Bradford Builders, Inc. v. Sears, Roebuck & Co.

270 F.2d 649
CourtCourt of Appeals for the Fifth Circuit
DecidedNovember 4, 1959
Docket17479
StatusPublished
Cited by15 cases

This text of 270 F.2d 649 (Bradford Builders, Inc. v. Sears, Roebuck & Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bradford Builders, Inc. v. Sears, Roebuck & Co., 270 F.2d 649 (5th Cir. 1959).

Opinion

SIMPSON, District Judge.

Bradford Builders, Inc. (hereinafter Bradford) a general contractor, had a contract with the Dade County Board of Public Instruction for the erection of a school building. The plans and specifications called for the enclosure of the property by a wire fence, supported by metal posts, set in concrete. On July 5, 1956, Sears, Roebuck & Co. (hereinafter Sears) entered into a sub-contract with Bradford to erect the fence. The sub-contract contained an agreement for the sub-contractor not to sublet any portion of the work, except with the contractor’s written consent.

Prior thereto, on March 8, 1956, Sears had entered into a general contract with one Jack Wilson, under which Wilson agreed, for a three year term, to accept all jobs for the installation of fence materials tendered him by Sears. Wilson’s contract with Sears contained a typical broad indemnity agreement to save Sears harmless from any claim, demand or suit against it by reason of any negligence, alleged negligence or breach of contract arising directly or indirectly from any act in connection with any installation or job undertaken pursuant to the contract. This Wilson contract was in force during the pertinent period.

Sears tendered the Bradford job to Wilson, with Bradford’s Superintendent, Ginder’s, knowledge 1 and Wilson agreed in writing to do the job, this agreement again indemnifying Sears.

*651 Bradford’s engineer, Ginder, furnished a voluminous and complete set of plans and specifications to Wilson for examination. The fence line location was shown with exactitude only on the “Plot Plan”, Sheet A-l, of the plans. It was necessary to follow this drawing to determine exact location and distances of the fence, which were not shown in detail elsewhere. The fence was installed by Wilson at the location shown on the Plot Plan. A separate sheet of the plans, Sheet M-l, showed the location of a power pole outside the property limits, with a primary electric cable running underground from this pole to a transformer vault attached to the main building. Wilson examined this sheet, along with the others submitted, noted that the underground cable shown thereon was close to and diagonal to the fence line but did not touch the fence line (shown thereon but not in detail). He gave this sheet of the plans no further attention.

In digging a post-hole for the fence, Wilson broke through the concrete conduit and cut the cable. He completed the fence installation. Bradford incurred an expense of $3169.46 in repairing and replacing the primary cable and conduit.

Bradford brought this suit against Sears in the state court, on two counts, the first for negligence in performance of the work, the second for breach of contract in procuring Wilson to do the work. Sears timely removed the case to the District Court on grounds of diversity of citizenship and requisite amount in controversy. (Title 28 U.S.C. §§ 1441(a) and 1332.) Sears defended on the following grounds: (1) Denial of negligence ; (2) Acquiescence by Bradford in Sears’ employment of Wilson to perform the work and a resulting waiver and es-toppel; (3) That Wilson was an independent contractor; and (4) That by furnishing a blue-print differing from existing conditions, Bradford “proximately caused or contributed to and assumed the risk of any damage it may have sustained.”

Sears brought Wilson in by third-party complaint based upon the indemnity provisions of its contract with Wilson. Wilson’s answer to the third-party complaint-denied negligence and also pleaded Bradford’s deviation from the plans. His answer demanded trial by jury.

Later, Sears was given leave to file and-filed a compulsory counterclaim against; Bradford for the contract price of installing the fence, $1,768. In this pleading Sears also demanded a jury trial. Bradford’s answer to the counterclaim admitted that it had not paid the contract price, asserted that it was willing to give Sears credit therefor, denied performance of the contract and re-averred negligence on the part of Wilson as Sears’ agent.

After pre-trial conference, the order upon which indicated that the case was to-be tried to a jury, the case was tried before a jury upon the issues above set forth.

