeals of Kentucky (pre-1976), 1964)
Bankers Bond Co. v. Buckingham, Commonwealth Treasurer
97 S.W.2d 596 (Court of Appeals of Kentucky (pre-1976), 1936)
All-American Movers, Inc. v. Commonwealth ex rel. Hancock
552 S.W.2d 679 (Court of Appeals of Kentucky, 1977)
Culbertson v. Ashland Cement & Construction Co.
139 S.W. 792 (Court of Appeals of Kentucky, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
986 F.2d 1421, 1993 U.S. App. LEXIS 9544, 1993 WL 30493, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-education-of-henderson-county-kentucky-v-spinazzolo-systems-ca6-1993.