O'Neill Construction Co. v. Philadelphia

6 A.2d 525, 335 Pa. 359, 1939 Pa. LEXIS 439
CourtSupreme Court of Pennsylvania
DecidedApril 20, 1939
DocketAppeal, 317
StatusPublished
Cited by18 cases

This text of 6 A.2d 525 (O'Neill Construction Co. v. Philadelphia) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'Neill Construction Co. v. Philadelphia, 6 A.2d 525, 335 Pa. 359, 1939 Pa. LEXIS 439 (Pa. 1939).

Opinion

Opinion by

Mr. Justice Stern,

In the construction of the Little Tacony Creek sewer, from a point southwest of Lewis Street to the junction of Little Tacony and Frankford Creeks, the City of Philadelphia let the job in two sections, one extending *361 from the northeasterly end to a point about 700 feet northeast of Frankford Creek, and the other completing the sewer southwesterly to that creek. The first section was constructed by the firm of Mazóla & Morana and was finished about a year before the second was begun. Plaintiff company was the low bidder on the latter job. It entered into a contract with the city, in which it agreed to perform the work in accordance with the specifications, the proposal, and the approved plans as shown upon the drawings. The sewer required an excavation of a width of 12 ft. 10 in. and a depth of 11 ft. 6 in.; its center line ran along or close to the northwesterly edge of Little Tacony Creek. Plaintiff began its work at the junction of the two creeks, proceeding northeasterly, and for a distance of about 180 feet met with no unusual difficulty. Beginning at that point, and for the remaining 520 feet of its contract, it encountered a submerged mass of cribbing buried some two or three feet under the surface and apparently constructed by some former owner of the abutting land in order to prevent erosion of the bank. It lay in the northwesterly half of the area of the sewer excavation, and formed a compact structure approximately 8% feet in width and of equal height, with long, heavy timbers laid longitudinally and railroad ties crosswise. To remove it required considerable extra labor, and the present suit in assumpsit was brought to recover the sum of $23,474.88, with interest, alleged to represent the additional cost to plaintiff of excavation made necessary by this unexpected condition. The case was tried without a jury under the Act of April 22, 1874, P. L. 109. -Judgment was entered for defendant.

Ordinarily, as plaintiff admits, a contractor is presumed, in the absence of an express provision to the contrary, to have assumed the risk of unforeseen contingencies arising during the course of the work, unless performance is rendered impossible by an act of God, the law, or the other party: Cramp & Co. v. Central *362 Realty Corporation, 268 Pa. 14, 20. Plaintiff’s claim rests upon an alleged misrepresentation made by the City in the plans upon which plaintiff based its bid. These plans showed six borings, 100 feet apart, from 7 to 13 feet in depth, and purporting to have been made along the center line of the sewer. At these points they represented the subsoil as consisting of successive layers of sand and loose stone, soft rock, and underlying hard rock, but did not show any artificial obstruction. The borings, with one exception, had not in fact been made on the center line of the sewer but alongside a retaining wall on the southeasterly bank of the creek about 12 feet distant from that line. The results there obtained were accurately represented on the plans, but, as previously stated, locations of all but one of the borings were not correctly shown. How this came about is not explained in the testimony. The city inspector who was present when the borings were made accurately recorded in his field book that “except as noted, all test borings are located approximately 16 inches north of the concrete retaining wall on the south bank of creek,” but whether the draftsman of the plans negligently failed to copy this thereon, or whether he considered it unimportánt that the borings were shown as on the center line of the sewer instead of twelve' feet away, does not appear. 1 The court below found that “all the ‘misrepresentations’ were innocent,” and this finding was justified by the evidence, since there was nothing to indicate any delibérate or intentional design on the part of the draftsman or of anyone else in the Bureau of Engineering and Surveys to misléad bidders as to the actual condition of the subsoil.

