Plato General Construction Corp./EMCO Tech Construction Corp. JV, LLC v. Dormitory Authority

89 A.D.3d 819, 932 N.Y.2d 504
CourtAppellate Division of the Supreme Court of the State of New York
DecidedNovember 9, 2011
StatusPublished
Cited by19 cases

This text of 89 A.D.3d 819 (Plato General Construction Corp./EMCO Tech Construction Corp. JV, LLC v. Dormitory Authority) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Plato General Construction Corp./EMCO Tech Construction Corp. JV, LLC v. Dormitory Authority, 89 A.D.3d 819, 932 N.Y.2d 504 (N.Y. Ct. App. 2011).

Opinion

[820]*820The plaintiff commenced this action to recover damages for delays in the construction of the Brooklyn College Library, which involved the gut renovation of two existing buildings and construction of an addition. The defendant, Dormitory Authority of the State of New York (hereinafter DASNY), as agent for the owner, City University of New York (hereinafter CUNY), entered into a contract with Turner Construction Company (hereinafter Turner), which is not a party to this action, whereby Turner agreed to act as construction manager, “[e]xpedite and coordinate the work of all Contractors,” and prepare a schedule for the project.

On May 20, 1999, DASNY entered into a contract with the plaintiff, Plato General Construction Corp./EMCO Tech Construction Corp. (hereinafter Plato), as prime general contractor, to perform general construction work for [821]*821$19,902,000. The contract between DASNY and Plato set the date of completion as March 20, 2001, and required Plato to pay liquidated damages of $1,000 per day for “each and every day that [Plato] shall be in default after the above time of completion.”

Pursuant to the “General Requirements” of the contract, the owner’s agent, DASNY, was required to provide a “Critical Path Method” (hereinafter CPM) schedule, but Plato was obligated to cooperate with Turner in the development, implementation, and updating of the CPM schedule. Section 13.01(A) of the “General Conditions” of the contract provided: “During the progress of the Work, other contractors may be engaged in performing work. The Contractor [Plato] shall coordinate the Contractor’s Work with the work of other contractors in such a manner as the Owner may direct.”

Section 11.02 of the “General Conditions” contained a no-damages-for-delay clause which stated: “No claims for increased costs, charges, expenses or damages of any kind shall be made by the Contractor against the Owner for any delays or hindrances from any cause whatsoever; provided that the Owner, in the Owner’s discretion, may compensate the Contractor for any said delays by extending the time for completion of the Work as specified in the Contract.” Section 13.01(D) provided: “Should the Contractor sustain any damage through any act or omission of any other contractor having a contract with the Owner or through any act or omission of any Subcontractor of said other contractor, the Contractor shall have no claim against the Owner for said damage.” Section 20.15 provided that Plato could not cancel the contract based upon DASNY’s breach thereof, and waived “any and all rights and remedies to which” Plato “might otherwise be or become entitled to because of any wrongful act or omission” of DASNY, except Plato’s right to damages. Provisions were made in the contract for changes and extra work.

In May 1999 Turner provided a schedule to Plato. Plato was to review and make any necessary changes in the schedule. Plato provided its CPM schedule on June 10, 1999.

Delays in the project were attributed to a number of causes. Consolidated Edison Company (hereinafter Con Edison) was installing “chiller lines” to run alongside the site; installation was to take 30 days, but was not completed for six months, interfering with demolition and construction for at least some of that period. Although the contract provided that Plato would have “[c]omplete access to the site after June 1999,” the library was not completely vacated until October 5, 1999. The contract [822]*822for heating, ventilation, and air conditioning (hereinafter HVAC) was not awarded until August 19, 1999, but the selected HVAC contractor, Precision Mechanical, Inc. (hereinafter Precision), was removed from the project on December 6, 1999, by mutual agreement, because it could not meet deadlines or provide a schedule for its portion of the project. Precision was replaced in January 2000 with Roy Kay, Inc. (hereinafter RKI).

RKI had to provide drawings redesigning the duct work system because the original design based upon DASNY’s engineer’s drawings was not sufficient to maintain sufficient airflow through the buildings and was not field-verified as to the height of existing beams. Plato claimed that the plans prepared by DASNY’s architect were also defective for failing to identify all of the asbestos in the walls, resulting in additional asbestos abatement work which delayed demolition.

Completion of the project was delayed by Plato’s failure to complete brickwork in a timely manner, as well as the fact that Plato’s subcontractors would not or could not complete their work, requiring Plato to perform much of the interior finishing work itself. Occupancy of the library was not turned over to Brooklyn College until August 28, 2002, 526 days after the contract completion date of March 20, 2001.

Plato commenced this action on March 30, 2005, to recover, inter alia, $15,834,257.41. DASNY counterclaimed for liquidated damages of $1,000 per day for 411 days, constituting the period from the March 20, 2001, the date the project originally was to have been completed, until August 28, 2002, the date the project was substantially completed, less a 115-day extension of time granted by DASNY.

