Dravo Corp. v. Commonwealth, Department of Highways

564 S.W.2d 16, 1977 Ky. App. LEXIS 907
CourtCourt of Appeals of Kentucky
DecidedNovember 25, 1977
StatusPublished
Cited by3 cases

This text of 564 S.W.2d 16 (Dravo Corp. v. Commonwealth, Department of Highways) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dravo Corp. v. Commonwealth, Department of Highways, 564 S.W.2d 16, 1977 Ky. App. LEXIS 907 (Ky. Ct. App. 1977).

Opinion

HOWERTON, Judge.

This appeal arises from a suit by appellant Dravo Corporation, a bridge construction company, against the Commonwealth of Kentucky which resulted in a judgment dismissing the plaintiff’s complaint after a lengthy trial by the court and extensive findings of fact and conclusions of law. On this appeal, Dravo Corporation cites numerous errors in those findings and conclusions.

The Department of Highways of the Commonwealth of Kentucky entered into a contract with Dravo Corporation in August 1970, for the construction of the substructure and approaches for the 1-24 Interstate bridges across the Tennessee River in Marshall and Livingston Counties, near Padu-cah, Kentucky. The total estimated cost of the contract, based upon unit prices, was six million, two hundred twenty three thousand, four hundred ninety eight dollars and fifty six cents ($6,223,498.56). During the construction, five change orders were approved totalling $296,539.51. This increase, along with unit price payments paid on piles actually furnished and driven, brought the total construction cost to $6,520,038.07. This amount, in large part, reflected the cost of “furnishing” and “driving” piles to support the approach abutments on each end of the bridges, and the intermediate “ land and river piers.

After requesting compensation for extra work and exhausting subsequent administrative remedies, Dravo Corporation brought suit in October 1972, pursuant to the provisions of the contract claim statute, KRS 44.310 (subsequently amended).

Dravo’s complaint alleged damages as a result of changes in the contract drawings, plans, requirements and specifications relating to bearing pilework for the substructure after work had begun on the project. Fur *18 ther, it was alleged that Dravo encountered conditions in the rock and subsurface conditions at the project site which were different from the representations and drawings promulgated by the Highway Department and which constituted changed conditions resulting in additional expenses and extra work for which the contractor was entitled to compensation. The Highway Department admitted that it had changed the design in the contract drawings, but denied that the changes constituted changes in the contract requirement for which Dravo would be entitled to compensation beyond the unit prices paid for the work under the terms of the contract. Appellees additionally argued that the cost of the performance after the changes and alterations in the plans did not exceed the cost of the performance prior to such changes. Finally, the appellee argued that the character of the work had not been changed, and denied that subsurface conditions were different from those shown on the design drawings.

After preliminary hearings, motions, and discovery, a trial before the court was held in December 1973, lasting over a period of two weeks. The testimony of each party consisted entirely of engineering witnesses. A transcript of over 800 pages in eight volumes was compiled. Over 60 exhibits were introduced either jointly or by one of the parties. From this mass of information, the trial court entered a judgment dismissing appellant’s complaint, based upon 31 separate findings of fact and 30 conclusions of law.

The briefs on this appeal are extensive and exhaustive. In the main, the argument of the appellant is that the trial court made several errors in its findings of fact and had these errors not been made, the conclusions of the trial court would have been counter to the conclusions and judgment rendered. The appellant argues that the trial court erred in concluding 1) that the subsurface conditions in the area of construction were not materially different from the representations of the substructure condition on the design plans and drawings for the bridge project, 2) that there were no misrepresentations on the design plans concerning the subsurface conditions and bearing pilework, 3) that there was no withholding of material information to the plaintiff and other prospective bidders concerning the subsurface conditions, and 4) that the change by the Department of Highways in the design of the substructure, after construction commenced, did not result in extra work for the appellant, and did not change the character of the work required of the contractor. It is argued that findings contra to these would have necessitated the awarding of damages to Dravo Corporation.

We affirm the decision of the circuit court. It is our conclusion that the judge correctly followed the law of this commonwealth, based upon his findings of fact. Of course, as to the findings of fact, we are controlled by CR 52.01 which states in part — “Findings of fact shall not be set aside unless dearly erroneous, and due regard shall be given to the opportunity of the trial court to judge the credibility of the witnesses.” (Emphasis ours) On reviewing the great wealth of argument and evidence in this case, we cannot say that any of the findings of the trial court are manifestly against the weight of the evidence. While neither the parties nor the court had benefit of the opinion during the trial of this case, we believe that the judgment reached is in conformity with a recent opinion of this court. See Codell Construction Company v. Commonwealth of Kentucky, Ky.App., 566 S.W.2d 161 (1977).

It was stated by this court in Codell, supra, that:

Generally, government agencies can provide bidders with estimates and other related information without incurring a risk of liability as to the accuracy of such information and estimates, only so long as their intent to do so is made clear by an express and unqualified disclaimer as to the accuracy of the information.

The plan sheets, numbers 28 and 29, provided boring logs with related boring data, together with an “estimated pile tip” elevation. On the second of these sheets, a disclaimer was given, stating “These data are *19 furnished for information only, and may or may not represent the actual conditions which will be found when work is executed.” The court buttressed its understanding of this disclaimer with additional facts concerning the entire concept of “test piles”. The court determined that the entire concept of running test piles was to determine the length of piles required in the construction. Section 11 of the special notes in the contract proposal even provided that if the test results indicated the structure foundation required re-design to achieve safety standards, no claim would be made against the Department for costs or construction delays required by the redesign.

Upon driving the first test pile, it was found that the pile would not act as a friction-type pile to achieve the required 80-ton minimum bearing capacity. The pile was thereafter driven deeper until the desired bearing capacity was met and subsequently, the pile was driven even deeper until it met “refusal” or founded on solid rock.

The trial court concluded that there was no material misrepresentation to the plaintiffs in the plans or specifications, nor was there a withholding of any material or significant information from prospective bidders.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
564 S.W.2d 16, 1977 Ky. App. LEXIS 907, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dravo-corp-v-commonwealth-department-of-highways-kyctapp-1977.