*363 The defense presented by the City to plaintiff’s action was the presence of certain clauses in the proposal forms and in the standard specifications absolving the City from liability in case the borings as shown on the plans did not properly represent the physical conditions. One such elause in the proposal forms was as follows: “Prospective bidders should determine for themselves the subsoil conditions that will be met with in the prosecution of the work. The record of test borings shown is not guaranteed by the City. Refer to clause A-76 of the Standard Specifications.” A clause in the specifications provided: “Bidders must examine the location of the proposed work and make themselves acquainted with the conditions on the ground and the character of material to be encountered.” Another clause in the specifications (A-76, entitled “Borings”) was as follows: “Where borings and underground and overhead structure locations are of record in the Bureau, they were made for the information of the Bureau, as an aid to complying with the provisions of the Act of Assembly of June 25, 1919; their correctness is not guaranteed by the City, and in no event is this information to be considered as a part of the contract. If this information is used by a bidder in preparing his proposal, he must assume all risks resulting from conditions differing from approximation shown. If the bidders desire to obtain such data, the City will afford them the opportunity at their own expense, to make wash drillings, core borings, or dig test pits on the site of the work.”

Plaintiff relies upon cases in various jurisdictions holding that clauses in a contract which provide for immunity against liability for fraudulent misrepresentation are invalid and unenforceable. Thus in S. Pearson & Son, Ltd. v. Dublin Corporation, (1907) A. C. 351, the defendant corporation furnished plaintiffs with plans and specifications for the construction of sewage works. In the plans, representations were made as to *364 the position of a certain wall. In the contract it was stipulated that the contractor should satisfy himself as to the dimensions and nature of all existing structures and that the corporation did not hold itself responsible for the accuracy of the information as to the sections or foundations of existing walls and that no charges for extra work or otherwise would be allowed in consequence of incorrect information or inaccuracies in the drawings or specifications. Plaintiff brought an action of deceit against the corporation, claiming damages for false representations as to the position, dimensions and foundations of the wall, whereby they had been put to greater expense in performing the contract than would otherwise have been required. It being shown that the representations had been made by the corporation either with a knowledge of their falsity or with reckless indifference as to whether they were, true or false, it was held by the House of Lords that the plaintiffs were entitled to recover notwithstanding the protective provision of the contract, on the ground that this clause afforded immunity only as to honest mistakes, and that “no one can escape liability for his own fraudulent statements by inserting in a contract a clause that the other party shall not rely upon them”; (per Lord Loreburn, L.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mar-Paul Co. v. Jim Thorpe Area School District
7 Pa. D. & C.5th 387 (Carbon County Court of Common Pleas, 2008)
Department of General Services v. Pittsburgh Building Co.
920 A.2d 973 (Commonwealth Court of Pennsylvania, 2007)
Commonwealth v. L & L Boiler Maintenance, Inc.
407 A.2d 98 (Commonwealth Court of Pennsylvania, 1979)
Commonwealth v. Brayman Construction Co.
382 A.2d 767 (Commonwealth Court of Pennsylvania, 1978)
Dravo Corp. v. Commonwealth, Department of Highways
564 S.W.2d 16 (Court of Appeals of Kentucky, 1977)
Codell Construction Co. v. Commonwealth
566 S.W.2d 161 (Court of Appeals of Kentucky, 1977)
Cruz Construction Co. v. Lancaster Area Sewer Authority
439 F. Supp. 1202 (E.D. Pennsylvania, 1977)
Commonwealth v. Osage Co.
355 A.2d 845 (Commonwealth Court of Pennsylvania, 1976)
Commonwealth v. Acchioni & Canuso, Inc.
324 A.2d 828 (Commonwealth Court of Pennsylvania, 1974)
Branna Construction Corp. v. West Allegheny Joint School Authority
242 A.2d 244 (Superior Court of Pennsylvania, 1968)
M. L. Shalloo, Inc. v. Ricciardi & Sons Construction, Inc.
205 N.E.2d 239 (Massachusetts Supreme Judicial Court, 1965)
Montgomery v. Philadelphia
139 A.2d 347 (Supreme Court of Pennsylvania, 1958)
State v. Hartford Accident & Indemnity Co.
70 A.2d 109 (Supreme Court of Connecticut, 1949)
Pennsylvania Turnpike Commission v. Smith
39 A.2d 139 (Supreme Court of Pennsylvania, 1944)
Burke v. Allegheny County
9 A.2d 396 (Supreme Court of Pennsylvania, 1939)
City of Reading v. Rae
106 F.2d 458 (Third Circuit, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
6 A.2d 525, 335 Pa. 359, 1939 Pa. LEXIS 439, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oneill-construction-co-v-philadelphia-pa-1939.