Montgomery v. Philadelphia

139 A.2d 347, 391 Pa. 607
CourtSupreme Court of Pennsylvania
DecidedJanuary 16, 1958
DocketAppeal, 352
StatusPublished
Cited by14 cases

This text of 139 A.2d 347 (Montgomery v. Philadelphia) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Montgomery v. Philadelphia, 139 A.2d 347, 391 Pa. 607 (Pa. 1958).

Opinion

Opinion by

Mr. Justice Chidsey,

This is an appeal from the order of the common pleas court sustaining defendant’s demurrer to plaintiff’s amended complaint in assumpsit.

The amended complaint avers that on July 12, 1955, the plaintiff entered into a contract with the -City of Philadelphia in which -he agreed -to- furnish• all the.-la-: *609 bor and materials to . . do all general construction work in tbe course of tbe construction of a Civic Auditorium (more commonly known as The Dell), in Fair-mount Park . . .” for the price or sum of $256,294. Plaintiff contends that due to the misrepresentations of the city as to the character of the soil involved in the construction upon which he was entitled to rely, the cost of excavation to complete performance was increased by $52,091. He further alleges that after it was discovered that the soil was not decayed mica, as anticipated, 1 but rock, he was enticed and induced to continue the excavation by the assurances of city officials that his demands would be duly considered. He also maintains that he is entitled to recover the sum of $20,491.22 for additional work and materials supplied in accordance with orders issued by authorized agents of the defendant. Plaintiff finally claims an additional $15,402.44, 2 as the alleged balance due on the original contract price of $256,294. Defendant’s preliminary objections to the amended complaint in the nature of a demurrer averred that plaintiff failed to state a cause of action for the following reasons: (a) by the terms of the Notice to Bidders which is incorporated in the contract by reference, defendant city is not responsible for the accuracy of soil conditions inasmuch as plaintiff assumed full responsibility for soil conditions; (b) plaintiff’s action insofar as it exceeds the contract limitation and appropriation for same is barred by law; (c) by the terms of the contract, no claim for extras can be allowed unless ordered in writing by the engineer and approved by the recreation commissioner. Plaintiff does not aver that *610 lie has complied with this condition precedent provided for in the contract.

Throughout the complaint, plaintiff alternately bases his claim for relief upon contract or quasi-contract. A consideration of both theories of recovery reveals no basis in law for the allowance of plaintiff’s claim.

The contract provision involved in plaintiff’s first contention states in paragraph (3) of the Notice to Bidders (an extract from the Standard Contract Requirements of the City of Philadelphia), which by law is incorporated into the contract, that bidders are required to acquaint themselves with the Standard Contract Requirements and examine in detail the character of the soil and the site of the work to be done under the contract. In addition to these general admonitions as to inspection of the situs, paragraph (3) further provides that: “Where borings, test piles, and existing underground and overhead structure locations are shown, they are for the information of the City; their correctness is not guaranteed by the City, and in no event is this information to he considered as a part of the contract. If this information is used by a bidder in preparing his proposal, he must assume all risks resulting from conditions differing from the approximation shown. If bidders desire to obtain such data, the City will afford. them the opportunity, at their own expense, to make borings or soundings, to drive test piles, or to dig test pits on the site of the work.” (Emphasis supplied). The contract further provides: “plans and specifications. Drawings— Sheets 1 to 8, L-l, S-l, M-l, E-l and E-2, all inclusive, dated December 28, 1954, with notes thereon, together with these specifications and their Standard Contract Requirements and Special Conditions form the basis upon which the Contract's are made. . . .” “General. *611 The Contractor shall accept the site as he finds it. All excavation is unclassified. The type of soil and depth at which rock may be reasonably encountered is assumed to be such as shown in the table of test borings shown on Drawing. The locations of these borings are also shown on Dwg. No. 1.”

