Gottlieb Contracting, Inc. v. City of New York

86 A.D.2d 588, 446 N.Y.S.2d 311, 1982 N.Y. App. Div. LEXIS 15112
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJanuary 28, 1982
StatusPublished
Cited by12 cases

This text of 86 A.D.2d 588 (Gottlieb Contracting, Inc. v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gottlieb Contracting, Inc. v. City of New York, 86 A.D.2d 588, 446 N.Y.S.2d 311, 1982 N.Y. App. Div. LEXIS 15112 (N.Y. Ct. App. 1982).

Opinion

Judgment, Supreme Court, New York County (Graves, J.), entered on September 24, 1980, awarding plaintiff $35,808.24 after trial without a jury, unanimously reversed, on the law, without costs or disbursements, and the complaint dismissed. After competitive bidding plaintiff was awarded the electrical contract in connection with the rehabilitation of the Hamilton Grange Branch Library, a landmark building located on 145th Street in Manhattan. The contract price was $127,480. The contract contained exculpatory clauses which, in essence, absolved the city from any liability for damages suffered by the contractor if delayed in the performance of its work by any act or omission of the city or any other contractor having a contract with the city for the performance of work upon the site. The project was to be completed no later than July 21,1974. As a result of delays, however, plaintiff was unable to [589]*589finish until July 31, 1975. The work was not accepted until February, 1976. Work which should have been performed in 3,100 man hours took 4,200 man hours. Plaintiff commenced this action against the city for the recovery of damages allegedly incurred by reason of the delays in completing its work. Plaintiff contends that these delays were caused solely by the city’s failure to make suitable work sites available, to procure performance by the other contractors according to schedule, to provide adequate plans and specifications, and to supervise and co-ordinate the project properly; and by the city’s issuance of excessive change orders to the other prime contractors upon whose work progress plaintiff’s performance depended. The city interposed the exculpatory clauses as affirmative defenses. Trial Term held the city liable for plaintiff’s delay damages, notwithstanding the exculpatory provisions in the contract, and despite its finding that “the City may not have actively or wrongfully interfered with plaintiff’s work”. The complaint should have been dismissed. The rule in this State is that “[i]f the delay or obstruction is within the contemplation of the parties at the time the contract is entered into the ‘no damage’ clause will be valid and enforceable unless the delay was caused by conduct constituting active interference with the contractor’s performance”. (Peckham Road Co. v State of New York, 32 AD2d 139, 141-142, affd 28 NY2d 734; see Cauldwell-Wingate Co. v State of New York, 276 NY 365, at p 375.) On this record it is clear to us that all of the delay, except for a 10-week period chargeable to plaintiff, was the result of the other prime contractors’ inaction, faulty performance and defaults under their contracts, types of delay which are precisely within the contemplation of the exculpatory clauses. Since the delays complained of were within the contemplation of the parties at the time the contract was entered and since the delay was not, as Trial Term properly found, caused by the active interference of the city, plaintiff’s delay damage claims against it are barred. Concur — Sullivan, J. P., Ross, Carro, Silverman and Bloom, JJ.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tutor Perini Corp. v. State Univ. Constr. Fund
2025 NY Slip Op 52062(U) (New York Supreme Court, Albany County, 2025)
Tougher Industries, Inc. v. Dormitory Authority
130 A.D.3d 1393 (Appellate Division of the Supreme Court of New York, 2015)
LoDuca Associates, Inc. v. PMS Construction Management Corp.
91 A.D.3d 485 (Appellate Division of the Supreme Court of New York, 2012)
Plato General Construction Corp./EMCO Tech Construction Corp. JV, LLC v. Dormitory Authority
89 A.D.3d 819 (Appellate Division of the Supreme Court of New York, 2011)
Travelers Casualty & Surety Co. v. Dormitory Authority-State
735 F. Supp. 2d 42 (S.D. New York, 2010)
Corinno Civetta Construction Corp. v. City of New York
493 N.E.2d 905 (New York Court of Appeals, 1986)
Honeywell, Inc. v. City of New York
108 A.D.2d 125 (Appellate Division of the Supreme Court of New York, 1985)
Novak & Co. v. New York City Housing Authority
108 A.D.2d 612 (Appellate Division of the Supreme Court of New York, 1985)
Novak & Co. v. New York City Housing Authority
125 Misc. 2d 647 (New York Supreme Court, 1984)
Gottlieb Contracting, Inc. v. City of New York
449 N.E.2d 422 (New York Court of Appeals, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
86 A.D.2d 588, 446 N.Y.S.2d 311, 1982 N.Y. App. Div. LEXIS 15112, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gottlieb-contracting-inc-v-city-of-new-york-nyappdiv-1982.