Lattea v. City of Akron

458 N.E.2d 868, 9 Ohio App. 3d 118, 9 Ohio B. 182, 1982 Ohio App. LEXIS 11296
CourtOhio Court of Appeals
DecidedDecember 23, 1982
Docket82AP-65
StatusPublished
Cited by21 cases

This text of 458 N.E.2d 868 (Lattea v. City of Akron) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lattea v. City of Akron, 458 N.E.2d 868, 9 Ohio App. 3d 118, 9 Ohio B. 182, 1982 Ohio App. LEXIS 11296 (Ohio Ct. App. 1982).

Opinion

Whiteside, P.J.

This appeal arises from an accident in which the west sidewalk of the Grant Street Bridge in Akron, Ohio, collapsed and fell onto Interstate 76, killing plaintiff’s decedents, Rev. and Mrs. John Barrickman. At the time that the sidewalk collapsed, demolí *120 tion work on the bridge was being carried out by defendant-appellant, John G. Ruhlin Construction Company (hereinafter “Ruhlin”), pursuant to a contract with the state of Ohio, Department of Transportation (hereinafter “State”). The plaintiff-appellee, Emlous Lattea, Administrator of the Estates of Rev. and Mrs. Barrickman, brought a wrongful death action in the Summit County Court of Common Pleas against Ruhlin and the city of Akron (hereinafter “Akron”). Defendant Ruhlin filed a third-party complaint against the state and, pursuant to R.C. 2743.03(E)(1), the action was transferred to the Court of Claims.

Defendant Ruhlin also filed a cross-claim against Akron, as did the state. Akron, in turn, filed cross-claims against the state and Ruhlin.

Defendants Ruhlin and Akron, with the consent of third-party defendant state, admitted negligence as to the claim of the Barrickman estates against defendants Ruhlin and Akron, reserving for future determination any rights and defenses on the various cross-claims and third-party complaints as between defendants and third-party defendant.

A jury trial was held solely on the issue of damages, resulting in a verdict for plaintiff estates of $1,006,864 jointly against Ruhlin and Akron.

A separate trial to the court was then held to determine how the $1,006,864 judgment was to be apportioned between defendant Akron, third-party defendant state and defendant Ruhlin.

Defendant Ruhlin appeals from the resultant trial court’s holding that it was liable for the full amount of the judgment and raises six assignments of error, as follows:

“I. The trial court erred as a matter of law in holding that the City of Akron violated no legal duty by reason of having supplied false, inaccurate and misleading blueprints for use in the demolition of the Grant Street bridge.
“II. The trial court erred as a matter of law in holding that the Ohio Department of Transportation violated no legal duty by reason of having supplied false, inaccurate and misleading blueprints for use in the demolition of the Grant Street Bridge.
“III. The trial court erred as a matter of law in holding that the act of Ruhlin in cutting the top level of steel reinforcement bars was the sole proximate cause of the deaths of John and Patricia Bar-rickman.
“IV. The trial court erred as a matter of law in holding that the project supervisor and project inspector were only agents of the Ohio Department of Transportation.
“V. The trial court erred as a matter of law in failing to hold the City of Akron and the Ohio Department of Transportation liable by reason of their participation in the decision to cut the upper set of steel reinforcement bars.
“VI. The trial court erred as a matter of law in failing to hold the City of Akron jointly liable for the collapse of the bridge by reason of R.C. 723.01.”

The Akron Grant Street Bridge runs in a northerly and southerly direction above Interstate 76. It was constructed in 1960-1961 by the National Engineering and Contracting Company pursuant to a contract with the state. As designed and constructed, the bridge had two cantilevered sidewalks on the east and west sides of the bridge. In a cantilevered design, part of each sidewalk rests on the bridge deck or slab, and part of the sidewalk extends out beyond the outermost edge of the bridge deck.

Those portions of the cantilevered sidewalks extending out beyond the edge of the bridge deck were intended to be supported primarily by two sets of steel reinforcing bars placed in each sidewalk, one row above the other. In the west sidewalk, there were also two rows of telephone conduit running through the sidewalk from north to south between the two sets of bars. The construction plans *121 provided that the steel bars should run in a transverse direction from the outermost edge of the western sidewalk to that portion of the sidewalk resting on the bridge deck, one set above the conduit and the other set below the conduit. As constructed, however, the lower level of reinforcing bars was cut off at the point where they were to have passed under the conduits.