After a nonjury trial, the Supreme Court, in a written decision (see Plato Gen. Constr. Corp. v Dormitory Auth. of the State of N.Y., 27 Misc 3d 1226[A], 2010 NY Slip Op 50916[U] [2010]), determined that DASNY could not rely on the no-damages-for-delay clause in the contract, because DASNY had waived that clause. The Supreme Court found, inter alia, that DASNY breached the contract by failing to fulfill its duty of scheduling and coordination of the work, failing to have an HVAC contractor in place at the beginning of the project, failing to notify the other contractors of a redesign of the HVAC system, and failing to remove all books from the library, delaying full access to the site until October 1999. The Supreme Court found that uncontemplated delays were incurred, among other things, by Con Edison’s excavation for the chiller line, and the fact that additional asbestos was found in the walls. However, the Supreme Court also found that Plato was responsible for some [823]*823of the delay because of errors in masonry work, and the fact that virtually none of its subcontractors completed their tasks. Based upon its findings, the Supreme Court found that DASNY was responsible for 66% of the 526-day delay from March 20, 2001, until August 28, 2002, and Plato was responsible for the remaining 34% of that delay (179 days).

Since this case involves a nonjury trial, the authority of the Appellate Division “is as broad as that of the trial court . . . and ... it may render the judgment it finds warranted by the facts, taking into account in a close case ‘the fact that the trial judge had the advantage of seeing the witnesses’ ” (Northern Westchester Professional Park Assoc. v Town of Bedford, 60 NY2d 492, 499 [1983], quoting York Mtge. Corp. v Clotar Constr. Corp., 254 NY 128, 133-134 [1930]; see DePaula v State of New York, 82 AD3d 827 [2011]; Bryant v State of New York, 77 AD3d 875, 875-876 [2010]). The question of whether the no-damages-for-delay clause is applicable here involves questions of law and fact.

The purpose of a no-damages-for-delay clause is to “extend acceptability to a range of unreasonable delay” by the contractee (in this case DASNY) (see Kalisch-Jarcho, Inc. v City of New York, 58 NY2d 377, 384 [1983]). However, as is true of contracts generally, implicit in such a provision is “the obligation of fair dealing” (id.).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tutor Perini Corp. v. State Univ. Constr. Fund
2025 NY Slip Op 52062(U) (New York Supreme Court, Albany County, 2025)
Henick-Lane, LLC v. Stellar Mgt. Group, Inc.
2025 NY Slip Op 05190 (Appellate Division of the Supreme Court of New York, 2025)
Matter of Centurion Cos., Inc. v. Bowne Tech Constr. Corp.
2025 NY Slip Op 04246 (Appellate Division of the Supreme Court of New York, 2025)
Gamma USA, Inc. v. Pavarini McGovern, LLC
2025 NY Slip Op 03380 (Appellate Division of the Supreme Court of New York, 2025)
Matter of Owen Steel Co., Inc. v. City Univ. of N.Y.
2025 NY Slip Op 00920 (Appellate Division of the Supreme Court of New York, 2025)
Hudson Meridian Constr. Group LLC v. Bayport Constr. Corp.
2024 NY Slip Op 03383 (Appellate Division of the Supreme Court of New York, 2024)
Five Star Elec. Corp. v. A.J. Pegno Constr. Co., Inc./Tully Constr. Co., Inc.
198 N.Y.S.3d 340 (Appellate Division of the Supreme Court of New York, 2023)
Stonewall Contr. Corp. v. Long Is. Rail Rd. Co.
2020 NY Slip Op 4505 (Appellate Division of the Supreme Court of New York, 2020)
Iannucci v. Kucker & Bruh, LLP
2018 NY Slip Op 3514 (Appellate Division of the Supreme Court of New York, 2018)
Sunoce Properties, Inc. v. Bally Total Fitness of Greater New York, Inc.
2017 NY Slip Op 1586 (Appellate Division of the Supreme Court of New York, 2017)
Schindler Elevator Corp. v. Tully Construction Co.
139 A.D.3d 930 (Appellate Division of the Supreme Court of New York, 2016)
J. Petrocelli Contracting, Inc. v. Morganti Group, Inc.
137 A.D.3d 1082 (Appellate Division of the Supreme Court of New York, 2016)
Sher v. RBC Capital Markets, LLC
539 B.R. 260 (D. Maryland, 2015)
Tougher Industries, Inc. v. Dormitory Authority
130 A.D.3d 1393 (Appellate Division of the Supreme Court of New York, 2015)
Matter of Georgetown Unsold Shares, LLC v. Ledet
130 A.D.3d 99 (Appellate Division of the Supreme Court of New York, 2015)
Joy Builders, Inc. v. Town of Clarkstown
127 A.D.3d 1029 (Appellate Division of the Supreme Court of New York, 2015)
Kleinberg Electric, Inc. v. E-J Electric Installation Co.
111 A.D.3d 410 (Appellate Division of the Supreme Court of New York, 2013)
Amerex Group, Inc. v. Lexington Insurance
678 F.3d 193 (Second Circuit, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
89 A.D.3d 819, 932 N.Y.2d 504, Counsel Stack Legal Research, https://law.counselstack.com/opinion/plato-general-construction-corpemco-tech-construction-corp-jv-llc-v-nyappdiv-2011.