M. L. Shalloo, Inc. v. Ricciardi & Sons Construction, Inc.

205 N.E.2d 239, 348 Mass. 682, 1965 Mass. LEXIS 871
CourtMassachusetts Supreme Judicial Court
DecidedMarch 8, 1965
StatusPublished
Cited by27 cases

This text of 205 N.E.2d 239 (M. L. Shalloo, Inc. v. Ricciardi & Sons Construction, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M. L. Shalloo, Inc. v. Ricciardi & Sons Construction, Inc., 205 N.E.2d 239, 348 Mass. 682, 1965 Mass. LEXIS 871 (Mass. 1965).

Opinion

Cutter, J.

The plaintiff (Shalloo) brings this bill to reach and apply funds of the defendant, Bieeiardi and Sons Construction, Inc. (Construction refers to the corporation as distinguished from Bieeiardi individually), in the hands of Southern New England Conference Association of Seventh Day Adventists (the Adventists) and of a bank. Shalloo seeks to recover (a) amounts alleged to be owed to it upon a subcontract with Construction, which was prime contractor upon certain work ordered by the Adventists, and (b) for extra work.

The case was referred to a master, whose report was confirmed. A final decree was entered that Construction was indebted to Shalloo in the sum of $3,319.72 1 (with interest and costs), which was to be paid to Shalloo by the Adventists from funds retained under the prime contract. Shalloo appealed. The facts are stated on the basis of the master’s report.

Construction agreed by a prime contract to perform all work for the Adventists to develop a site for a school, as shown by certain plans and specifications. Bieeiardi, a representative of Construction, Shalloo’s president, and Shalloo’s superintendent met at the site. Bieeiardi furnished Shalloo “the contract documents, specifications, a grading plan and a test boring report [included in the specifications] relating to the site.” The boring report “showed no water content within the contract area” (see fn. 2, infra). “Bieeiardi told Shalloo that . . . [Construction] would do all the engineering . . . with reference to the setting of stakes in connection with . . . work Shalloo was to do.” Shalloo thereafter executed a subcontract to do certain of the work. It provided, among other things, *684 (a) that “ [u]pon prepared subgrade, loam shall be . . . spread ... to the lines and grades and dimensions shown on the [p]lan,” and (b), in par. Fifth, “No extra work . . . under this contract will be recognized or paid for, unless agreed to in writing before the work is done . . .. ”

Shalloo completed all but three or four per cent of the subgrading before suspending work on December 9, 1960, for the winter. Eicciardi was at the site every day. On May 22, 1961, Shalloo resumed subgrading and spreading loam. During the subgrading, Shalloo’s employees stripped loam and piled it as directed by the architect or Eicciardi. “When an area was stripped the engineers” then “set the stakes in it with the necessary markings ... to gain the required subgrade. . , . When the rough cut sub-grade was reached the engineers checked it and if corrections were needed . . . [they] set new stakes . . . and . . . [Shalloo’s] employees did . . . grading to meet the requirements of those stakes.”

After May 22, 1961, a dispute arose concerning whether the subgrade preparation had been properly done. This culminated in Shalloo’s leaving the job. Construction retained others to do the work left undone. Despite this the master found that, although Shalloo 1 ‘ did not fully perform its contract, there is a balance due it on the contract for work that it did do.” Shalloo’s right to recover this balance (see fn. 1) is no longer open to dispute for Construction took no appeal from the final decree and is entitled to no more favorable decree. See Turgeon v. Turgeon, 330 Mass. 402, 409.

“While . . . [Shalloo] was working ... in both 1960 and 1961 it did certain work at the request of either the architect of the . . . Adventists or . . . Eicciardi which . . . [was] not within the written [sub]contract . . . for which . . . [Shalloo] claims compensation as extras. In none of these instances was there any compliance with” par. Fifth of the subcontract “requiring an agreement in writing for any extra work,” but “Eicciardi knew of such extra work . . . either by . . . his request for it or his *685 presence on the job site and knowing from observation . . . and making no objection.”

The master made findings with respect to the nature and value of this extra work as follows: (A) extra work extending the limits of the football field beyond those shown in the grading plan, $806.60; (B) similar extra work on the baseball field, $397.70; (C) extension of the southwest corner of the site, $746.60; (D) revision of subgrading of a perimeter road, $930; and (E) extra work caused by the Wet condition on the slopes of the site, $10,200. 2 The total of these items was $13,080.90. The issues presented for decision all relate to this extra work.

1. With respect to the first four items of extra work, the subsidiary findings fully support the master’s conclusion that the items “were not within the written contract.” The items were work in addition to those shown on a plan or plans in accordance with which Shalloo was working. The situation with respect to the extra work because of the wet area is discussed separately below.

