Cruz Construction Co. v. Lancaster Area Sewer Authority

439 F. Supp. 1202, 1977 U.S. Dist. LEXIS 13274
CourtDistrict Court, E.D. Pennsylvania
DecidedOctober 27, 1977
DocketCiv. A. 75-3671
StatusPublished
Cited by2 cases

This text of 439 F. Supp. 1202 (Cruz Construction Co. v. Lancaster Area Sewer Authority) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cruz Construction Co. v. Lancaster Area Sewer Authority, 439 F. Supp. 1202, 1977 U.S. Dist. LEXIS 13274 (E.D. Pa. 1977).

Opinion

MEMORANDUM AND ORDER

TROUTMAN, District Judge.

This is an action by Cruz Construction Company, Inc. (Cruz) for damages for alleged breaches of a construction contract by the Lancaster Area Sewer Authority (the Authority). Cruz has asserted two causes of action, the first alleging underpayment for work completed and the second seeking recovery of damages suffered by Cruz in reliance on certain representations allegedly made by certain agents of the Authority. Before the Court is the Authority’s motion for summary judgment as to the second cause of action.

The following facts are uncontradicted:

1. Cruz entered into a contract with the Authority for the construction of a sanitary sewerage system.

2. Included in the contract or incorporated into the contract were various documents, including the conditions and prices stated in the Proposal, General Conditions, Supplemental General Conditions and Special Conditions of the Contract, the Plans, the Specifications and other contract documents (the contract documents).

3. Huth Engineers, Inc. (Huth) was the project engineer and prepared many of the contract documents including the plans and the specifications and supervised construction of the project.

4. Included in the plans were certain test borings or soundings which were plotted at 200 foot intervals and which indicated the level at which rock was first encountered by the contractor making the borings.

5. The contract documents also included an estimate of 8,050 cubic yards as the amount of rock that would have to be removed from trenches that were to be excavated in the course of the construction of the project.

6. Edward Cruz is the Vice President and Chief Operating Officer of Cruz. He first learned of the sewer project by reading about it in the Dodge Reports.

*1204 7. Upon learning of the project, Edward Cruz and another officer of the corporation, Evaristo Cruz, picked up available contract documents from Huth, reviewed the documents and inspected the job site with those documents in hand.

8. Cruz bid $10.00 per square foot for removal of rock from trenches within a two-foot pay width.

9. Upon commencement of the work, Cruz encountered rock at much higher levels than were indicated on the test borings shown on the plans. As a consequence, Cruz removed 27,124 cubic yards of rock from the two-foot pay width, not 8,050 as was estimated.

10. The Authority paid Cruz for all of the 27,124 cubic yards of rock removed, at the rate of $10.00 per cubic yard.

11. Cruz advised the Authority and Huth fully as to the difference in the subsurface rock conditions.

12. Cruz was forced to employ more costly and time-consuming techniques to remove the rock because of the greater quantity of rock removed as opposed to that which it would have been obliged to remove had the rock been as indicated by the test borings.

13. Cruz was also required to excavate rock from a greater width than the estimated two-foot pay width, and was, therefore, required to backfill the increased trench area with stone and to pave and restore the surface over a greater than anticipated area.

14. Jack McSherry, who was employed as Chief Construction Engineer, testified in deposition that test borings in Lancaster County were extremely unreliable because of the unpredictable nature of rock in Lancaster County, but there was no warning in the contract documents as to such unreliability. Furthermore, McSherry testified that no test boring results can ever be used to accurately estimate rock quantity unless such borings are taken at five-foot intervals.

15. McSherry testified further that he could not understand why the borings were included in the plans or why the estimate was computed to be 8,050 cubic yards, instead of a round figure such as 8,000 or even 10,000, in light of the extreme unreliability of such test borings in the Lancaster County area.

16. Allen Forbes, Executive Director of the Authority, testified that he was responsible for estimating the quantity of rock and that he based his estimate on the test borings. He also testified that no rock overrun in the entire sewer project was as great as that in this case.

17. Forbes testified further that he was informed during the construction of the sewer that Cruz was encountering more rock than that which had been estimated.

18. Calvin Levis, President of Huth, testified that Huth generally does not utilize test borings because of their great unreliability, and that it was a mistake to include such information in the plans.

19. Elmer Wagner, Vice President of Huth, testified that Huth occasionally makes test borings but does not include such information in plans.

20. Cruz did not obtain a written work order prior to performing the additional work necessitated by the overrun of rock.

21. Cruz did not submit a claim for this work along with its first estimate after completion of its work.

On these facts, Cruz contends that it based its bid of $10.00 per square yard upon the information in the contract documents, including the test borings and the estimate of 8,050 square yards of rock to be removed from the two-foot pay width.

The Authority counters that there are two reasons why Cruz cannot recover. First, the contract documents preclude reliance on the information, and such information is excluded from the contract documents by the terms of the documents. Second, plaintiff was required to obtain a written work order to perform the extra work and was required to submit a claim for this work with the first estimate after the work was completed.

*1205 The documents do include exculpatory clauses regarding physical conditions of the construction site. There are four pertinent provision in the “Information for Bidders” section of the specifications. They are:

“10. CONDITIONS OF WORK
Each bidder must inform himself fully of the conditions relating to the construction of the project and the employment of labor thereon. Failure to do so will not relieve a successful bidder of his obligation to furnish all material and labor necessary to carry out the provisions of his contract. Insofar as possible the contractor, in carrying out his work, must employ such methods or means as will not cause any interruption of or interference with the work of any other contractor.
4s 4s 4: 4s 4: 4:
“17. OBLIGATION OF BIDDER
At the time of the opening of bids each bidder will be presumed to have inspected the site and to have read and to be thoroughly familiar with the plans and contract documents (including all addenda). The failure or omission of any bidder to examine any form, instrument or document shall in no way relieve any bidder from any obligation in respect of his bid.
4s 4s 4: 4s 4. 4:
“20. SITE CONDITIONS

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Midwest Dredging Co. v. McAninch Corp.
424 N.W.2d 216 (Supreme Court of Iowa, 1988)
Environmental Utilities Corp. v. Lancaster Area Sewer Authority
453 F. Supp. 1260 (E.D. Pennsylvania, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
439 F. Supp. 1202, 1977 U.S. Dist. LEXIS 13274, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cruz-construction-co-v-lancaster-area-sewer-authority-paed-1977.