At the conclusion of the evidence the District Judge withdrew the issues raised by Bradford’s breach of contract count from the jury and submitted the case between Bradford and Sears upon the issues of negligence and contributory negligence, and also submitted the issues between Sears and Wilson, to the jury. It was stated in the Court’s charge that the counterclaim for the performance of the work, in the amount of $1,768 was admitted by Bradford. The jury found for Sears and against Bradford on Bradford’s claim, found against Bradford on the counterclaim in the amount of $1,768, and as they were instructed to do In the event that Sears prevailed on the main suit, found for Wilson with respect to Sears’ third-party complaint for indemnification.

*652 From the final judgment consequent upon this verdict, Bradford entered this appeal, strenuously asserting six grounds upon which we are asked to reverse the judgment for new trial. 2

For the reasons hereinafter set forth, we affirm the District Court.

Bradford’s first question raises the propriety of the case being tried to a jury when neither of the original parties asked for jury trial in their original pleadings, the only such demand being present in Wilson’s answer, and in Sears’ counterclaim. As pointed out, the pretrial order clearly contemplated a jury trial. Appellant’s brief asserts that objection to trial before a jury was made when the case was called for trial, but admits that the transcript brought here records no such objections. The brief points out that objections were made by the motion for new trial and statement of points. Of course, without a record to sustain such objections, they were of no avail in the motion for new trial or in the statement of points. It would be entirely consistent from this record to conclude that Bradford’s counsel acquiesced in the trial of all contested issues before a jury and first objected after a jury verdict adverse to their client. If the reporter’s record was deficient in this respect, it was counsel’s duty to supply the omission, by calling upon the court reporter to transcribe the colloquy, by affidavit of some person present when the colloquy occurred, or in some other fashion. As the matter stands, we agree with appellee’s counsel that Bradford is “flying blind” as to this point.

Additionally, timely demand having been made for jury trial at least as to the issues between Sears and Wilson, we are of the plain view that the discretionary power to order trial by jury of any or all issues is plainly conferred by Rule 39(b), F.R.Civ.P. If there was not sufficient compliance with Rule 38, F.R.Civ.P., the trial Court’s denial of Bradford’s post-trial motions (see Footnote 2) indicates the District Court’s view that the jury’s conclusions were correct. In considering these motions the District Court had the benefit of Rule 61, F.R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

C & G Construction Co. v. Morrison Assurance Co.
96 F.R.D. 670 (S.D. Georgia, 1983)
Lattea v. City of Akron
458 N.E.2d 868 (Ohio Court of Appeals, 1982)
Commercial Contractors, Inc. v. Sumar Contractors, Inc.
302 So. 2d 88 (Supreme Court of Alabama, 1974)
Miller v. Town & Country Inc.
74 Misc. 2d 1038 (Suffolk County District Court, 1973)
City of Orlando v. HL Coble Construction Co.
282 So. 2d 25 (District Court of Appeal of Florida, 1973)
Katz v. Harrington
226 So. 2d 11 (District Court of Appeal of Florida, 1969)
Sawyer v. United States
297 F. Supp. 324 (E.D. New York, 1969)
Baut v. Pethick Construction Company
262 F. Supp. 350 (M.D. Pennsylvania, 1966)
M. L. Shalloo, Inc. v. Ricciardi & Sons Construction, Inc.
205 N.E.2d 239 (Massachusetts Supreme Judicial Court, 1965)
Burns v. Hartford Accident and Indemnity Company
157 So. 2d 84 (District Court of Appeal of Florida, 1963)
Albina Engine & Machine Works, Inc. v. Abel
305 F.2d 77 (Tenth Circuit, 1962)
Chichester v. Golden
204 F. Supp. 634 (S.D. California, 1962)
Kann v. Commissioner
1961 T.C. Memo. 294 (U.S. Tax Court, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
270 F.2d 649, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bradford-builders-inc-v-sears-roebuck-co-ca5-1959.