Paragraph Fifth of the subcontract “obviously could not prevent oral contracts for extra work, for the parties had power to waive or alter that provision orally at any time. ’ ’ See Zarthar v. Saliba, 282 Mass. 558, 560. See also Bartlett v. Stanchfield,148 Mass. 394, 396; Vitti v. Garabedian, 264 Mass. 1, 6; Cueroni v. Coburnville Garage, Inc. 315 Mass. 135, 138-139. Cf. Stuart v. Cambridge, 125 Mass. 102, 109-110 (“ [n]o evidence ... of any waiver”). The master’s findings establish thát eithér the Adventist’s architect or Ricciardi directed Shalloo to do each of the first *686 four items of the extra work and that “Rieeiardi knew of such extra work.” From these findings, we think that waiver of par. Fifth, if it is applicable at all to work not covered by the subcontract (see Howard v. Harvard. Congregational Soc. 223 Mass. 562, 565; Farm-Bite Implement Co. v. Fenestra, Inc. 340 Mass. 276, 287), should be inferred.

The subcontract, although somewhat confusing in form, wé interpret as calling for the work to be done “according to the plans and specifications . . . of . . . [the] [architect, and to . . . [his] full satisfaction.” 3 In connection with this provision also must be read the provisions of the prime contract set out in the margin. 4 We take that contract to have been one of the contract documents which the master found was shown to Shalloo when the subcontract was being made. Shalloo was entitled to rely on its provisions. See Vappi & Co. Inc. v. Sullivan, 331 Mass. 463, 466-467. In the circumstances, the prime contract and the accompanying documents not only set limits on the work to be done under the subcontract but defined for Shalloo the authority of the architect and of Construction, represented by Rieeiardi. Shalloo should have been allowed to recover for the first four items of extra work.

2. As has been noted, the test boring report, which was not made a part of the master’s report,

Related

NSTAR Electric Co. v. Department of Public Utilities
968 N.E.2d 895 (Massachusetts Supreme Judicial Court, 2012)
JRJ Construction Co. v. D.A. Sullivan & Sons, Inc.
17 Mass. L. Rptr. 327 (Massachusetts Superior Court, 2003)
Marshall v. Stratus Pharmaceuticals, Inc.
749 N.E.2d 698 (Massachusetts Appeals Court, 2001)
Hartford Insurance v. Hertz Corp.
572 N.E.2d 1 (Massachusetts Supreme Judicial Court, 1991)
Findlen v. Winchendon Housing Authority
553 N.E.2d 554 (Massachusetts Appeals Court, 1990)
Abdow v. Ence
1986 Mass. App. Div. 93 (Mass. Dist. Ct., App. Div., 1986)
Richardson Electrical Co. v. Peter Francese & Son, Inc.
484 N.E.2d 108 (Massachusetts Appeals Court, 1985)
Fall River Savings Bank v. Callahan
463 N.E.2d 555 (Massachusetts Appeals Court, 1984)
Katz v. Belko
450 N.E.2d 630 (Massachusetts Appeals Court, 1983)
Adams v. Elliott
1982 Mass. App. Div. 315 (Mass. Dist. Ct., App. Div., 1982)
Barnes v. Orange Foundry, Inc.
1982 Mass. App. Div. 266 (Mass. Dist. Ct., App. Div., 1982)
Worcester Air Conditioning Co. v. Commercial Union Insurance
439 N.E.2d 845 (Massachusetts Appeals Court, 1982)
Everett Credit Union v. Allied Ambulance Services, Inc.
424 N.E.2d 1142 (Massachusetts Appeals Court, 1981)
D. Federico Co., Inc. v. Commonwealth
415 N.E.2d 855 (Massachusetts Appeals Court, 1981)
Glynn v. City of Gloucester
401 N.E.2d 886 (Massachusetts Appeals Court, 1980)
J. D'Amico, Inc. v. Town of Saugus
401 N.E.2d 884 (Massachusetts Appeals Court, 1980)
Powell's General Contracting Co. v. Marshfield Housing Authority
390 N.E.2d 267 (Massachusetts Appeals Court, 1979)
O'CONNOR v. City Manager of Medford
389 N.E.2d 440 (Massachusetts Appeals Court, 1979)
Boston Edison Co. v. Boston Redevelopment Authority
371 N.E.2d 728 (Massachusetts Supreme Judicial Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
205 N.E.2d 239, 348 Mass. 682, 1965 Mass. LEXIS 871, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m-l-shalloo-inc-v-ricciardi-sons-construction-inc-mass-1965.