Cauldwell-Wingate Co. v. State

12 N.E.2d 443, 276 N.Y. 365, 1938 N.Y. LEXIS 1197
CourtNew York Court of Appeals
DecidedJanuary 11, 1938
DocketClaim 21953
StatusPublished
Cited by27 cases

This text of 12 N.E.2d 443 (Cauldwell-Wingate Co. v. State) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cauldwell-Wingate Co. v. State, 12 N.E.2d 443, 276 N.Y. 365, 1938 N.Y. LEXIS 1197 (N.Y. 1938).

Opinions

Crane, Ch. J.

On or about March 1,1928, Cauldwell-Wingate Company entered into a contract with the State of New York, through the State Office Site and Building Commission, for the construction of a superstructure, State Office Building, New York city, specification No. 5014, project No. 1936, and addenda 1, 2 and 3, which contract was completed and the construction accepted by the State of New York, on or about January 20, 1930. The completion date provided for in said contract was March 31, 1929.

*370 The State had advertised for, and awarded, two separate contracts; one, for the excavation and foundation work; and the other, for the erection of the superstructure. The contract of J. L. McDonald for the foundations was approved by the State on March 10, 1928. The Cauldwell-Wingate contract for the superstructure was approved March 2,1928.

The Cauldwell-Wingate Company could not begin the superstructure work until McDonald had finished the foundations; consequently, the contract contained the following provision:

“ (B) General Description, page 3, paragraph 3.
“Work not included: The work of this contract is contingent upon the execution of the foregoing work by the Foundation Contractor and shall follow said work in orderly sequence. * * * The time of completion specified for the foundation work is July 1, 1928.”

What was meant by the “ execution of the foregoing work by the Foundation Contractor? ” The plans and specifications for this work were submitted to these contractors before bidding, and for the purpose of procuring bids thereon. These were the representations made by the State as to the nature of the_foundation, and the work which the foundation company was expected to do, in accordance with its bid thereon. At the time of the advertising for, and of the letting of, each of these two contracts, the site consisted of a city block, the area of which was graded over and entirely covered with a cinder fill, except a small portion, which was occupied by two small brick buildings. The foundation plans and specifications which were furnished Cauldwell-Wingate Company and other bidders on the superstructure “ for information pertaining to work included in the foundation contract ” showed the elevation and the artificial structures to be removed and only represented thereon the aforesaid two small brick buildings. The superstructure was to be built on a finished foundation to be constructed by the State.

*371 The judge, in his opinion in this case, has found: The plans furnished McDonald by the State included a cross section and showed ‘ the elevation and artificial structures to be removed and only represented thereon the aforesaid two buildings.’ ”

This provision (B), general description in the CauldweE-Wingate contract, stating, The work of this contract is contingent upon the execution of the foregoing work by the Foundation Contractor and shaE foEow said work in orderly sequence,” has reference to this foundation work shown in these plans and specifications submitted to aE of the contractors for the purpose of bidding. This point is to be noted as we go along, as it is decisive of the questions presented.

The contract read as a whole meant this: McDonald was to dig and construct the foundations according to the plans and specifications submitted. No superstructure work could be commenced untE the foundation was complete. CauldweE-Wingate Company made its contract to erect the superstructure upon the completion of the foundation, according to the plans and specifications submitted to it. These plans and specifications caEed for work which could be completed in about three weeks, and so it was stated in the specifications that the foundation work would be completed July 1, 1928. AE the bidding, both by the foundation contractor and the superstructure contractor, was based upon the plans and specifications submitted by the State’s engineers — the servants and employees of the State — and aE of the conditions in the contracts of these two parties must be read, bearing this fact in mind.

What was the superstructure contractor to do immediately upon signing this contract? It was expected to assemble aE of its material and working equipment, including the fabrication of the steel, so as to have everything in readiness to proceed on July 1, 1928. It was under severe penalties for delay. The contract aEowed nine months to erect the entire superstructure, after the *372 dates specified for completion of the foundations, and obligated it to the payment of liquidated damages and severe penalties for delay, or failure to complete within the specified time. The Cauldwell Company, by the contract provision above quoted, accepted the contingency of delay in the execution of the foundation contract, but only such delay as was occasioned in the performance of that contract, according to plans and specifications. The plans and specifications were its only guide, and the measure alike of its duty and its obligations. If the foundation contractor were delayed in doing its work, the Cauldwell Company assumed such risk. It did not, however, by any provisions of its contract, assume the risk and loss occasioned by the act of the State, in furnishing to both these contractors misleading, imperfect and defective plans and specifications, wherein and whereby the whole scheme of foundation building had to be revised, new plans and specifications adopted, and the work which was to take three weeks necessarily extended for almost a year. Instead of a surface such as represented, there appeared upon further investigation an underground swamp or pond and other obstacles.

