NASDI LLc v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV)

CourtDistrict Court, S.D. New York
DecidedSeptember 28, 2020
Docket1:17-cv-03578
StatusUnknown

This text of NASDI LLc v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV) (NASDI LLc v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV)) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NASDI LLc v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV), (S.D.N.Y. 2020).

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK -------------------------------------- X : NASDI LLC, : : Plaintiff, : 17cv3578 (DLC) : -v- : OPINION AND ORDER : SKANSKA KOCH INC. KIEWIT : INFRASTRUCTURE CO. (JV) d/b/a SKANSKA : KIEWIT JV, : : Defendant. : : -------------------------------------- X

APPEARANCES

For plaintiffs: Mark L. McAlpine Douglas W. Eyre Thomas H. Trapnell McAlpine PC 3201 University Drive, Ste 100 Auburn Hills, MI 48326

For defendants: Paul Monte Melissa Salsano Peckar & Abramson, P.C. 41 Madison Avenue 20th Floor New York, NY 10010

DENISE COTE, District Judge: Plaintiff NASDI LLC (“NASDI”) worked as a subcontractor for defendant Skanska Koch Inc. Kiewit Infrastructure Co. (JV) (“SKK”) on the demolition and reconstruction of a bridge between New York and New Jersey (the “Project”). Days before the final stage of the Project was to begin, NASDI walked off the Project, citing SKK’s refusal to pay additional costs NASDI demanded due to the delay in commencing that final stage of the Project. NASDI now brings this action to recover the excess costs it

asserts it sustained during the early phases of the Project and for various Project delays. It is largely undisputed, however, that NASDI failed to comply with the notice and claim procedure in its agreement with SKK (the “Subcontract”). Therefore, in addition to its breach of contract claim, NASDI also asserts that SKK had abandoned the Subcontract through making substantial changes to the Project and that NASDI is therefore entitled to recover its costs on a theory of quantum meruit. NASDI also pursues a claim that, just before NASDI walked off the Project, SKK breached the covenant of good faith and fair dealing imposed by the Subcontract. SKK has responded with counterclaims against NASDI for

breach of contract and for indemnification. This Opinion resolves SKK’s motion for summary judgment on NASDI’s claims and on SKK’s counterclaim for breach of contract. For the following reasons SKK’s motions are granted. Background The following facts are undisputed or taken in the light

most favorable to NASDI, unless otherwise noted. In 2013, the Port Authority of New York & New Jersey (the “PA”) selected SKK as its general contractor to reconstruct the Bayonne Bridge, which connects Staten Island, New York to Bayonne, New Jersey. The PA and SKK executed their agreement in April 2013 (the

“Prime Contract”). The Subcontract SKK executed the Subcontract with NASDI in July 2013. NASDI was to perform the demolition work on the Project and receive a total payment of $20,359,375. Pursuant to §4.2, that sum would distributed in a series of “Progress Payments” made “pursuant to payment applications to be submitted by Subcontractor to Contractor, for the value of Subcontractor’s Work completed during each prior Payment Period as jointly estimated by Subcontractor and Contractor, using a mutually agreed upon Price Breakdown.” Section 5 of the Subcontract acknowledged SKK’s control

over the schedule for the Project. It provides: 5. SCHEDULING AND PROSECUTION OF THE WORK. . . . Subcontractor agrees to proceed with the determinations of Contractor as to the times when and locations where Subcontractor’s work shall be performed in order to coordinate same with other Work consistent with the overall intent of the Progress Schedule. Contractor does not assure Subcontractor that it shall be able to commence, prosecute or complete its Work at the time stated, or in the sequence, manner or durations provided for in any Progress Schedule, or that the entire Work shall be completed at the time fixed in such Progress Schedule. A reasonable number of multiple come-backs, and of multiple or partial punch lists are anticipated and allowed for by Subcontractor in the Subcontract Price. Subcontractor’s completion of its Work within the Prime Contract time for completion of the Work, AND the Progress Schedule, AND WITHIN any interim PRIME CONTRACT milestones applicable to its WORK, AND subcontractor’s cooperation with Contractor’s efforts to schedule and coordinate the Prime Work, ARE of the essence of this Subcontract.

(emphasis in original).