Plaintiff’s argument that he had a right to rely on defendant’s representations as to the condition of the soil, is effectively answered by the decision of this Court in O’Neill Construction Company, Inc. v. Philadelphia, 335 Pa. 359, 6 A. 2d 525, where, concerning an almost identical clause, on pps. 365, 366 it is stated: “It is unnecessary in the present case to determine— in the absence of precedents in our own jurisdiction— to what extent the rule laid down in these authorities should be accepted as the law of Pennsylvania, because the facts here are different, both in respect to the terms of the contract (as to which the learned trial judge said: £What words could be stronger?’), and in regard to the alleged misrepresentations concerning the borings. The specifications and the proposal forms not only provided, as in the eases cited, that bidders must determine for themselves the conditions of the subsoil and that the correctness of the borings shown on the plans was not guaranteed by the City, but bidders were notified that the borings were made for the information of the Bureau in order to enable it to comply with the provisions of the Act of June 25, 1919, P. L. 581, article XX, section 2, which requires the department having charge of an improvement to estimate its cost, so that no bid in excess of the estimate should be accepted and that the liability of the City in the contract should be limited by the appropriations. It was further stated that ‘In no event is this information to he considered as a part of the contract.’ Since the plans were, hy reference, a part of the contract, this *612 ■statement was equivalent to notice that the information furnished by the borings was not to be considered as a pari of the plans. ■ In effect, therefore, the borings were as'much obliterated from the plans as if physically erased, and their appearance thereon was relegated to the status of private memoranda for the City’s own purpose.” (Emphasis supplied).

As demonstrated by the quoted language, the court in the O’Neill case explicitly negated the argument that the borings were a part of the plans, where, as here, the plans were, by reference, included as a basis for, and part of the contract. The provision that “The type of soil and depth at which rock may be reasonably encountered is assumed to be such as shown in the table of test- borings shown on Drawing. ...” is not ■sufficient to counteract the strongly worded express prohibition' that “. . . in no event is this information [test borings] to be considered as a part of the contract. . . .”

Since it may be assumed that plaintiff, being engaged in the contracting business, should have knowledge of the effect of a standard contract provision (almost duplicating that in the O’Neill case), it is unreasonable to permit plaintiff to rely on a provision that generally guarantees the correctness of the test borings, when the borings, themselves, have, in the words of the O’Neill

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth v. Anjo Construction Co.
487 A.2d 455 (Commonwealth Court of Pennsylvania, 1985)
Thomas M. Durkin & Sons, Inc. v. Nether Providence Township School Authority
460 A.2d 800 (Superior Court of Pennsylvania, 1983)
Acchione and Canuso v. COM., DEPT. OF TR.
461 A.2d 765 (Supreme Court of Pennsylvania, 1983)
J. A. & W. A. Hess, Inc. v. Hazle Township
400 A.2d 1277 (Supreme Court of Pennsylvania, 1979)
Environmental Utilities Corp. v. Lancaster Area Sewer Authority
453 F. Supp. 1260 (E.D. Pennsylvania, 1978)
Cruz Construction Co. v. Lancaster Area Sewer Authority
439 F. Supp. 1202 (E.D. Pennsylvania, 1977)
Dick Corp. v. State Public School Building Authority
365 A.2d 663 (Commonwealth Court of Pennsylvania, 1976)
Commonwealth v. Acchioni & Canuso, Inc.
324 A.2d 828 (Commonwealth Court of Pennsylvania, 1974)
Branna Construction Corp. v. West Allegheny Joint School Authority
242 A.2d 244 (Superior Court of Pennsylvania, 1968)
Montgomery v. Levy
177 A.2d 448 (Supreme Court of Pennsylvania, 1962)
Maryland Casualty Co. v. Darby Township
20 Pa. D. & C.2d 543 (Delaware County Court of Common Pleas, 1959)
Acchione v. City of Philadelphia
16 Pa. D. & C.2d 261 (Philadelphia County Court of Common Pleas, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
139 A.2d 347, 391 Pa. 607, Counsel Stack Legal Research, https://law.counselstack.com/opinion/montgomery-v-philadelphia-pa-1958.