The Court of Claims was under the impression that the contractor for the superstructure was bound to make borings to discover the nature of the subsoil, and should have been aware of these conditions. We can find no such onerous duty placed upon this contractor. The information to bidders, entitled, “ Visit to Site,” leads to no such conclusion. This reads: “ Proposals will be held as having been made with full knowledge of conditions and requirements. The Contractor will be held to have visited the premises, prior to the time of submitting his proposal, and to have appraised the conditions under which the work of this contract is to be executed.” Very unreasonable indeed would it be to hold that a contractor, whose only work commenced when the foundations were finished, was obliged to make soundings and borings to discover whether the plans and specifications of the State *373 regarding such foundations were true or false. Whether this were McDonald’s duty we need not now determine. Certainly it was no obligation resting upon the superstructure contractor. This apparently was the main argument for rejecting Cauldwell’s claim for damages in this case. The Court of Claims made these findings: “ That the subsurface of the contract site was found to consist of old foundations, piling and obstructions not shown upon the plans or specifications. That a portion of such old structures had been erected in former days over a pond which once had water to a depth of about fifty feet.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Corinno Civetta Construction Corp. v. City of New York
493 N.E.2d 905 (New York Court of Appeals, 1986)
J. R. Stevenson Corp. v. County of Westchester
113 A.D.2d 918 (Appellate Division of the Supreme Court of New York, 1985)
Kalisch-Jarcho, Inc. v. City of New York
448 N.E.2d 413 (New York Court of Appeals, 1983)
Gottlieb Contracting, Inc. v. City of New York
86 A.D.2d 588 (Appellate Division of the Supreme Court of New York, 1982)
Alvord & Swift v. Stewart M. Muller Construction Co.
385 N.E.2d 1238 (New York Court of Appeals, 1978)
Twin Village Construction Corp. v. State
64 A.D.2d 866 (Appellate Division of the Supreme Court of New York, 1978)
Vanderlinde Electric Corp. v. City of Rochester
54 A.D.2d 155 (Appellate Division of the Supreme Court of New York, 1976)
Buckley & Co., Inc. v. State
356 A.2d 56 (New Jersey Superior Court App Division, 1975)
County Asphalt, Inc. v. State
40 A.D.2d 26 (Appellate Division of the Supreme Court of New York, 1972)
Rusciano Construction Corp. v. State
37 A.D.2d 745 (Appellate Division of the Supreme Court of New York, 1971)
Tully & Di Napoli, Inc. v. State
34 A.D.2d 439 (Appellate Division of the Supreme Court of New York, 1970)
Peckham Road Co. v. State
32 A.D.2d 139 (Appellate Division of the Supreme Court of New York, 1969)
Grant Construction Co. v. Burns
443 P.2d 1005 (Idaho Supreme Court, 1968)
Johnson, Drake & Piper, Inc. v. State
29 A.D.2d 793 (Appellate Division of the Supreme Court of New York, 1968)
Norman Co. v. County of Nassau
27 A.D.2d 936 (Appellate Division of the Supreme Court of New York, 1967)
M. L. Shalloo, Inc. v. Ricciardi & Sons Construction, Inc.
205 N.E.2d 239 (Massachusetts Supreme Judicial Court, 1965)
L. I. Waldman & Co. v. State
11 A.D.2d 845 (Appellate Division of the Supreme Court of New York, 1960)
McCree & Company v. State
91 N.W.2d 713 (Supreme Court of Minnesota, 1958)
Endres Plumbing Corp. v. State
198 Misc. 546 (New York State Court of Claims, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
12 N.E.2d 443, 276 N.Y. 365, 1938 N.Y. LEXIS 1197, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cauldwell-wingate-co-v-state-ny-1938.