Sixteen years after construction, defendant Akron and the state entered into a contract for necessary repairs to the Grant Street Bridge. As part of its share of the cost of the bridge repair, Akron agreed to assume and contribute one hundred percent of the cost of preparing the project plans. The bridge repair itself was, however, a state project.

The state contracted with defendant Ruhlin for the repair of the Grant Street Bridge in accordance with specifications the state prepared and project plans prepared by Akron but approved by the state. This contract provided that defendant Ruhlin was to dismantle and replace the entire bridge deck and sidewalks, although the method of so doing was left up to Ruhlin as was customary in the construction trade.

The plans submitted by Akron to the state and then submitted by the state to Ruhlin were inaccurate in that the plans showed two sets of reinforcing bars running through the west sidewalk. Relying upon the missing lower reinforcement bars to support the sidewalk, Ruhlin, while dismantling the bridge, purposefully cut the upper set of steel reinforcement bars which extended into the cantilevered concrete section of the west sidewalk. No scaffolding or supports were provided by Ruhlin underneath the sidewalk. With no support from the reinforcing bars, the cantilevered portion of the sidewalk fell onto Interstate 76 below, killing plaintiffs decedents.

The decision to cut the top level of reinforcement bars was made on the job site by two Ruhlin employees, with the approval of Randall Monteith, the Project Supervisor. Chuck Dowling, the Project Inspector, was also aware of the decision to cut the bars and observed Ruhlin employees as this aspect of the job progressed.

Monteith and Dowling were at the job site in order to see that the repair to the Grant Street Bridge was done in accordance with the plans and specifications and in a safe manner. Although their exact status was a matter of controversy in the case, the trial court stated in its findings of fact that:

“Randall Allison Monteith and pharles E. Dowling, regular employees of the City of Akron, were assigned to the Grant Street Bridge Project as ‘loaned employees’ or agents of the Ohio Department of Transportation for the entire period of their service on that project. They were answerable to and received their supervision, instructions and orders from supervisory employees of the Ohio Department of Transportation.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fixel v. LSMJ1, LLC
N.D. Ohio, 2023
CSX Transp., Inc. v. Columbus Downtown Dev. Corp.
307 F. Supp. 3d 719 (S.D. Ohio, 2018)
Goscenski v. Ohio Dept. of Transp.
2014 Ohio 3426 (Ohio Court of Appeals, 2014)
Bach v. Dicenzo, Unpublished Decision (5-26-2005)
2005 Ohio 2611 (Ohio Court of Appeals, 2005)
Allan D. Mills v. River Terminal Railway Company
276 F.3d 222 (Third Circuit, 2002)
Mills v. River Terminal Railway Co.
276 F.3d 222 (Sixth Circuit, 2002)
Nevins v. Ohio Department of Transportation
724 N.E.2d 433 (Ohio Court of Appeals, 1998)
Kunz v. Beneficial Temporaries
921 P.2d 456 (Utah Supreme Court, 1996)
Whitney v. Horrigan
679 N.E.2d 315 (Ohio Court of Appeals, 1996)
Franklin Park Mall, Inc. v. Wtvg, Inc.
655 N.E.2d 1378 (Ohio Court of Appeals, 1995)
Mahathiraj v. Columbia Gas of Ohio, Inc.
617 N.E.2d 737 (Ohio Court of Appeals, 1992)
Schneider National, Inc. v. Holland Hitch Co.
843 P.2d 561 (Wyoming Supreme Court, 1992)
Harris v. Ohio Department of Transportation
614 N.E.2d 779 (Ohio Court of Appeals, 1992)
Westfield Insurance Co. v. Jeep Corp.
562 N.E.2d 912 (Ohio Court of Appeals, 1988)
Philip Morris, Inc. v. Emerson
368 S.E.2d 268 (Supreme Court of Virginia, 1988)
Hartford Accident & Indemnity Co v. J.I. Case Co.
625 F. Supp. 1251 (S.D. Ohio, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
458 N.E.2d 868, 9 Ohio App. 3d 118, 9 Ohio B. 182, 1982 Ohio App. LEXIS 11296, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lattea-v-city-of-akron-ohioctapp-1982.