Appendix A to the Subcontract set forth a number of target dates by which NASDI was to complete its work. The Appendix indicated that these dates were provisional because the overall schedule for the Project had not been finalized. SKK did not share the overall schedule for the Project with NASDI prior to NASDI executing the Subcontract. Pursuant to §6 of the Subcontract, entitled “Changes and Extras,” SKK could “at any time order or require changes in Subcontractor’s Work consisting of additions, deletions or other revisions, with the Subcontract Price being adjusted accordingly (“Change Order”).” Section 6.1.1 details the payment procedure for “changes in the Work that have been initiated by the [PA].” If the PA is the source of NASDI’s change in work, NASDI is directed to promptly submit any Claims it may have . . . in sufficient time to allow [SKK] to process such Claims, credits or deductions with the [PA] within the time and in the manner provided for in the Prime Contract. Where the changes are “not initiated or payable to” SKK by the PA, §6.1.2 made compensation to NASDI “payable pursuant to separate written agreement.”

Under §6.4, the failure of NASDI “to immediately commence performance of any Change Order” when directed to do so is a “material breach” of the Subcontract. Where SKK and NASDI have not agreed upon the additional compensation due following a change, NASDI “may reserve its rights to extra compensation . . . by delivering to [SKK] written notice of a Claim therefor pursuant to Section 7, or 23,[1] whichever may apply, prior to the commencement of any extra work.” Section 7 of the Subcontract provides the procedure for NASDI to make “Claims.” The Subcontract defines a “claim” broadly as “any request, demand, or claim for, extra or additional compensation in money, extension of time . . . or

other relief arising under or relating to the Subcontract.” Section 7.1 sets forth the notice and documentation requirements for NASDI to make a claim:

1 Section 23 applies, inter alia, to a claim by NASDI “of a type or character not addressed elsewhere in this Subcontract.” It also includes choice of law and forum provisions and contains a waiver by NASDI for “any claim for special, incidental, consequential or penal damages.” As a condition precedent to a suit for damages, NASDI must comply “with all the notice provision of this Subcontract applicable to such item of Claim or damage.” 7.1 NOTICE OF CONDITION. Unless a shorter time limit is required under the Prime Contract, within twenty- four (24) hours after the commencement of any condition claimed to be grounds for a Claim, Subcontractor shall give Contractor a written statement of any such condition, together with the particulars of time and money claimed and the reason(s) therefor, and thereafter submit updates of such particulars to Contractor from time to time not more than thirty (30) days after any further such costs or losses of time are incurred.

Section 7.3 affirms that such notice was to be strictly observed: 7.3 STRICT COMPLIANCE. Without limitation, strict compliance with all of the terms of this Section and all other “notice” provisions of or incorporated into this Subcontract is a condition precedent to the assertion by Subcontractor of Claims or suits of any kind. The failure of Subcontractor to timely and strictly comply with the requirements of this Section 7 will be conclusively deemed to be a waiver by Subcontractor of, and will relieve Contractor of all responsibility to present or pay for, any such Claim or dispute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Riegel v. Medtronic, Inc.
451 F.3d 104 (Second Circuit, 2006)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Eastman Kodak Co. v. Image Technical Services, Inc.
504 U.S. 451 (Supreme Court, 1992)
Continental Insurance v. Atlantic Casualty Insurance
603 F.3d 169 (Second Circuit, 2010)
Ridinger v. Dow Jones & Co. Inc.
651 F.3d 309 (Second Circuit, 2011)
Topps Co., Inc. v. Cadbury Stani SAIC
526 F.3d 63 (Second Circuit, 2008)
Wright v. Goord
554 F.3d 255 (Second Circuit, 2009)
Dalton v. Educational Testing Service
663 N.E.2d 289 (New York Court of Appeals, 1995)
Crawford v. Franklin Credit Management Corp.
758 F.3d 473 (Second Circuit, 2014)
Raymond Smith v. County of Suffolk
776 F.3d 114 (Second Circuit, 2015)
Gemmink v. Jay Peak Inc.
807 F.3d 46 (Second Circuit, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
NASDI LLc v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV), Counsel Stack Legal Research, https://law.counselstack.com/opinion/nasdi-llc-v-skanska-koch-inc-kiewit-infrastructure-co-jv-nysd-2020.